No oil and gas drilling sites, water storage facility, recycled water storage facility, temporary supervisor structures or oil and gas processing or transfer site of any type or nature shall be drilled, constructed or erected nor shall any work in preparation therefor be commenced within the boundaries of Cross Creek Township unless and until the person or entity has first registered with Cross Creek Township for the purpose of commencement of operations. Appendixes 1, 2, 3,[6] as well as, all applicable ordinances adopted by Cross Creek Township, and federal and state laws and regulations shall be adhered to by the applicant. Each registration shall be accompanied by the following items and by payment of a fee, set by resolution, made payable to "Cross Creek Township."
(a)
The Township shall be provided the name of the person supervising the drilling operation, and a phone number where such person can be reached 24 hours a day shall be updated to the extent necessary if contact information changes.
(b)
The oil and gas drill sites shall only be permitted on property that is a minimum of 10 acres or larger. Multiple property owners can combine adjoining parcels to achieve the minimum 10 acres required.
(c)
Prior to beginning any work on a drill site, the applicant shall submit to the Township a copy of all permits (general, ESCGP-1) issued by the Pennsylvania Department of Environmental Protection (PA DEP). In addition, the Township shall be provided copies of all plans (erosion and sedimentation control, grading, etc.) required by DEP. All required permits shall be maintained throughout the duration of the drilling operation. Any suspension or revocation of permits by DEP shall be reported to the Township and shall constitute a violation of Township zoning approval and may result in the suspension or revocation of zoning approval.
(d)
Access directly to state roads shall require Pennsylvania Department of Transportation (PADOT) highway occupancy permit approval. Prior to initiating any work at a drill site, the Township shall be provided a copy of the highway occupancy permit and enter into a road use maintenance agreement as provided for in Appendix 4.[7]
(e)
The applicant must provide the Township with a plan showing the proposed truck routes to be utilized during the drilling operation. The proposed hauling routes must be designed to minimize the impact on collector, connector and local streets within the Township. The Township reserves the right to designate required truck hauling routes involving Township roads. Any safety issues to public roads or other facilities should be mitigated and repaired immediately.