Administrative Provisions
Application Fee | Escrow | |
|---|---|---|
If no new tower | $400 | $2,000 |
If a new tower is proposed | $1,000 | $5,000 |
Upon completion of the review, the Board shall adopt a motion specifying whether the escrow amount specified above is sufficient. In the event the Board shall determine the amount is excessive, it shall under motion specify the amount that shall be deemed sufficient, including a specification, if appropriate, that no escrow be posted. In the event the Board shall determine the amount specified above is insufficient, it shall so specify and shall further set forth the amount required to be posted in light of the criteria specified herein. |
a. | Residential. | ||
Minimum Fee | $60 | ||
1. | Utility Uses: | ||
Solar Panels, Oil Tanks, Generators, Propane Tanks, Sprinklers | $60 | ||
2. | Accessory Uses: | ||
Minor detached improvements up to 200 square feet (shed, flag pole, fence, pergola, swing set, etc. | $60 | ||
Major detached improvements over 200 square feet (detached garage, gazebo, shed, swing set, etc.) | $120 | ||
Driveways and sidewalks | $60 | ||
Sports courts with lighting | $100 | ||
Sports courts without lighting | $60 | ||
Patios | $60 | ||
Decks | $80 | ||
Retaining walls: | |||
Wall or walls in a single slope less than a cumulative height of 3 feet | $60 | ||
Wall or walls in a single slope greater than a cumulative height of 3 feet | $360 | ||
Pools: | |||
Above ground | $60 | ||
In-ground | $100 | ||
Additions, alterations, or reconstruction (sunrooms, porches, bedrooms, finished basements, baths, or creation of any enclosed space or area covered by a roof) | $60 up to $30,000 of cost and $420 for every $5,000 thereafter | ||
Renovation | $60 up to $10,000 of cost and $20 for every $5,000 thereafter | ||
New 1- and 2-family homes | $600 | ||
Mobile home replacement | $80 | ||
Temporary tents | $60 | ||
Processing fee | $40 | ||
Revisions | |||
First revision submitted within 60 days from date of denial | No charge | ||
First revision submitted after 60 days from date of denial | $40 | ||
Revision to existing zoning permit | $40 | ||
Any second revision | Must resubmit as a new application | ||
b. | Nonresidential. | ||
New nonresidential construction: | $200 up to $50,000 of cost and $20 for every $50,000 thereafter | ||
Construction trailer | $100 | ||
Commencement or change of use with tenant fit out | $200 | ||
Commencement or change of use with continuing certificate of occupancy inspection: | $300 | ||
Nonresidential less than 12,000 square feet | $300 | ||
Nonresidential greater than 12,000 square feet | $400 | ||
Industrial factory | $700 | ||
Each additional reinspection | $60 | ||
Signs: | |||
Sign less than 15 square feet | $100 | ||
Sign greater than 15 square feet | $160 | ||
Revisions: | |||
First revision | $60 | ||
Second revision | Must resubmit as a new application | ||
Administrative Provisions
Application Fee | Escrow | |
|---|---|---|
If no new tower | $400 | $2,000 |
If a new tower is proposed | $1,000 | $5,000 |
Upon completion of the review, the Board shall adopt a motion specifying whether the escrow amount specified above is sufficient. In the event the Board shall determine the amount is excessive, it shall under motion specify the amount that shall be deemed sufficient, including a specification, if appropriate, that no escrow be posted. In the event the Board shall determine the amount specified above is insufficient, it shall so specify and shall further set forth the amount required to be posted in light of the criteria specified herein. |
a. | Residential. | ||
Minimum Fee | $60 | ||
1. | Utility Uses: | ||
Solar Panels, Oil Tanks, Generators, Propane Tanks, Sprinklers | $60 | ||
2. | Accessory Uses: | ||
Minor detached improvements up to 200 square feet (shed, flag pole, fence, pergola, swing set, etc. | $60 | ||
Major detached improvements over 200 square feet (detached garage, gazebo, shed, swing set, etc.) | $120 | ||
Driveways and sidewalks | $60 | ||
Sports courts with lighting | $100 | ||
Sports courts without lighting | $60 | ||
Patios | $60 | ||
Decks | $80 | ||
Retaining walls: | |||
Wall or walls in a single slope less than a cumulative height of 3 feet | $60 | ||
Wall or walls in a single slope greater than a cumulative height of 3 feet | $360 | ||
Pools: | |||
Above ground | $60 | ||
In-ground | $100 | ||
Additions, alterations, or reconstruction (sunrooms, porches, bedrooms, finished basements, baths, or creation of any enclosed space or area covered by a roof) | $60 up to $30,000 of cost and $420 for every $5,000 thereafter | ||
Renovation | $60 up to $10,000 of cost and $20 for every $5,000 thereafter | ||
New 1- and 2-family homes | $600 | ||
Mobile home replacement | $80 | ||
Temporary tents | $60 | ||
Processing fee | $40 | ||
Revisions | |||
First revision submitted within 60 days from date of denial | No charge | ||
First revision submitted after 60 days from date of denial | $40 | ||
Revision to existing zoning permit | $40 | ||
Any second revision | Must resubmit as a new application | ||
b. | Nonresidential. | ||
New nonresidential construction: | $200 up to $50,000 of cost and $20 for every $50,000 thereafter | ||
Construction trailer | $100 | ||
Commencement or change of use with tenant fit out | $200 | ||
Commencement or change of use with continuing certificate of occupancy inspection: | $300 | ||
Nonresidential less than 12,000 square feet | $300 | ||
Nonresidential greater than 12,000 square feet | $400 | ||
Industrial factory | $700 | ||
Each additional reinspection | $60 | ||
Signs: | |||
Sign less than 15 square feet | $100 | ||
Sign greater than 15 square feet | $160 | ||
Revisions: | |||
First revision | $60 | ||
Second revision | Must resubmit as a new application | ||