PLANNING BOARD: SPECIAL USE PERMITS AND SITE PLAN REVIEW AND APPROVAL
The duration of an approved special use permit shall be six months or such greater period not to exceed one year as may be specified in the approval by the planning board. Special use permit approval may be renewed by the planning board for a period of six months upon written application to the planning board and copies to the code enforcement officer, such application to be submitted prior to the expiration of the special use permit approval period. |
On application, and after public notice and hearing, the planning board may authorize the issuance by the code enforcement officer of permits for any of the special uses for which this law requires such permits. |
In addition to the above, in the case of any use located in, or directly adjacent to, a residential district: | |
a. | The location and size of such use, the nature and intensity of operations involved in or conducted in connection therewith, its site layout and its relation to existing streets shall be such that both pedestrian and vehicular traffic to and from the use and the assembly of persons in connection therewith will not be hazardous or inconvenient to, or incongruous with, the said residential district or conflict with the normal traffic of the neighborhood. |
b. | The location and height of buildings, the location, nature and height of walls and fences, and the nature and extent of landscaping on the site shall be such that the use will not hinder or discourage the appropriate development and use of adjacent land and buildings. |
Developers of land adjoining state or county highways are advised to consult with the District Engineer of the New York State Department of Transportation or Cattaraugus County Highway Superintendent at the concept layout stage in order to resolve problems of street openings or storm water drainage at the earliest possible stage in the design process. The planning board shall provide written comments on the concept plan of a proposed development and in the course of its review may consult with other interested public agencies. |
The concept plan shall include the following information: |
The requirement for submission of these documents may be waived at the sole discretion of the planning board. |
In its review of a preliminary site plan, the planning board may consult with the code enforcement officer, fire and police departments, other local and Cattaraugus County officials, and any designated private consultants, in addition to representatives of federal and state agencies including, but not limited to, the soil conservation service, the New York State Department of Transportation (NYSDOT) and the New York State Department of Environmental Conservation (NYSDEC). |
If more then one year has elapsed between the time of the planning board's report on the preliminary site plan and submission by the applicant of a final site plan application, and if the planning board finds that conditions have changed significantly in the interim, the planning board may require a resubmission of the preliminary site plan for further review and possible revisions prior to accepting the proposed final site plan application for review. The final site plan shall conform to the approved preliminary site plan, and shall incorporate any revisions or other features that may have been recommended by the planning board at the preliminary review. All revisions shall be clearly indicated by the applicant. |
PLANNING BOARD: SPECIAL USE PERMITS AND SITE PLAN REVIEW AND APPROVAL
The duration of an approved special use permit shall be six months or such greater period not to exceed one year as may be specified in the approval by the planning board. Special use permit approval may be renewed by the planning board for a period of six months upon written application to the planning board and copies to the code enforcement officer, such application to be submitted prior to the expiration of the special use permit approval period. |
On application, and after public notice and hearing, the planning board may authorize the issuance by the code enforcement officer of permits for any of the special uses for which this law requires such permits. |
In addition to the above, in the case of any use located in, or directly adjacent to, a residential district: | |
a. | The location and size of such use, the nature and intensity of operations involved in or conducted in connection therewith, its site layout and its relation to existing streets shall be such that both pedestrian and vehicular traffic to and from the use and the assembly of persons in connection therewith will not be hazardous or inconvenient to, or incongruous with, the said residential district or conflict with the normal traffic of the neighborhood. |
b. | The location and height of buildings, the location, nature and height of walls and fences, and the nature and extent of landscaping on the site shall be such that the use will not hinder or discourage the appropriate development and use of adjacent land and buildings. |
Developers of land adjoining state or county highways are advised to consult with the District Engineer of the New York State Department of Transportation or Cattaraugus County Highway Superintendent at the concept layout stage in order to resolve problems of street openings or storm water drainage at the earliest possible stage in the design process. The planning board shall provide written comments on the concept plan of a proposed development and in the course of its review may consult with other interested public agencies. |
The concept plan shall include the following information: |
The requirement for submission of these documents may be waived at the sole discretion of the planning board. |
In its review of a preliminary site plan, the planning board may consult with the code enforcement officer, fire and police departments, other local and Cattaraugus County officials, and any designated private consultants, in addition to representatives of federal and state agencies including, but not limited to, the soil conservation service, the New York State Department of Transportation (NYSDOT) and the New York State Department of Environmental Conservation (NYSDEC). |
If more then one year has elapsed between the time of the planning board's report on the preliminary site plan and submission by the applicant of a final site plan application, and if the planning board finds that conditions have changed significantly in the interim, the planning board may require a resubmission of the preliminary site plan for further review and possible revisions prior to accepting the proposed final site plan application for review. The final site plan shall conform to the approved preliminary site plan, and shall incorporate any revisions or other features that may have been recommended by the planning board at the preliminary review. All revisions shall be clearly indicated by the applicant. |