§ 19.6-97 Utility Scale Solar Energy Farm.

[Adopted 6-15-2020; amended 11-16-2020; 10-16-2022; 3-16-2026]

§ 19.6-97.1 Applicability, permitting.

The requirements set forth in this § 19.6-97 govern the siting, development, construction, installation, operation, and decommissioning of utility scale solar energy facilities in the county. A Conditional Use Permit (CUP) is required for each utility scale solar energy farm proposed to be constructed, installed, or operated in the county. Small scale solar energy arrays and associate apparatus used for individual residential dwellings, not connected to the electrical grid, shall be considered an accessory use to the principal dwelling and permitted as such. A Battery Energy Storage Facility may be constructed in association with a Utility Scale Solar facility with a Conditional Use Permit. A Battery Energy Storage Facility constructed in association with an electrical substation, wholly contained within the secure perimeter of the substation or immediately adjacent on property owned by the utility company, shall not constitute a separate land use and therefore is not subject to the Conditional Use Permit requirement. A standalone Battery Energy Storage Facility is not permitted in any zoning district.

§ 19.6-97.2 Applications and required information for a utility scale solar energy farm.

In addition to the material required for a Conditional Use Permit petition, applications for utility scale solar energy facilities (farms) and/or Battery Energy Storage Facilities associated with Utility Scale Solar Energy Facilities shall include the following information:
A. 
Project Narrative: A narrative identifying the applicant, facility owner, property owner, and the operator of the facility. The narrative should include an overview of the project and its location, the size of the site and the project area; the current use of the site, the estimated time for construction, including a proposed date for commencement of construction; the maximum rated capacity of the facility; the approximate number, types and expected footprint of the solar and/or battery storage equipment to be constructed to include photovoltaic panels, ancillary facilities, fencing, buffering, where the electricity generated at the facility will be transmitted, and the location of the proposed electrical grid interconnection.
B. 
Site Development Plan: A site development plan of a scale and specification, in accordance with the requirements found in the Conditional Use Permit application shall be submitted with the application. Additional information may be required, as determined by the Zoning Administrator, such as scaled elevation view or other supporting drawings, photographs of the site, photographic simulations or modeling of the proposed solar energy facility, specifically from sensitive locations, as deemed necessary by the Zoning Administrator, aerial imagery or other mapping of the site or any other technical report necessary for the proper review of the Conditional Use Permit petition. If the petition is granted, then a full site development plan shall be required in accordance with the regulations found elsewhere in this article. Additional required information and/or studies to be submitted at the time of Conditional Use Permit application:
(1) 
A natural heritage and wildlife management study, consistent with the Virginia Division of Wildlife Resources Solar Energy Facility Guidance that identifies any threatened or endangered species and wildlife travel patterns, together with any necessary mitigation measures to ensure compatibility of the project.
(2) 
Virginia Cultural Resource Information System report. A report by the Virginia Department of Historic Resources, Virginia Cultural Resource Information System, must be submitted to identify historical, architectural, archeological, or other cultural resources on or near the proposed facility. A copy of the cultural resources review conducted in conjunction with the Virginia Department of Historic Resources for the permit by rule process shall be submitted by the applicant prior to issuance of a building permit, shall be in addition to the initial report required above, and shall further identify historical, architectural, archeological, or other cultural resources on or near the proposed facility.
(3) 
A Construction Plan to be approved prior to the issuance of a Building Permit, which shall include a proposed construction schedule, proposed hours of construction, and how the applicant plans to effectively mitigate dust, noise, and other nuisances commonly associated with large construction projects.
(4) 
A Glint and Glare Study. This study shall demonstrate either that the panels will be sited, designed, and installed to eliminate glint and glare effects on roadway users, nearby residences, commercial areas, or other sensitive areas. The applicant will use reasonably available mitigation techniques to reduce glint and glare to the lowest achievable levels. The study will assess and quantify potential glint and glare effects and address potential health, safety, and visual impacts associated with glint and glare. Any such assessment must be conducted by qualified individuals using appropriate and commonly excepted engineering methods.
(5) 
A Water Resource Plan. This plan shall identify the availability of and proposed usage of private and/or public water and sewer services. This plan shall include a plan for continuous monitoring of groundwater quality during the life of the facility. Monitoring stations shall be placed within 50 feet of any property line adjacent to existing residential uses. Monitoring Stations shall be placed at a minimum of one station per 500-foot interval. For Utility-Solar projects, the applicant shall submit annual monitoring reports to the Zoning Administrator throughout the life cycle of the project. For Battery Energy Storage Facility projects, the applicant shall provide baseline groundwater quality information prior to commencement of construction, then the applicant shall submit monitoring reports once every three years, starting from the time the Certificate of Occupancy is issued, to the Zoning Administrator throughout the life cycle of the project.
(6) 
Fire, Rescue, Law Enforcement (Emergency Services) assessment. Applicant shall submit a detailed assessment of impacts to local Fire, Rescue and Law Enforcement and any mitigation techniques that will be used to reduce these impacts. Specifically, the assessment should detail training of local resources and methods to be used in the event of a fire or accident requiring local emergency services response, specifically addressing fire, rescue, and emergency services access to the site.
(a) 
Facility shall have a monitoring system for continuous 24-hour/7-days-a-week automated fire detection.
(b) 
National Fire Protection Association (NFPA) 855 signage requirements shall be utilized along signage with emergency contact information placed in a high-visibility location near the entrance to the facility.
(c) 
Emergency Services personnel shall be provided with a key, code, or other means (e.g., Knox-Box®) to access the property in the event of an emergency.
C. 
Documentation of right to use property for the proposed facility: Documentation shall include proof of control over the proposed site or possession of the right to use the proposed site in the manner requested. Any sensitive financial or confidential information may be redacted.
D. 
Decommissioning plan for Utility-Scale Solar Energy Farm; security.
(1) 
The applicant shall provide a detailed decommissioning plan that provides procedures and requirements for removal of all parts of the solar energy generation facility and its various structures, and any and all hazardous residuals found to be present in the environment, confirmed by pre- and post-development contamination testing, at the end of the useful life of the facility or if it is deemed abandoned or unsafe. The plan shall include the location, size, number, and type of PV modules; identification of any per- and polyfluoroalkyl substances (PFAS) associated with the project; whether the PV modules are likely to be characterized as hazardous waste upon decommissioning; and certifications that: (i) no child or forced labor have contributed to the manufacturing of any component of the project; and (ii) no decommissioned component will be disposed of in any landfill, current or future, or transfer station, current or future, located within Appomattox County. The plan shall include the anticipated life of the facility, the estimated overall cost of decommissioning the facility in current dollars, the methodology for determining such estimate, and the manner in which the project will be decommissioned. The decommissioning plan and the estimated decommissioning cost shall be update every five years, from the date of the certificate of occupancy or upon request of the Zoning Administrator; however, the updated costs shall be no more than twice every 10 years. Estimated decommission costs shall be for the total cost of restoration and shall not exclude net salvage value of the facility's equipment, devices, panels, wiring, steel support structures, concrete or any other improvement. Additionally, the estimated decommission costs shall include a reasonable allowance for the estimated administrative costs related to a default of the owner, lessee, or developer, and include an annual inflation factor that will ensure the return of the property to its pre-development land use.
(2) 
Security: Prior to receiving a certificate of occupancy to begin operation, the applicant must provide security, with the County as primary oblige and all participating landowners serving as additional obliges, in the amount of the estimated cost of the decommissioning. Options for security shall include a cash escrow, Certified check(s), or an Irrevocable Letter of Credit. The security must remain valid until the decommissioning obligations have been met and no surety instrument will be released until another is deemed acceptable, as a substitution. The security may be adjusted up or down by the County if the estimated cost of decommissioning the facility changes. The security must be renewed or replaced, if necessary, to account for any changes in the total estimated cost of decommissioning if deemed by the updated estimates. Security is a mandatory condition of all conditional use permits for utility scale solar energy farms.
(3) 
The Operator and Lessor must provide a Parent Company Guarantee (PCG), otherwise known as a downstream guarantee, in a form and substance reasonably acceptable to the County Attorney, ensuring fulfillment of any financial obligations related to the decommissioning and clean-up of the project that is not paid in full by the cash escrow, Certified Check(s) or Irrevocable Letter of Credit. The Parent Company Guarantee must be provided prior to the issuance of any permit or approval for said project. A draft version of the Parent Company Guarantee shall be submitted as part of the Conditional Use Permit application or site plan review process for a Battery Energy Storage Facility associated with an electrical substation. The Parent Company Guarantee must clearly outline the financial obligations covered, including but not limited to, the costs of removing all equipment, restoring the land, and any environmental remediation required. The Parent Company Guarantee must include a provision that is binding upon the Operator and the Lessor and any successors or assigns. Failure to provide the required Parent Company Guarantee shall result in the suspension of any proceedings and/or approval processes underway related to the project. The Operator and Lessor shall also be liable for any costs incurred by Appomattox County in review, approval, and enforcement of this agreement, including any associated attorney's fees and/or court costs.
(4) 
The decommissioning plan, cost estimates, and all updates to plans and estimates shall be sealed by a professional engineer licensed to do business in the Commonwealth of Virginia.
(5) 
Liability Insurance: The owner, operator, lessee, or applicant shall propose a reasonable amount of liability insurance that the applicant deems adequate to cover operations at the facility. The applicant shall provide proof of such reasonable and adequate liability insurance for the facility prior to the issuance of a building permit.
E. 
Economic Analysis: An economic impact analysis, prepared by a qualified third-party that reports any expected change in the value of the subject property, expected employment during the construction of the facility, any expected impact on the county's tax revenues, the estimated costs to the county associated with the facility in the form of additional services, and information on any other economic benefits or burdens from the project.
F. 
Environmental Protection and Product Safety: All utility scale solar energy farms shall incorporate generally accepted national environmental protection and product safety standards for the use of solar panels and battery technologies for solar photovoltaic (electric energy) projects, such as those developed for existing product certifications and standards including the National Sanitation Foundation/American National Standards Institute No. 457, International Electrotechnical Commission No. 61215-2, Institute of Electrical and Electronics Engineers Standard 1547, and Underwriters Laboratories No. 61730-2.
(1) 
Certification that no per -and poly-fluroalkyl substances (PFAS) are utilized on any component, part, or panel associated with this project.
(2) 
Virginia Department of Environmental Quality Compliance: Any and all fines levied by the Virginia Department of Environmental Quality (VDEQ) for Erosion and Sediment Control or Stormwater Management violations, specifically applied to any project approved and constructed in Appomattox County, shall be matched 100%, and made payable to Appomattox County at the same time, as prescribed by VDEQ.
G. 
Review fees: The county may retain qualified third-parties to review portions of the conditional use permit petition or the site development plan that are outside of the county’s areas of expertise and do not have adequate state and federal review. Any costs incurred by the county for such review by qualified third-parties shall be billed to the applicant and must be paid in full prior to the issuance of a certificate of occupancy.
H. 
Community meeting: A public meeting shall be held prior to the county’s public hearing with the Planning Commission to give the community the opportunity to hear from the petitioner and ask questions regarding the proposed facility. The meeting shall be held at a location within a reasonable distance to the project and must be advertised in a newspaper with local circulation for two consecutive weeks prior to the meeting. The petitioner shall provide the Zoning Administrator with the date, time and place of the meeting, a copy of the advertisement, and a summary of any input/comments received from members of the public. Such information shall be provided to the Zoning Administrator no less than seven business days prior to the Planning Commission public hearing.

§ 19.6-97.3 Visual impacts, setbacks, and buffering.

The petitioner shall demonstrate through project siting, and if necessary, through mitigation, that the solar project minimizes impacts to viewsheds from all residential areas, and any areas of scenic, historical, cultural or recreational significance. The following should be adhered to in placement, buffering and/or setback:
A. 
A vegetative buffer sufficient to mitigate the visual impact of the facility is required along all areas adjacent to public roadways. For Utility-Scale Solar projects, the buffer shall consist of a 300-foot wide landscaped strip to include trees, shrubs and other vegetation considered native to the area. The landscaped strip may be located within the setback area and should run around or near the perimeter fence. Tree plantings in the buffer strip shall be a minimum of five feet in height at the time of planting, no more than 15 feet between trees. Trees may be staggered. Existing trees and vegetation may be maintained within the buffer areas and may supplement and satisfy landscaping requirements. An alternative to tree plantings is to construct an earthen berm, minimum height of six feet high. Berm must be stabilized with native grasses and/or plantings. The landscaped buffer must be maintained in good condition for the life of the project.
B. 
The solar panel arrays and battery storage facilities shall be set back a minimum of 500 feet, as measured from all property lines, internal and external, to the project. All other structures or infrastructure shall meet the minimum setback for the underlying zoning district. All equipment associated with a battery energy storage facilities shall be set back a minimum of 75 feet, as measured from all property lines, internal and external, to the project. Solar panel arrays and battery storage facilities shall be set back a minimum of 500 feet from the edge of water for any stream, creek, pond, lake or wetland or 300 feet from the 100-year floodplain, whichever is greater. Existing wells shall be abandoned in accordance with current Virginia Department of Health regulations. Ground-mounted solar arrays and associated battery energy storage facilities and equipment shall not exceed a height of 20 feet above average grade. This limit does not apply to utility poles and interconnection equipment associated with connection to the electrical grid.
C. 
The solar panel array area shall be enclosed by a security fence. The fence shall not be less than six feet in height and should be equipped with appropriate anticlimbing devices such as strands of barbed wire at the top. Fencing should be installed on the interior of the buffer area so that it is screened from adjacent property. The fence shall be maintained in good repair for the life of the project.
D. 
Pollinator Habitats: The facility area will utilize, as reasonably practical, seeds with appropriate pollinator-friendly native plants, shrubs, trees, grasses, forbs, and wildflowers. The facility must be seeded promptly following completion of construction in such a way as to reduce invasive weed growth. This requirement does not alter or negate any requirements of proper Erosion and Sediment Control measures as required by other local and state law.

§ 19.6-97.4 Processing of application.

The conditional use permit petition will follow the normal and customary process for such petitions, meaning, a duly advertised public hearing before the Planning Commission, followed by a recommendation, and then a duly advertised public hearing before the Board of Supervisors, followed by final consideration. Petitions are subject to any action afforded any other conditional use permit as enumerated elsewhere in the Zoning Ordinance.

§ 19.6-97.5 2232 review for utility scale solar energy farm.

In accordance with the Code of Virginia § 15.2-2232 et seq, utility scale solar energy farm petitions and associated Battery Energy Storage Facility petitions are subject to review against the county's Comprehensive Plan. Prior to the petition being considered by the Planning Commission, the Planning Commission shall make a determination as to conformity with the Comprehensive Plan, unless a valid siting agreement has been executed as stated in Code of Virginia § 15.2-2316.9. The 2232 review may be advertised and approved concurrently with the rezoning and conditional use permit petition.

§ 19.6-97.6 Unsafe or abandoned projects; decommissioning.

A. 
If the utility scale solar energy facility and/or battery energy storage facility is determined to be unsafe by the Building Official, then the facility shall be required to be repaired by the facility owner, site owner, or operator. Repairs shall be made in a timely manner as established by the Building Official. Should the repairs not be completed in the time frame provided, then the owners or operators will be instructed to commence decommissioning in accordance with the approved decommissioning plan.
B. 
If the facility is not operated for a continuous period of 12 months, then the county may notify the owner/operator by registered mail and provide 45 days for the owner/operator to respond. If no response is provided, then the owner/operator will be instructed to commence decommissioning in accordance with the approved decommissioning plan.
C. 
If the facility is abandoned, the owner/operator is required to notify the Zoning Administrator in writing.
D. 
Within 365 days of the date of said notification, or if determined to be abandoned by the Zoning Administrator in accordance with the above subsections, then the county may pursue legal action to have the facility removed at the expense of the facility owner, site owner, or operator, each of whom shall be jointly and severally liable for the expense of removing or repairing the facility. The county may also call upon the decommissioning security to remove the facility.
E. 
Within 365 days of the date abandonment has been determined, whether as declared by the County, or as scheduled by the owners or operator, the facility owner, site owner, or operator shall complete the physical removal of the facility in compliance with decommissioning plan established for such facility. This period may be extended at the request of the owners or operator, upon approval of the Board of Supervisors.