Test. Development permits that result in a reduction of a level of service below the minimum level of service standard cannot be approved. For arterial roads, transit, fire/EMS, law enforcement, schools and parks, available and planned capacity will be used in conducting the concurrency test. For water, power, sanitary sewer, fire flow and stormwater management, only available capacity will be used in conducting the concurrency test.
(1)
If the capacity of public facilities is equal to or greater than the capacity required to maintain the level of service standard for the impact from the development permit, the concurrency test is passed. A certificate of capacity will be issued according to the provisions of FMC § 22.12.003.
(2)
If the capacity of public facilities is less than the capacity required to maintain the level of service standard for the impact from the development permit, the concurrency test is not passed. The applicant may:
(A)
Modify the application to reduce the need for public facilities that do not exist;
(B)
Demonstrate to the director's satisfaction that the development will have a lower need for capacity than usual and, therefore, capacity is adequate;
(C)
Arrange with the appropriate facility and service provider capacity for the provision of the additional concurrency facilities required; or
(D)
Appeal the results of the concurrency test to the hearing examiner in accordance with the provisions of FMC § 22.12.006.