Expedited review for coastal restoration projects and the repair or reconstruction of certain coastal structures. In the case of an application for a coastal restoration project or for the repair or reconstruction of certain coastal structures, as enumerated in and pursuant to §
255-4-28 hereof, the publication, notice, and public comment requirements of Subsection
F shall not apply. In such applications, after receipt of all information required by the Planning Department pursuant to Subsection
E, the Department shall either issue an administrative natural resources special permit or, within five days, refer the matter to the Zoning Board of Appeals, in accordance with the procedures for all other administrative natural resources special permits. At the request of an applicant for an expedited permit under this subsection, the Planning Department may waive the preparation and mailing of a draft permit as would be required by Subsection
G. Where the Planning Department finds that the work proposed is neither a coastal restoration project nor the repair or reconstruction of a coastal structure as authorized in §
255-4-28, the application may not be processed under this subsection and shall be subject to the procedural requirements governing all other applications for administrative natural resources special permits.
[Amended 4-13-2007 by L.L. No. 14-2007]