Zoneomics Logo
search icon

Sewerd City Zoning Code

CHAPTER 15

25. - Floodplain Management

15.25.010 - Findings and statement.

A.

Findings.

1.

The flood hazard areas of the City of Seward are subject to periodic inundation which may result in loss of life and property, health and safety hazards, disruption of commerce and governmental services, extraordinary public expenditures for flood protection and relief and impairment of the tax base, all of which adversely affect the public health, safety and general welfare.

2.

These flood losses may be caused by the cumulative effect of obstructions in flood hazard areas which increase flood heights and velocities and, when inadequately anchored, cause damage in other areas. Uses that are inadequately flood proofed, elevated or otherwise protected from flood damage, also contribute to flood loss.

B.

Statement of purpose. It is the purpose of this chapter to promote public health, safety, and general welfare, and to minimize public and private losses due to flooding in flood hazard areas by provisions designed to:

1.

Protect human life and health;

2.

Minimize expenditure of public money for costly flood control projects;

3.

Minimize the need for rescue and relief efforts associated with flooding and generally undertaken at the expense of the general public;

4.

Minimize prolonged business interruptions;

5.

Minimize damage to public facilities and utilities such as water and gas mains; electric, telephone and sewer lines; and streets and bridges located in flood hazard areas;

6.

Help maintain a stable tax base by providing for the sound use and development of flood hazard areas so as to minimize blight areas caused by flooding;

7.

Notify potential buyers that property is in a Special Flood Hazard Area;

8.

Notify those who occupy flood hazard areas that they assume responsibility for their actions; and

9.

Participate in and maintain eligibility for flood insurance and disaster relief.

C.

Methods of reducing flood losses. In order to accomplish its purposes, this chapter includes methods and provisions to:

1.

Restrict or prohibit development which is dangerous to health, safety, and property due to water or erosion hazards, or which result in damaging increases in erosion, flood heights or velocities;

2.

Require that development vulnerable to floods, including facilities, be protected against flood damage at the time of initial construction;

3.

Control the alteration of natural floodplains, stream channels, and natural protective barriers, which help accommodate or channel floodwaters;

4.

Control filling, grading, dredging, and other development which may increase flood damage; and

5.

Prevent or regulate the construction of flood barriers which will unnaturally divert floodwaters, or which may increase flood hazards in other areas.

(Ord. 98-11; Ord. No. 2023-009, § 1, 4-10-2023)

15.25.020 - Definitions.

For purposes of this chapter, the following words and phrases shall be defined as follows:

Alluvial fan. A geomorphologic feature characterized by a cone or fan-shaped deposit of boulders, gravel, and fine sediments that have been eroded from mountain slopes, transported by flood flows, and then deposited on the valley floors, and which is subject to flash flooding, high velocity flows, debris flows, erosion, sediment movement and deposition, and channel migration.

Appeal. A request for a review of the Floodplain Administrator's interpretation of any provision of this ordinance or a request for a variance.

Appurtenant structure. A structure that is on the same parcel of property as a principal structure, the use of which is incidental to the use of the principal structure.

Area of shallow flooding. A designated Zone AO, AH, AR/AO or AR/AH (or VO) on a community's Flood Insurance Rate Map (FIRM) with a one percent or greater annual chance of flooding to an average depth of one to three feet where a clearly defined channel does not exist, where the path of flooding is unpredictable, and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow.

Area of special flood hazard. The land in the floodplain within a community subject to a 1 percent or greater chance of flooding in any given year. It is shown on the Flood Insurance Rate Map (FIRM) as Zone A, AO, AH, A1-30, AE, A99, AR (V, VO, V1-30, VE). "Special flood hazard area" is synonymous in meaning with the phrase "area of special flood hazard".

Base flood. The flood having a one percent chance of being equaled or exceeded in any given year.

Base flood elevation (BFE). The elevation to which floodwater is anticipated to rise during the base flood.

Basement. Any area of the building having its floor sub-grade - i.e., below ground level - on all sides.

Breakaway wall. A wall that is not part of the structural support of the building and is intended through its design and construction to collapse under specific lateral loading forces, without causing damage to the elevated portion of the building or supporting foundation system.

Building. See "Structure."

Coastal high hazard area. An area of special flood hazard extending from offshore to the inland limit of a primary frontal dune along an open coast and any other area subject to high velocity wave action from storms or seismic sources.

Development. Any human-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.

Elevation certificate. An administrative tool of the National Flood Insurance Program (NFIP) that can be used to provide elevation information, to determine the proper insurance premium rate, and to support a request for a Letter of Map Amendment (LOMA) or Letter of Map Revision based on fill (LOMR-F).

Federal Emergency Management Agency. The agency responsible for administration of the National Flood Insurance Program.

Flood or flooding.

A.

A general and temporary condition of partial or complete inundation of normally dry land areas from:

1.

The overflow of inland or tidal waters;

2.

The unusual and rapid accumulation or runoff of surface waters from any source or;

3.

Mudslides (i.e., mudflows) which are proximately caused by flooding as defined in paragraph (a)(2) of this definition and are akin to a river of liquid and flowing mud on the surfaces of normally dry land areas, as when earth is carried by a current of water and deposited along the path of the current.

B.

The collapse or subsidence of land along the shore of a lake or other body of water as a result of erosion or undermining caused by waves or currents of water exceeding anticipated cyclical levels or suddenly caused by an unusually high water level in a natural body of water, accompanied by a severe storm, or by an unanticipated force of nature, such as flash flood or an abnormal tidal surge, or by some similarly unusual and unforeseeable event which results in flooding as defined in paragraph (a)(1) of this definition.

Flood elevation study. An examination, evaluation and determination of flood hazards and, if appropriate, corresponding water surface elevations, or an examination, evaluation and determination of mudslide (i.e., mudflow) and/or flood-related erosion hazards.

Flood insurance rate map (FIRM). The official map of a community, on which the Federal Insurance Administrator has delineated both the special flood hazard areas and the risk premium zones applicable to the community. A FIRM that has been made available digitally is called a Digital Flood Insurance Rate Map (DFIRM).

Flood insurance study (FIS). See "Flood elevation study".

Floodplain or flood-prone area. Any land area susceptible to being inundated by water from any source. See "Flood or flooding."

Floodplain administrator. The community official designated by title to administer and enforce the floodplain management regulations.

Floodplain management. The operation of an overall program of corrective and preventive measures for reducing flood damage, including but not limited to emergency preparedness plans, flood control works, and floodplain management regulations.

Floodplain management regulations. Zoning ordinances, subdivision regulations, building codes, health regulations, special purpose ordinances (such as floodplain ordinance, grading ordinance and erosion control ordinance) and other application of police power. The term describes such state or local regulations, in any combination thereof, which provide standards for the purpose of flood damage prevention and reduction.

Flood proofing. Any combination of structural and nonstructural additions, changes, or adjustments to structures which reduce or eliminate risk of flood damage to real estate or improved real property, water and sanitary facilities, structures, and their contents.

Floodway. The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than a designated height. Also referred to as "Regulatory Floodway."

Freeboard. A factor of safety usually expressed in feet above a flood level for purposes of flood plain management. "Freeboard" tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization of the watershed.

Functionally dependent use. A use which cannot perform its intended purpose unless it is located or carried out in close proximity to water. The term includes only docking facilities, port facilities that are necessary for the loading and unloading of cargo or passengers, and ship building and ship repair facilities, and does not include long-term storage or related manufacturing facilities.

Highest adjacent grade. The highest natural elevation of the ground surface prior to construction next to the proposed walls of a structure.

Historic structure. Any structure that is:

A.

Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;

B.

Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;

C.

Individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of Interior; or

D.

Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either:

1.

By an approved state program as determined by the Secretary of the Interior or

2.

Directly by the Secretary of the Interior in states without approved programs.

Levee. A man-made structure, usually an earthen embankment, designed and constructed in accordance with sound engineering practices to contain, control or divert the flow of water so as to provide protection from temporary flooding.

Levee system. A flood protection system which consists of a levee, or levees, and associated structures, such as closure and drainage devices, which are constructed and operated in accordance with sound engineering practices.

Lowest floor. The lowest floor of the lowest enclosed area (including "Basement"). An unfinished or flood resistant enclosure, usable solely for parking of vehicles, building access or storage in an area other than a basement area is not considered a building's lowest floor, provided that such enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirements of this chapter.

Manufactured home. A structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when attached to the required utilities. The term "manufactured home" does not include a "recreational vehicle." *Manufactured homes are not allowed within City limits.

Mean sea level. For purposes of the National Flood Insurance Program, the National Geodetic Vertical Datum (NGVD) of 1929 or other datum, to which Base Flood Elevations shown on a community's Flood Insurance Rate Map are referenced.

New construction. For floodplain management purposes, "new construction" means structures for which the "start of construction" commenced on or after the effective date of a floodplain management regulation adopted by a community and includes any subsequent improvements to such structures.

One-hundred-year flood or 100-year flood. See "Base flood."

Reasonably safe from flooding. Development that is designed and built to be safe from flooding based on consideration of current flood elevation studies, historical data, high water marks and other reliable data known to the community. In unnumbered A zones where flood elevation information is not available and cannot be obtained by practicable means, reasonably safe from flooding means that the lowest floor is at least two feet above the highest adjacent grade.

Recreational vehicle. A vehicle which is:

A.

Built on a single chassis;

B.

400 square feet or less when measured at the largest horizontal projection;

C.

Designed to be self-propelled or permanently towable by a light-duty truck; and

D.

Designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.

Regulatory floodway. See "Floodway".

Sheet flow area. See "Area of shallow flooding".

Special flood hazard area (SFHA). See "Area of special flood hazard".

Start of construction. Includes substantial improvement and means the date the building permit was issued, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days from the date of the permit. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation. Permanent construction does not include land preparation, such as clearing, grading, and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundation or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.

Structure. For floodplain management purposes, a walled and roofed building, including a gas or liquid storage tank, that is principally above ground.

Substantial damage. Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged conditions would equal or exceed 50 percent of the market value of the structure before the damage occurred.

Substantial improvement. Any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure before the "start of construction" of the improvement. This term includes structures which have incurred "substantial damage," regardless of the actual repair work performed. The term does not, however, include either:

1.

Any project for improvement of a structure to correct existing violations of state or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions; or

2.

Any alteration of a "historic structure," provided that the alteration will not preclude the structure's continued designation as a "historic structure."

Variance. A grant of relief from the terms of a flood plain management regulation.

Violation. The failure of a structure or other development to be fully compliant with the community's floodplain management regulations. A structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in this ordinance is presumed to be in violation until such time as that documentation is provided.

Water surface elevation. The height, in relation to the National Geodetic Vertical Datum (NGVD) of 1929, or other datum, of floods of various magnitudes and frequencies in the floodplains of coastal or riverine areas.

(Ord. 98-11; Ord. No. 2013-010, § 1, 7-8-2013; Ord. No. 2023-009, § 2, 4-10-2023; Ord. No. 2026-001, 1, 1-26-2026)

15.25.030 - General provisions.

A.

Lands to which this chapter applies. This chapter shall apply to all special flood hazard areas within the boundaries of the City of Seward.

B.

Basis for establishing special flood hazard areas. The special flood hazard areas identified by the Federal Insurance Administrator in a scientific and engineering report titled "The Flood Insurance Study (FIS) for the Kenai Peninsula Borough, Alaska and Incorporated Areas (City of Seward)" dated September 27, 2013 and October 20, 2016, with accompanying Flood Insurance Rate Maps (FIRMs) dated September 27, 2013 and October 20, 2016, are hereby adopted by reference and declared to be a part of this chapter. The FIS and FIRM panels are available for viewing at City Hall

C.

Compliance. All development within special flood hazard areas is subject to the terms of this ordinance and other applicable regulations.

D.

Abrogation and greater restrictions. This ordinance is not intended to repeal, abrogate or impair any existing easements, covenants or deed restrictions. However, where this ordinance and another ordinance, easement, covenant or deed restriction conflict or overlap, whichever imposes the more stringent restrictions shall prevail.

E.

Interpretation. In the interpretation and application of this chapter, all provisions shall be:

1.

Considered as minimum requirements;

2.

Liberally construed in favor of the governing body; and

3.

Deemed neither to limit nor repeal any other powers granted under state statutes.

F.

Penalties for Non-compliance. Violation of the provisions of this chapter by failure to comply with any of its requirements (including violations of conditions and safeguards established in connection with conditions) shall be subject to a fine as set by the City Council. Nothing herein contained shall prevent the City of Seward from taking such other lawful action as is necessary to prevent or remedy any violation.

G.

Disclaimer of liability. The degree of flood protection required by this chapter is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur on rare occasions. Flood heights may be increased by human-made or natural causes. This chapter does not imply that land outside the special flood hazard areas or uses permitted within such areas will be free from flooding or flood damages. This chapter shall not create liability on the part of the City of Seward, any officer or employee thereof, for any flood damages that result from reliance on this chapter or any administrative decision lawfully made hereunder.

H.

Severability. This chapter and the various parts thereof are hereby declared to be severable. Should any section of this chapter by declared by the courts to be unconstitutional or invalid, such decision shall not affect the validity of the chapter as a whole, or any portion thereof other than the Section so declared to be unconstitutional of invalid.

(Ord. 98-11; Ord. No. 2013-010, § 1, 7-8-2013; Ord. No. 2016-006, § 1, 9-12-2016; Ord. No. 2023-009, § 3, 4-10-2023; Ord. No. 2026-001, 1, 1-26-2026)

15.25.040 - Administration.

A.

Designation of the floodplain administrator. The city manager or designee is hereby appointed to administer, implement and enforce this ordinance by granting or denying development permits in accordance with its provisions. The floodplain administrator may delegate authority to implement these provisions.

B.

Duties and responsibilities of the floodplain administrator. Duties of the floodplain administrator shall include, but not be limited to:

1.

Permit review. Review all development permits to determine that:

a.

The permit requirements of this chapter have been satisfied;

b.

All other required state and federal permits have been obtained;

c.

The site is reasonably safe from flooding;

d.

In areas where a floodway has not been designated, require that no new construction, substantial improvements or other development (including fill) shall be permitted within Zones A1-30 and AE unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one foot at any point within the community.

2.

Use of other base flood data. When base flood elevation data has not been provided in accordance with Section 15.25.030(B), the floodplain administrator shall obtain, review and reasonably utilize any base flood elevation data available from a federal, state or other source, in order to administer section 15.25.050. Any such information shall be consistent with the requirements of the Federal Insurance Administrator.

3.

Obtain and maintain for public inspection. Obtain and maintain the following for public inspection and make available as needed:

a.

Certification required by section 15.25.050(A)(3)(a) (lowest floor elevations for all structures, bottom of the lowest horizontal structural member (if applicable), and service facilities/mechanical equipment);

b.

Certification required by section 15.25.050(A)(3)(b) (lowest floor elevations or floodproofing of non-residential structures and service facilities/mechanical equipment);

c.

Certification required by section 15.25.050(A)(3)(d) (engineered flood openings);

d.

Certification required by section 15.25.050(F)(1) (floodway encroachments);

e.

Records of all variance actions, including justification for their issuance;

f.

Improvement and damage calculations.

4.

Notification to other entities.

a.

Whenever a watercourse is to be altered or relocated, notify adjacent communities and the State Coordinating Office prior to such alteration or relocation of a watercourse, and submit evidence of such notification to the Federal Insurance Administrator through appropriate notification means, and assure that the flood carrying capacity of the altered or relocated portion of said watercourse is maintained.

b.

Base flood elevations may increase or decrease resulting from physical changes affecting flooding conditions. As soon as practicable, but not later than six months after the date such information becomes available, the floodplain administrator shall notify the Federal Insurance Administrator of the changes by submitting technical or scientific data in accordance with Volume 44 Code of Federal Regulations Section 65.3. Such a submission is necessary so that upon confirmation of those physical changes affecting flooding conditions, risk premium rates and floodplain management requirements will be based upon current data.

c.

Notify the Federal Insurance Administrator in writing of acquisition by means of annexation, incorporation or otherwise, of additional areas of jurisdiction.

5.

Remedial actions. Take actions on violations of this chapter as required in Section 15.25.030(F) herein.

C.

Establishment of development permit.

1.

Development permit shall be obtained before construction or development begins within any special flood hazard area established in Section 15.25.030(B).

2.

Application for a development permit may be made on forms furnished by the floodplain administrator and may include, but not be limited to, plans in duplicate drawn to scale showing the nature, location, dimensions and elevation of the area in question, existing or proposed structures, fill, storage of materials, drainage facilities and the location of the foregoing. Specifically, the following information is required:

a.

For A Zones (A, A1-30, AE, AH, AO):

i.

Proposed elevation in relation to mean sea level of the lowest floor (including basement) of all structures. In Zone AO, elevation of existing highest adjacent grade and proposed elevation of lowest floor of all structures;

ii.

Proposed elevation in relation to mean sea level to which any non-residential structure will be floodproofed;

iii.

Certification by a registered professional engineer or architect that the floodproofing methods for any non-residential structure meet the floodproofing criteria in section 15.25.050(A)(3)(b); and

iv.

Description of the extent to which any watercourse will be altered or relocated as a result of proposed development.

b.

For V Zones (VE, V1-30 and V):

i.

Proposed elevation in relation to mean sea level of the bottom of the lowest structural member of the lowest floor (excluding pilings and columns) of all structures, and whether such structures contain a basement;

ii.

Base flood elevation data for subdivision proposals or other development, including manufactured home parks or subdivisions, greater than 50 lots or five acres, whichever is the lesser; and

iii.

Description of the extent to which any watercourse will be altered or relocated as a result of proposed development.

D.

Issuing a development permit.

1.

Upon determination that the submitted and recorded information connected with the permit application meets the terms of this chapter, the administrative official shall issue a floodplain development permit to the original applicant.

2.

If the project involves the construction of a residential structure in a special flood hazard area, the planning department floodplain management office will issue an initial permit based on the building plans in the application. A final permit will be issued after the applicant submits an elevation certificate and floodplain management staff determines that the building is in compliance with all floodplain regulations.

3.

The floodplain development permit shall be valid until the expiration date provided that the start of construction occurs within 180 days of the permit issue date. If construction does not begin within this time period, the permit will expire 180 days from the issue date. The floodplain administrator shall be notified at least three days prior to start of construction for possible site inspection and notice-to-proceed.

4.

The flood plain permit shall be valid for the extent of the project for which it was issued.

5.

The floodplain development permit is not assignable without permission from the administrator.

6.

The city may charge fees for permits and variances. Fees shall be established by resolution of the city council to be paid by the applicant at the time that the floodplain development permit application is submitted.

(Ord. 98-11; Ord. No. 2023-009, § 4, 4-10-2023)

15.25.050 - Provisions for flood hazard reduction.

A.

Standards of construction. In all special flood hazard areas, the following standards are required:

1.

Alteration of watercourses.

a.

The flood carrying capacity within the altered or relocated portion of said watercourse must be maintained; and b. Maintenance must be provided within the altered or relocated portion of said watercourse to ensure that the flood carrying capacity is not diminished; and c. Conditions as stated in 15.25.040(B)(3)(b) and 15.25.040(B)(3)(c) must be met.

2.

Anchoring. All new construction and substantial improvements shall be anchored to prevent flotation, collapse or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy.

3.

Construction materials and methods.

a.

All new construction and substantial improvements shall be constructed with materials resistant to flood damage;

b.

All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage; and

c.

All new construction and substantial improvement shall be constructed with electrical, heating, ventilation, plumbing and air conditioning equipment and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.

d.

Within Zones AH or AO, adequate drainage paths shall be constructed around structures on slopes to guide floodwaters around and away from proposed structures.

4.

Elevation and floodproofing.

a.

Residential construction.

1.

For A Zones (A, AE, A1-30, AH, AO). Residential construction, new or substantial improvement, shall have the lowest floor, including basement, elevated to or above the Base Flood Elevation.

i.

In a Zone AO, the Base Flood Elevation is determined from the FIRM panel as the depth number specified. If no depth is specified, the required elevation is at minimum two feet above highest adjacent grade.

ii.

In a Zone A where the base flood elevation has not been determined, the base flood elevation is determined locally by the criteria set out in Section 15.25.040(B)(2). A minimum of two feet above highest adjacent grade may result in a lower insurance premium.

iii.

In Zones AE, A1-30, and AH, the base flood elevation is determined from the FIS and/or FIRM.

iv.

A garage attached to a residential structure, constructed with the garage floor slab below the base flood elevation, must be designed to allow for the automatic entry and exit of flood waters. See section 15.25.050(A)(3)(d).

Upon completion of the structure, certification by a registered professional engineer or surveyor that the elevation requirements of the lowest floor, including basement, of this section have been satisfied shall be provided to the floodplain administrator for verification.

2.

For V Zones (VE, V1-30 and V). Residential construction, new or substantial improvement, shall:

i.

Be located landward of the reach of mean high tide;

ii.

Have the bottom of the lowest structural member of the lowest floor (excluding pilings and columns), elevated to or above the base flood elevation;

iii.

Have the pile or column foundation and structure attached thereto be anchored to resist flotation, collapse and lateral movement due to the effects of wind and water loads acting simultaneously on all building components. Water loading values used shall be those associated with the base flood. Wind loading values used shall be those required by applicable State or local building standards. Construction of structures with timber piling, posts, or piers as the sole structural support, is prohibited except for docks, wharves, and other engineered stand-alone structures expressly approved by the building official in accordance with the International Building Code as adopted by the city.

iv.

Have the space below the lowest floor, usable solely for parking of vehicles, building access, or storage, either free of obstruction or constructed with non-supporting breakaway walls, open wood lattice-work, or insect screening intended to collapse under wind and water loads without causing collapse, displacement, or other structural damage to the elevated portion of the building or supporting foundation system. For the purposes of this section, a breakaway wall shall have a design safe loading resistance of not less than ten and no more than 20 pounds per square foot;

v.

Prohibit the use of fill for structural support of buildings; and

vi.

Prohibit human-made alteration of sand dunes and mangrove stands.

A registered professional engineer or architect shall develop or review the structural design, specifications and plans for the construction, and shall certify that the design and methods of construction to be used are in accordance with accepted standards of practice for meeting the provisions of this section.

Upon completion of construction, certification by a registered professional engineer or architect that these design standards have been satisfied, and certification by a registered professional engineer or surveyor that the elevation requirements of the bottom of the lowest structural member of the lowest floor, excluding pilings and columns, of this section have been satisfied shall be provided to the floodplain administrator for verification.

b.

Non-residential construction. For A Zones (A, AE, A1-30, AH, AO): Non-residential construction, new or substantial improvement, shall have the lowest floor either elevated to conform with section 15.25.050(A)(3)(a) subsections (i), (ii) or (iii) as appropriate, or, together with attendant utility and sanitary facilities,

i.

Be floodproofed below the elevation recommended under section 15.25.050(A)(3)(a) subsections (i), (ii) or (iii) as appropriate so that the structure is watertight with walls substantially impermeable to the passage of water; and

ii.

Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy.

iii.

A registered professional engineer or architect shall develop and/or review structural design, specifications, and plans for the construction, and shall certify that the design and methods of construction are in accordance with accepted standards of practice meeting the provisions listed above.

Upon completion of the structure, certification by a registered professional engineer or surveyor that the elevation requirements of the lowest floor, including basement, of this section have been satisfied shall be provided to the floodplain administrator for verification; or certification by a registered professional engineer or architect that the floodproofing design of this section is satisfied, including the specific elevation in relation to mean sea level to which such structures are floodproofed, shall be provided to the floodplain administrator for verification.

For V Zones (VE, V1-30, V). Floodproofing of non-residential structures is prohibited. All structures must be elevated and constructed according to the requirements set forth in section 15.25.050(A)(3)(a).

c.

Appurtenant structures (detached garages and storage structures).

1.

For A Zones (A, AE, A1-30, AH, AO).

a.

Appurtenant structures used solely for parking of vehicles or storage may be constructed such that the floor is below the base flood elevation, provided the structure is designed and constructed in accordance with the following requirements:

i.

Use of the appurtenant structure must be limited to parking of vehicles or storage;

ii.

The portions of the appurtenant structure located below the base flood elevation must be built using flood resistant materials;

iii.

The appurtenant structure must be adequately anchored to prevent flotation, collapse and lateral movement;

iv.

Any machinery or equipment servicing the appurtenant structure must be elevated or floodproofed to or above the base flood elevation;

v.

The appurtenant structure must comply with floodway encroachment provisions in 15.25.050(F); and

vi.

The appurtenant structure must be designed to allow for the automatic entry and exit of flood waters in accordance with section 15.25.050(A)(3)(d).

b.

Detached garages, storage structures and other appurtenant structures not meeting the above standards must be constructed in accordance with all applicable standards in section 15.25.050(A)(3)(a) subsections (i), (ii) or (iii) as appropriate.

c.

Upon completion of the structure, certification that the requirements of this section have been satisfied shall be provided to the floodplain administrator for verification.

2.

For V Zones (VE, V1-30 and V): Floodproofing of non-residential structures is prohibited. All structures must be elevated and constructed according to the requirements set forth in section 15.25.050(A)(3)(a).

d.

Flood openings. All new construction and substantial improvement with fully enclosed areas below the lowest floor (excluding basements) that are usable solely for parking of vehicles, building access or storage, and which are subject to flooding, shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the automatic entry and exit of floodwater. Designs for meeting this requirement must meet or exceed the following criteria: For non-engineered openings:

i.

Have a minimum of two openings with a total net area of not less than one square inch for every square foot of enclosed area subject to flooding;

ii.

The bottom of all openings shall be no higher than one foot above grade;

iii.

Openings may be equipped with screens, louvers, valves, or other coverings or devices provided that they permit the automatic entry and exit of floodwater.

Alternatively, a registered engineer or architect may design and certify engineered openings.

Upon completion of the structure, certification that the requirements of this section have been satisfied shall be provided to the Floodplain Administrator for verification.

B.

Standards for storage of materials and equipment.

1.

The storage or processing of materials that could be injurious to human, animal or plant life if released due to damage from flooding is prohibited in special flood hazard areas.

2.

Storage of other material or equipment may be allowed if not subject to damage by floods and if firmly anchored to prevent flotation, or if readily removable from the area within the time available after flood warning.

C.

Standards for water supply and waste disposal systems.

1.

All new or replacement water supply and sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the system and discharge from systems into flood waters.

2.

On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.

D.

Development proposals. All new development proposals, including subdivisions and manufactured home parks, shall:

1.

Be consistent with the need to minimize flood damage;

2.

Have public utilities and facilities such as sewer, gas, electrical and water systems located and constructed to minimize flood damage; and

3.

Provide adequate drainage to reduce exposure to flood hazards.

4.

Include base flood elevation data for all proposals greater than 50 lots or five acres, whichever is the lesser.

E.

Standards for recreational vehicles. All recreational vehicles placed on site shall:

1.

Be on site for fewer than 180 consecutive days,

2.

Be fully licensed and ready for highway use. A recreational vehicle is ready for highway use if it is on its wheels or jacking system, is attached to the site only by quick disconnect type utilities and security devices, and has no permanently attached additions; or

3.

Meet the permit requirements of section 15.25.040 of this ordinance and the applicable elevation and anchoring requirements. Methods of anchoring may include, but are not to be limited to, use of over-the-top or frame ties to ground anchors. The recreational vehicle must also be elevated on a permanent foundation such that the lowest floor of the vehicle is elevated to or above the base flood elevation and be securely anchored to an adequately anchored foundation system to resist floatation collapse and lateral movement. These requirements are in addition to applicable State and local anchoring requirements for resisting wind forces.

F.

Floodways. Located within the special flood hazard areas established in section 15.25.030(B) are areas designated as floodways. Since the floodway is an extremely hazardous area due to the velocity of floodwaters which carry debris, potential projectiles and erosion potential, the following provisions apply:

1.

Prohibit encroachments, including fill, new construction, substantial improvements, and other development within the adopted regulatory floodway unless it has been demonstrated through hydrologic and hydraulic analyses performed in accordance with standard engineering practice that the proposed encroachment would not result in any increase in flood levels within the community during the occurrence of the base flood discharge;

2.

If section 15.25.050(F)(1) is satisfied, all new construction and substantial improvements shall comply with all other applicable flood hazard reduction provisions of section 15.25.050.

3.

Encroachments within the adopted regulatory floodway that would result in an increase in base flood elevations may be permitted, provided that the applicant first applies for and fulfills the requirements for a Conditional Letter of Map Revision (CLOMR), and receives approval from the Federal Insurance Administrator to revise the FIRM and FIS in accordance with Section 15.25.040(B)(4)(b).

(Ord. 98-11; Ord. No. 2013-010, § 1, 7-8-2013; Ord. No. 2023-009, § 5, 4-10-2023; Ord. No. 2026-001, 1, 1-26-2026)

15.25.060 - Variance procedure.

A.

Nature of variances.

1.

The variance criteria set forth in this section of the ordinance are based on the general principle of zoning law that variances pertain to a piece of property and are not personal in nature. A variance may be granted for a parcel of property with physical characteristics so unusual that complying with the requirements of this ordinance would create an exceptional hardship to the applicant or the surrounding property owners. The characteristics must be unique to the property and not be shared by adjacent parcels. The unique characteristic must pertain to the land itself, not to the structure, its inhabitants or the property owners.

2.

Variances from the flood elevation or from other requirements in the flood ordinance are quite rare. The long-term goal of preventing and reducing flood loss and damage can only be met if variances are strictly limited. Therefore, the variance guidelines provided in this ordinance are more detailed and contain multiple provisions that must be met before a variance can be properly granted. The criteria are designed to screen out those situations in which alternatives other than a variance are more appropriate.

B.

Conditions for variances.

1.

Variances shall only be issued:

a.

On a determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisances, cause fraud on or victimization of the public or conflict with existing local laws or ordinances;

b.

For the repair, rehabilitation or restoration of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum necessary to preserve the historic character and design of the structure;

c.

Upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief;

d.

Upon a showing of good and sufficient cause;

e.

Upon a determination that failure to grant the variance would result in exceptional hardship to the applicant;

f.

Upon a showing that the use cannot perform its intended purpose unless it is located or carried out in close proximity to water. This includes only facilities defined in section 15.25.020 of this chapter in the definition of "functionally dependent use."

2.

Variances shall not be issued within any floodway if any increase in flood levels during the base flood discharge would result.

3.

Generally, variances may be issued for new construction and substantial improvements to be erected on a lot of one-half acre or less in size contiguous to and surrounded by lots with existing structures constructed below the base flood elevation, provided the procedures of sections 15.25.040 and 15.25.050 of this chapter have been fully considered. As the lot size increases beyond one-half acre, the technical justification required for issuing the variance increases.

C.

Variance criteria.

1.

In considering variance applications, the appeal board shall consider all technical evaluations, all relevant factors, standards specified in other sections of this chapter, and:

a.

The danger that materials may be swept onto other lands to the injury of others;

b.

The danger of life and property due to flooding or erosion damage;

c.

The susceptibility of the proposed facility and its contents to flood damage and the effect of such damage on the individual owner;

d.

The importance of the services provided by the proposed facility to the community;

e.

The necessity to the facility of a waterfront location, where applicable;

f.

The availability of alternative locations for the proposed use, which are not subject to flooding or erosion damage;

g.

The compatibility of the proposed use with existing and anticipated development;

h.

The relationship of the proposed use to the comprehensive plan and floodplain management program for that area;

i.

The safety of access to the property in time of flood for ordinary and emergency vehicles;

j.

The expected heights, velocity, duration, rate of rise, and sediment transport of the flood waters and the effects of wave action, if applicable, expected at the site; and,

k.

The costs of providing governmental services during and after flood conditions, including maintenance and repair of public utilities and facilities such as sewer, gas, electrical, water system and streets and bridges.

2.

Any applicant to whom a variance is granted shall be given written notice over the signature of a community official that:

a.

The issuance of a variance to construct a structure below the base flood elevation will result in increased premium rates for flood insurance up to amounts as high as $25.00 for $100.00 of insurance coverage, and

b.

Such construction below the base flood elevation increases risks to life and property.

3.

The floodplain administrator shall maintain a record of all variance actions, including justification for their issuance.

D.

Appeal procedure.

1.

Appeal board.

a.

The Seward Planning and Zoning Commission (commission) shall hear and decide appeals and requests for variances from the requirements of this chapter.

b.

The commission shall hear and decide appeals when it is alleged there is an error in any requirement, decision, or determination made by the administrative official in the enforcement or administration of this chapter.

c.

Those aggrieved by the decision of the commission, or any taxpayer, may appeal such decision to the city council sitting as board of adjustment, as provided in AS 29.40.050.

(Ord. 98-11; Ord. No. 2023-009, § 6, 4-10-2023)