4-2-130 INDUSTRIAL

DEVELOPMENT STANDARDS

4-2-130A

DEVELOPMENT STANDARDS FOR INDUSTRIAL ZONING DESIGNATIONS  

 

IL

IM

IH

LOT DIMENSIONS

Minimum Lot Size for lots created after September 1, 1985

35,000 sq. ft.

Minimum Lot Width/Depth for lots created after September 1, 1985

None

LOT COVERAGE

Maximum Lot Coverage for Buildings

65% of total lot area or 75% if parking is provided within the building or within a parking garage

None

HEIGHT

Maximum Building Height5, except for Public Facilities5,13

50 ft.;
Heights may exceed maximum with a Conditional Use Permit.

Maximum Height for Wireless Communication Facilities5

See RMC 4-4-140.

SETBACKS8,11

Minimum Front Yard

Principal Arterial streets:12 20 ft.

Other streets: 15 ft.; provided, that 20 ft. is required if a lot is adjacent to or abutting a lot zoned residential.

Principal Arterial streets:12 20 ft.

Other streets: 15 ft. Except 50 ft. is required if a lot is adjacent to or abutting a lot zoned residential.

Principal Arterial streets:12 20 ft.

Other streets: 15 ft.

Minimum Secondary Front Yard

Principal Arterial streets:12 20 ft.

Other streets: 15 ft. Except 50 ft. is required if a lot is adjacent to or abutting a lot zoned residential.

Principal Arterial streets:12 20 ft.

Other streets: 15 ft.

Minimum Freeway Frontage Setback

10 ft. landscaped setback from the property line.

Minimum Rear and Side Yards11

None, except 20 ft. if lot is adjacent to or abutting a lot zoned residential; which may be reduced to 15 ft. through the Site Plan development review process.

None, except 50 ft. if lot is adjacent to or abutting a lot zoned residential.

None, except 50 ft. if lot abuts a lot zoned residential.

20 ft. if lot abuts a lot zoned CN, CV, CA, CD, CO, COR, or lot with Public Facilities.

Clear Vision Area

In no case shall a structure over 42 in. in height intrude into the 20 ft. clear vision area defined in RMC 4-11-030.

LANDSCAPING

General

See RMC 4-4-070

SCREENING

Minimum Required for Outdoor Loading, Repair, Maintenance or Work Areas; Outdoor Storage, Refuse or Dumpster Areas

See RMC 4-4-095

Special Screening Requirements for Tow Truck Operations and Impoundment Yards

NA

6 to 10 ft. high solid wall or sight-obscuring fence required.

LOADING DOCKS

Location

Not permitted on the side of the lot that is adjacent to or abutting a lot zoned residential.2

NA

DUMPSTER/RECYCLING COLLECTION STATION OR CENTER

Location of Refuse or Recycling Areas

See RMC 4-4-090

PARKING

General

See RMC 4-4-080 and 10-10-13

SIGNS

General

See RMC 4-4-100

CRITICAL AREAS

General

See RMC 4-3-050 and 4-3-090

(Ord. 4851, 8-7-2000; Amd. Ord. 4963, 5-13-2002; Ord. 5153, 9-26-2005; Ord. 5528, 3-8-2010; Ord. 5574, 11-15-2010; Ord. 5676, 12-3-2012; Ord. 5744, 1-12-2015; Ord. 5746, 1-12-2015; Ord. 5759, 6-22-2015; Ord. 5841, 6-12-2017; Ord. 5965, 3-2-2020; Ord. 6100 (Att. B), 12-5-2022)

4-2-130B CONDITIONS ASSOCIATED WITH DEVELOPMENT STANDARDS TABLE FOR INDUSTRIAL ZONING DESIGNATIONS

1.    Reserved.

2.    These provisions may be modified through the site development plan review where the applicant can show that the same or better result will occur because of creative design solutions, unique aspects or use, etc., which have not been fully planned at the time of site plan development review.

3.    Reserved.

4.    Reserved.

5.    Building height shall not exceed the maximum allowed by the subject zoning district or the maximum allowed pursuant to RMC 4-3-020, Airport Related Height and Use Restrictions, whichever is less. (Ord. 6101, 12-12-2022)

6.    Reserved.

7.    Reserved.

8.    Specified development standards may be modified by an Administrative Conditional Use Permit in the Employment Area, or by a Hearing Examiner Conditional Use Permit outside the Employment Area.

9.    Reserved.

10.    Reserved.

11.    Allowed Projections into Setbacks:

a.    Eaves and cornices may extend over the required setback for a distance of up to twenty-four inches (24").

b.    Accessory buildings when erected so that the entire building is within a distance of thirty feet (30') from the rear lot line may also occupy the side yard setback of an inside lot line.

c.    Steps and decks having no roof and not exceeding forty-two inches (42") high may be built within a front setback.

12.    References to “principal arterial streets” include principal arterials as defined in the Arterial Street Plan and depicted in RMC 4-2-080E. (Ord. 5804, 5-23-2016)

13.    Public facilities are allowed the following height bonus: publicly owned structures shall be permitted an additional fifteen feet (15') in height above that otherwise permitted in the zone if “pitched roofs,” as defined herein, are used for at least sixty percent (60%) or more of the roof surface of both primary and accessory structures. In addition, in zones where the maximum permitted building height is less than seventy-five feet (75'), the maximum height of a publicly owned structure may be increased as follows, up to a maximum height of seventy-five (75') to the highest point of the building:

a.    When abutting a public street, one additional foot of height for each additional one and one-half feet (1-1/2') of perimeter building setback beyond the minimum street setback is required at street level unless such setbacks are otherwise discouraged (e.g., inside the Center Downtown Zone);

b.    When abutting a common property line, one additional foot of height for each additional two feet (2') of perimeter building setback beyond the minimum is required along a common property line; and

c.    On lots four (4) acres or greater, five (5) additional feet of height for every one percent (1%) reduction below a twenty percent (20%) maximum lot area coverage for public amenities such as recreational facilities, and/or landscaped open space areas, etc., when these are open and accessible to the public during the day or week, is permitted.

(Amd. Ord. 4963, 5-13-2002; Ord. 5519, 12-14-2009; Ord. 5574, 11-15-2010; Ord. 5607, 6-6-2011; Ord. 5676, 12-3-2012; Ord. 5744, 1-12-2015; Ord. 5759, 6-22-2015; Ord. 5965, 3-2-2020)