Upon the Director of Public Works or the designee’s determination that erosion control measures are deficient, but not hazardous, or that the contractor, permittee or owner did deposit, spill, drop or track any dirt, earth, mud, rock, sand, shale, debris, rubbish or other material on any right-of-way, the Director of Public Works will notify the contractor, permittee or owner to take remedial action to correct the deficiencies. Notification shall be done by at least one (1) of the following methods:
a.
Personal contact with the contractor, permittee or owner;
b.
Telephone contact with the contractor, permittee or owner;
c.
Email contact with the contractor, permittee or owner; or
d.
Posting notice on the property.
e.
Issue a stop work order for the site;
f.
Suspend land disturbance permit(s);
g.
Remedy the deficiencies and bill the contractor, permittee or owner for the actual and administrative costs. If the contractor, permittee or owner fails to reimburse the City for correcting the deficiencies within thirty (30) days, the City of Raymore will draw upon any and all financial securities to cover the actual and administrative costs; and/or
h.
Refer the case to the City Attorney for prosecution.