Approval Process
Figure 1000.1 Types of Approvals | ||||||||
|---|---|---|---|---|---|---|---|---|
Approval Type | Document Type | Number of Copies | Submitted to/Approved by | Submission Deadline | Drawing Scale | |||
1 | Lot plan review: permitted use | Application | 8 | Planning Commission | 30 days prior to regularly scheduled Planning Commission meeting | 1 inch = 20 feet unless defined by Planning Director | ||
• Residential • Nonresidential • Expansion of existing structure in flood-prone area | ||||||||
2 | Lot plan review: conditional use | Application | 17 | Council | 10 days before Council meeting | 1 inch = 20 feet unless defined by Planning Director | ||
3 | Lot plan review: change in use | Supplemental site plan | 8 | Planning Commission | 30 days prior to Planning Commission meeting | |||
4a | Occupancy permits: | Application | 1 | Building Official | Prior to occupancy | |||
• New structure • Existing nonresidential structure with new use • Change in use | ||||||||
4b | Occupancy permits: | Application | 1 | Zoning Officer | Prior to occupancy | |||
• Existing residential structure with new use • New use not specified | ||||||||
5 | Special permits | Application | 1 | Township Manager | Less than or equal to 2 months before activity; renewal less than or equal to 2 years | |||
6 | Building on slope greater than 25% | Application | 1 | Planning Department, Township Engineer | 30 days before Planning Commission meeting | |||
7 | Building permits | Application | 1 | Building Official | Not specified | |||
8 | Demolition permits | Application | 1 | Building Official | Not specified | |||
9 | Rezoning | Application | 1 | Council | See § 440-917 | |||
10 | Zoning permit | Application | 2 | Zoning Officer | N/A | |||
Approval Process
Figure 1000.1 Types of Approvals | ||||||||
|---|---|---|---|---|---|---|---|---|
Approval Type | Document Type | Number of Copies | Submitted to/Approved by | Submission Deadline | Drawing Scale | |||
1 | Lot plan review: permitted use | Application | 8 | Planning Commission | 30 days prior to regularly scheduled Planning Commission meeting | 1 inch = 20 feet unless defined by Planning Director | ||
• Residential • Nonresidential • Expansion of existing structure in flood-prone area | ||||||||
2 | Lot plan review: conditional use | Application | 17 | Council | 10 days before Council meeting | 1 inch = 20 feet unless defined by Planning Director | ||
3 | Lot plan review: change in use | Supplemental site plan | 8 | Planning Commission | 30 days prior to Planning Commission meeting | |||
4a | Occupancy permits: | Application | 1 | Building Official | Prior to occupancy | |||
• New structure • Existing nonresidential structure with new use • Change in use | ||||||||
4b | Occupancy permits: | Application | 1 | Zoning Officer | Prior to occupancy | |||
• Existing residential structure with new use • New use not specified | ||||||||
5 | Special permits | Application | 1 | Township Manager | Less than or equal to 2 months before activity; renewal less than or equal to 2 years | |||
6 | Building on slope greater than 25% | Application | 1 | Planning Department, Township Engineer | 30 days before Planning Commission meeting | |||
7 | Building permits | Application | 1 | Building Official | Not specified | |||
8 | Demolition permits | Application | 1 | Building Official | Not specified | |||
9 | Rezoning | Application | 1 | Council | See § 440-917 | |||
10 | Zoning permit | Application | 2 | Zoning Officer | N/A | |||