C Uses
The following provisions are provided to allow the review of those uses that are identified as a Conditional Use (identified herein as either “C-1” or “C-2” Uses) in the Table of Uses herein. The nature and proposed location of a Conditional Use may be such that certain use and location conditions may be necessary to protect adjacent properties and the general health, safety, and welfare of the City.
HISTORY:
Ord. 2024-6, 4/23/2024
HISTORY:
Ord. 2024-6, 4/23/2024
All requests to establish a C-1 or C-2 Use shall be initiated by filing a C-1 or C-2 Use Application, in the Office of the City Recorder, which may include a Building Permit Application, available from the Zoning Administrator. A property owner may present a C-1 or C-2 Use Application for review and decision by the Commission or Council, as applicable. An agent of the property owner, or a lessee of the property owner may present a C-1 or C-2 Use Application to the Commission or Council, as applicable, for review and decision, provided such application is accompanied by a property owner affidavit of authorization.
HISTORY:
Ord. 2024-6, 4/23/2024
HISTORY:
Ord. 2024-6, 4/23/2024
All C-1 or C-2 Use Applications shall comply with all requirements of this Chapter and this Ordinance, and all other applicable Land Use Ordinance and City requirements. All C-1 or C-2 Use Applications shall be determined complete by the Zoning Administrator, as provided by 17.09.060 herein. For C-1 or C-2 Use Applications determined to be incomplete, the Zoning Administrator shall comply with the requirements of 17.09.070 herein.
HISTORY:
Ord. 2024-6, 4/23/2024
HISTORY:
Ord. 2024-6, 4/23/2024
All C-1 and C-2 Use Applications shall include and provide the following information:
HISTORY:
Ord. 2024-6, 4/23/2024
The Commission for C-1 Use Applications and the Council for C-2 Use Applications shall review the Application and determine if the Application, from the materials presented by the Applicant, complies with the following:
HISTORY:
Ord. 2024-6, 4/23/2024
A C-1 or C-2 Use Application shall be approved by the Commission or Council, as applicable, if reasonable conditions are proposed, or can be imposed by the Commission or Council, to mitigate the reasonably anticipated detrimental effects of the proposed Conditional Use in accordance with applicable standards. Such reasonable conditions and applicable standards may relate to the location, construction, maintenance, operation, site planning, building architecture, traffic management and control, hours of operation, and other items of the proposed Conditional Use, and deemed reasonable by the Commission or Council.
The Commission for C-1 Use Applications and the Council for C-2 Use Applications may impose reasonable conditions related to any of the following uses, site planning, or building items, necessary to mitigate the reasonably anticipated detrimental effects of the proposed Conditional Use:
HISTORY:
Ord. 2024-6, 4/23/2024
HISTORY:
Ord. 2024-6, 4/23/2024
The approval of a C-1 Use Application by the Commission or C-2 Use Application by the Council shall authorize the establishment of the approved Conditional Use, subject to all reasonable conditions of approval. Approval of a C-1 or a C-2 Use shall not be deemed an approval of any other application, license, or permit.
HISTORY:
Ord. 2024-6, 4/23/2024
Any person aggrieved by a decision of the Commission regarding a C-1 Use Application, or a decision of the Council regarding a C-2 Use Application may appeal such decision as provided by 17.21 herein.
HISTORY:
Ord. 2024-6, 4/23/2024
HISTORY:
Ord. 2024-6, 4/23/2024
The continuing validity of a C-1 or C-2 Use Application approval is conditioned upon the Applicant proceeding after approval to implement the approval with reasonable diligence. For the purpose of this Ordinance, and this requirement, the approval of a C-1 or C-2 Use Application shall be effective for a period of one hundred eighty (180) calendar days, at the end of which time the Applicant shall have proceeded to implement the C-1 or C-2 Use Application approval. If the C-1 or C-2 Use Application approval is not commenced within one hundred eighty (180) calendar days from the date of approval by the Commission or Council, as applicable, the C-1 or C-2 Use Application approval shall expire and shall be rendered void.
HISTORY:
Ord. 2024-6, 4/23/2024