Applications for Development Subdivision and Site Plan Review and Approval
Application | Jurisdiction | ||
|---|---|---|---|
Variance (N.J.S.A. 40:55D-70d) | Planning Board | ||
Subdivision | Planning Board | ||
Site plan | Planning Board | ||
Conditional use | Planning Board | ||
Variance (N.J.S.A. 40:55D-70c) | Planning Board | ||
Building permit for structure not related to a street | Planning Board | ||
Building permit for structure in bed of mapped street, public drainageway, flood control basin or public area | Planning Board |
Type of Development Application | Time Period | |
|---|---|---|
Subdivision plats and site plans | 45 days | |
Preliminary approval | 45 days | |
Final approval | 45 days | |
Conditional use authorization | 95 days | |
Variance | 95 days | |
Direction for issuance of a building permit | 95 days |
Applications for Development Subdivision and Site Plan Review and Approval
Application | Jurisdiction | ||
|---|---|---|---|
Variance (N.J.S.A. 40:55D-70d) | Planning Board | ||
Subdivision | Planning Board | ||
Site plan | Planning Board | ||
Conditional use | Planning Board | ||
Variance (N.J.S.A. 40:55D-70c) | Planning Board | ||
Building permit for structure not related to a street | Planning Board | ||
Building permit for structure in bed of mapped street, public drainageway, flood control basin or public area | Planning Board |
Type of Development Application | Time Period | |
|---|---|---|
Subdivision plats and site plans | 45 days | |
Preliminary approval | 45 days | |
Final approval | 45 days | |
Conditional use authorization | 95 days | |
Variance | 95 days | |
Direction for issuance of a building permit | 95 days |