General Regulations
Types of Deciduous Trees Permitted to Meet Chapter Requirements | |
|---|---|
Acer rubrum - Red maple | Liquidambar styraciflua - Sweet gum |
Acer saccharum - Sugar maple | Liriodendron tulipifera - Tulip poplar |
Celtis occidentalis - Common hackberry | Quercus - All species of oaks |
Fraxinus americana - White ash | Tilia americana - American linden |
Fraxinus Pennsylvania - Green ash | Ulmus hybrids - Homestead or Sapporo autumn gold |
Gleditsia triacanthos - Thornless locust | |
Equivalent Continuous Sound Level Limits (5-minute LAeq and LCeq) | ||
|---|---|---|
Zoning District of Receiving Land Use | Day (7:00 a.m. to 7:00 p.m.) | Night 7:00 p.m. to 7:00 a.m., Sundays and Holidays |
R-1, R-2, R-3 | 50 dB(A)/60 dB(C) | 45 dB(A)/55 dB(C) |
C-1, C-1A, C2 | 60 dB(A) | 55 dB(A) |
I-1 | 65 dB(A) | 60 dB(A) |
Maximum Sound Level Limits (Slow Response LASmax and LCSmax) | ||
|---|---|---|
Zoning District of Receiving Land Use | Day (7:00 a.m. to 7:00 p.m.) | Night 7:00 p.m. to 7:00 a.m., Sundays and Holidays |
R-1, R-2, R-3 | 60 dB(A)/70 dB(C) | 55 dB(A)/65 dB(C) |
C-1, C-1A, C2 | 70 dB(A) | 65 dB(A) |
I-1 | 75 dB(A) | 70 dB(A) |
Step 1: The applicant shall develop and submit a pre-drilling plan which shall provide a project description, a hydrogeologic setting description, and a groundwater availability analysis. Following approval of the pre-drilling plan, the applicant shall move forward with the drilling plan, and once the well(s) is completed the project shall proceed to Step 2. |
Step 2: The applicant shall submit a constant rate aquifer testing plan. Following approval of the constant rate aquifer testing plan, the applicant shall perform the testing as approved. |
Step 3: Upon completion of the constant rate aquifer test, the applicant shall submit the results. These results shall include hydrographs of all monitoring locations, a revised groundwater availability analysis and hydrogeologic setting, and details of any observed impacts. |