- SOLAR AND BATTERY FACILITIES
The purpose of this article is to establish requirements for construction and operation of solar and battery facilities and to provide standards for the placement, design, construction, monitoring, modification, and removal of solar facilities; address public safety, minimize impacts on scenic, natural, and historic resources; and provide adequate financial assurance for decommissioning.
(Ord. of 2-17-2022, § 16-401)
This article shall apply to all solar and battery facilities constructed after the effective date of the ordinance from which this article is derived, including any physical modifications to any existing solar facilities that materially alter the type, configuration, or size of such facilities or other equipment.
(Ord. of 2-17-2022, § 16-402)
(a)
Rooftop and small-scale solar facilities may be installed by right in all zoning districts as an accessory use to provide electricity to individual structures; provided a site plan (as applicable) has been submitted to the zoning administrator for review and approval; all federal, state, and local regulations have been followed; and the system is located upon the property or structure being served. Rooftop facilities on commercial or industrial buildings shall also submit an engineering study to the building official's office for review and approval.
(b)
Medium-scale solar facilities may be installed by right as an accessory use in the industrial districts to provide electricity for use on-site for commercial and industrial applications; provided a site plan has been submitted to the zoning administrator for review and approval; all federal, state and local regulations have been followed; the system is located on the property or structure to be served; and the system is in accord with the underlying zoning requirements of the districts.
(c)
Solar facilities shall be permitted in zoning districts as follows:
(d)
Battery facilities shall be subject to a conditional use permit and permitted as follows:
(1)
An accessory use to utility-scale solar facilities, other energy generation facilities, or substations; or
(2)
A primary use on a parcel contiguous to utility-scale solar facilities, other energy generation facilities, and substations.
(e)
Solar facilities should locate on brownfields, county-owned capped landfills, or near existing industrial uses, where feasible.
(Ord. of 2-17-2022, § 16-403)
(a)
Pre-application meeting. A pre-application meeting shall be held with the zoning administrator to discuss the location, scale, and nature of the proposed use, what will be expected during that process, and the potential for a siting agreement.
(b)
Neighborhood meeting. A public meeting shall be held prior to the public hearing with the planning commission to give the community an opportunity to hear from the applicant and ask questions regarding the proposed project.
(1)
The applicant shall inform the zoning administrator's office and adjacent property owners in writing of the date, time, and location of the meeting at least seven days but no more than 14 days in advance of the meeting date.
(2)
The date, time, and location of the meeting shall be advertised in the county's newspaper of record by the applicant at least seven days but no more than 14 days in advance of the meeting date.
(3)
The meeting shall be held within the county at a location open to the general public with adequate parking and seating facilities which may accommodate persons with disabilities.
(4)
The meeting shall give members of the public the opportunity to review application materials, ask questions of the applicant, and provide feedback.
(5)
The applicant shall provide to the zoning administrator a summary of any input received from members of the public at the meeting.
(c)
Submittal of the permit application and fees.
(1)
There is a combined application for the 2232 review and CUP permit.
(2)
There are separate fees for the 2232 review and CUP permit.
(d)
2232 review. Code of Virginia, §15.2-2232 requires a review of public utility facility proposals by the planning commission to determine if their general or approximate location, character, and extent are substantially in accord with the comprehensive plan or part thereof.
(1)
The planning commission must determine, at a public meeting, whether the project is in substantial accord with the comprehensive plan. Failure of the planning commission to act within 60 days of submission, unless the time is extended by the board of supervisors, shall be deemed approval.
a.
If the planning commission approves the 2232 review, the project shall be recommended for a public hearing for the CUP permit.
b.
If the planning commission does not approve the 2232 review, the applicant may appeal the decision to the board of supervisors within ten days after the decision of the planning commission. The appeal shall be by written petition to the board of supervisors setting forth the reasons for the appeal. The appeal shall be heard and determined within 60 days from its filing unless the time is extended by the applicant. A majority vote of the board of supervisors shall overrule the planning commission.
(2)
If the board of supervisors agree to negotiate a siting agreement in accordance with Code of Virginia, § 15.2-2316.8, the 2232 review process may be delayed until negotiations are complete. If the siting agreement is approved, it fulfills the requirement for a 2232 review.
(3)
Consideration of the conditional use permit by the planning commission. The planning commission must consider the conditional use permit application at a public hearing. The planning commission has three options:
a.
Recommend approval of the application to the board of supervisors to include recommendation conditions, if applicable.
b.
Recommend denial of the application to the board of supervisors with written reasons for its decision.
c.
Defer the application for further discussion and consideration.
(4)
Consideration of the conditional use permit by the board of supervisors. The board of supervisors must consider the conditional use permit application at a public hearing. The board of supervisors has three options:
a.
Approve the application to include recommended conditions, if applicable.
b.
Deny the application with written reasons for its decision.
c.
Defer the application for further discussion and consideration.
(5)
Siting agreement. The process may also include negotiating a siting agreement in accordance with Code of Virginia, § 15.2-2316.8. The board of supervisors must consider the siting agreement at a public hearing. An approved siting agreement fulfills the requirement for a 2232 review (Code of Virginia, § 15.2-2232).
(Ord. of 2-17-2022, § 16-404)
Applications for a conditional use permit shall include:
(1)
An application packet including:
a.
Completed county application form and checklist.
b.
Documents demonstrating the ownership of the subject parcels.
c.
Proof that the applicant has authorization to act upon the owner's behalf.
d.
Identification of the intended utility company who will interconnect to the facility.
e.
List of all adjacent property owners, their tax map numbers, and addresses.
f.
A description of the current use and physical characteristics of the subject parcels.
g.
A description of the existing uses of nearby properties.
h.
A narrative identifying the applicant, owner, or operator, and describing the proposed solar facility project, including an overview of the project and its location, approximate rated capacity of the solar facility project, the approximate number of panels, representative types, expected footprint of solar equipment to be constructed, and type and location of interconnection to electrical grid.
i.
Aerial imagery which shows the proposed location of the solar facility, fenced area, driveways, and interconnection to electrical grid with the closest distance to all adjacent property lines and dwellings along with main points of ingress/egress.
j.
Payment of the application fee and any additional review costs, advertising, or other required staff time.
(2)
Concept plan. A concept plan prepared by an engineer with a professional engineering license in the commonwealth, that shall include the following:
a.
Project title information including tax parcel number, zoning, owner names, addresses, and phone numbers.
b.
Neighboring property information including tax parcel number, zoning, and owner names.
c.
Existing wetlands, waterways, and floodplains.
d.
Locations and types of soils on site.
e.
Areas of steep slopes.
f.
Existing and proposed buildings and structures including preliminary locations of the proposed solar panels and related equipment.
g.
Existing and proposed points of ingress/egress including access roads, drives, turnout locations, and parking.
h.
Location of substations, electrical cabling from the solar facility systems to the substations, ancillary equipment, buildings, and structures including those within any applicable setback.
i.
Fencing or other methods of ensuring public safety.
j.
Locations of topsoil to be removed and preserved.
k.
Locations of stormwater drainage and erosion and sediment control features.
l.
Setbacks.
m.
The location and nature of proposed buffers and screening elements, including vegetative and constructed buffers.
(3)
An estimated construction schedule.
(4)
Environmental inventory and impact statement regarding any site and viewshed impacts, including direct and indirect impacts to national and state forests, national or state parks, wildlife management areas, conservation easements, recreational areas, or any known historic or cultural resources within three miles of the proposed project using information provided by the state department of environmental quality (DEQ), the state department of conservation and recreation (DCR), state department of wildlife resources (DWR), state department of historic resources (DHR), and/or a report prepared by a qualified third party, such as ConserveVirginia or Virginia Cultural Resource Information System.
(5)
A visual impact analysis demonstrating project siting and proposed mitigation, if necessary, so that the solar facility minimizes impact on the visual character of the county.
a.
The applicant shall provide accurate, to scale, photographic simulations showing the relationship of the solar facility and its associated amenities and development to its surroundings. The photographic simulations shall show such views of solar structures from locations such as property lines and roadways, as deemed necessary by the county in order to assess the visual impact of the solar facility.
b.
The total number of simulations and the perspectives from which they are prepared shall be established by the zoning administrator after the pre-application meeting.
(6)
Solar facility inventory. An inventory of all solar facilities, existing or proposed, within a four-mile radius.
(7)
Draft traffic study. The study shall include modelling the construction and decommissioning processes. County staff will review the study in cooperation with the Virginia Department of Transportation (VDOT).
(8)
Draft landscaping plan. The plan shall indicate:
a.
All ground cover, screening and buffering materials, landscaping, and elevations.
1.
Ground cover shall be native vegetation where compatible with site conditions.
2.
Screening vegetation shall include pollinator plants where compatible with site conditions.
3.
Only EPA approved herbicides shall be used for vegetative and weed control at the solar energy facility by a licensed applicator. No herbicides shall be used within 150 feet of the location of an approved groundwater well. The applicant shall submit an herbicide land application plan prior to approval of the certificate of occupancy (or equivalent). The plan shall specify the type of herbicides to be used, the frequency of land application, the identification of approved groundwater wells, wetlands, and streams, and the distances from land application areas to features such as wells, wetlands, streams, and other bodies of water. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
b.
Locations of wildlife corridors.
c.
Maintenance requirements.
(9)
Draft decommissioning and reclamation plan. A detailed decommissioning and reclamation plan, certified by an engineer, which shall include the following:
a.
The anticipated life of the project. The applicant shall provide the basis for determining the anticipated life of the project.
b.
The estimated decommissioning and reclamation cost in current dollars. The applicant shall provide a cost estimate for the decommissioning and reclamation of the facility prepared by a professional engineer or contractor who has expertise in the removal of solar facilities. The decommissioning and reclamation cost estimate shall explicitly detail the cost without any reduction for salvage value.
c.
The method of ensuring that funds will be available for decommissioning and reclamation. A proposed method of providing appropriate escrow, surety, or security for the cost of the decommissioning and reclamation plan. The surety shall be updated when the decommissioning and reclamation cost estimate is updated. The estimated cost of decommissioning shall be guaranteed by the deposit of funds in an amount equal to the estimated cost in an escrow account at a federally insured financial institution approved by the county unless otherwise provided for in subsection (9)c.4 of this section.
1.
The applicant shall deposit the required amount into the approved escrow account before any building permit is issued to allow construction of the solar facility.
2.
The escrow account agreement shall prohibit the release of the escrow funds without the written consent of the county. The county shall consent to the release of the escrow funds upon the owner's or occupant's compliance with the approved decommissioning and reclamation plan. The county may approve the partial release of escrow funds as portions of the approved decommissioning plan are performed.
3.
The amount of funds required to be deposited in the escrow account shall be the full amount of the estimated decommissioning and reclamation cost.
4.
The county may approve alternative methods to secure the availability of funds to pay for the decommissioning and reclamation of a solar facility, such as a performance bond, letter of credit, or other security approved by the county.
d.
The method that the estimated cost will be kept current. The decommissioning and reclamation cost estimate shall include a mechanism for calculating increased removal costs due to inflation. This cost estimate shall be recalculated every five years and the surety shall be updated accordingly. If the recalculated estimated cost exceeds the original estimated cost by ten percent, then the owner or occupant shall deposit additional funds into the escrow account to meet the new cost estimate. If the recalculated estimated cost is less than 90 percent of the original estimated cost, then the county may approve reducing the amount of the escrow account to the recalculated estimate of cost.
e.
The manner in which the site will be decommissioned and reclaimed. This will include:
1.
Notice to the zoning administrator by certified mail and in person of the proposed date of discontinued operations and plans for removal.
2.
A traffic study submitted with application modelling the decommissioning processes. County staff will review the study in cooperation with VDOT.
3.
An estimated deconstruction schedule.
4.
Removal of all solar electric systems, buildings, cabling, electrical components, security barriers, roads, foundations, pilings, and any other associated facilities, so that any agricultural ground upon which the facility and/or system was located is again tillable and suitable for agricultural or forestall uses.
5.
The site shall be graded and re-seeded or replanted within 12 months of removal of solar facilities to restore it to as natural a pre-development condition as possible. Re-grading and re-seeding or replanting shall be initiated within a six-month period of removal of equipment. Any exception to site restoration, such as leaving access roads in place or re-seeded or replanted, must be requested by the landowner in writing, and this request must be approved by the board of supervisors.
6.
Hazardous material from the property shall be disposed of in accordance with federal and state law.
(10)
Additional information may be required as determined by the zoning administrator, such as a scaled elevation view of the property and other supporting drawings, photographs of the proposed site, photo or other realistic simulations or modeling of the proposed project from potentially sensitive locations as deemed necessary by the zoning administrator to assess the visual impact of the project, landscaping plan, coverage map, and additional information that may be necessary for a technical review of the proposal.
(Ord. of 2-17-2022, § 16-405)
(a)
Generally. A utility-scale solar facility shall be constructed, operated, and maintained in substantial compliance with the approved concept plan with allowances for changes required by the state department of environmental quality (DEQ) permit by rule (PBR) or state corporation commission (SCC) permit process.
(b)
Location standards for utility-scale solar facilities. The location standards stated in this subsection for utility-scale solar facilities are intended to mitigate the adverse effects of such uses on adjoining property owners, the area, and the county.
(1)
The minimum area of a utility-scale solar facility shall be 100 acres or more.
(2)
The equipment, improvements, structures, and percent of acreage coverage of a utility-scale solar facility shall be shown on the approved concept plan and site plan. The percent of acreage coverage shall not exceed 65 percent.
(c)
Height.
(1)
The maximum height of the lowest edge of photovoltaic panels shall be ten feet as measured from the finished grade. The maximum height of the highest edge of photovoltaic panels shall not exceed 15 feet as measured from the finished grade.
(2)
The maximum height of other facility structures shall not exceed 15 feet. This limit shall not apply to utility poles or the interconnection to the overhead electric utility grid.
(3)
The board of supervisors may approve a greater height based upon the demonstration of a significant need where the impacts of increased height are mitigated.
(d)
Setbacks. Solar facilities shall meet all setback requirements for primary structures for the zoning district in which the facility is located and the requirements set forth in this subsection (the more restrictive requirements shall apply).
(1)
The minimum setback of structures and uses associated with the facility, including fencing, PV panels, parking areas, and outdoor storage, but not including landscaping and berming, shall be:
a.
150 feet from adjacent property lines.
b.
150 feet from all public rights-of-way.
c.
300 feet from a dwelling.
(2)
The planning commission or board of supervisors may require increased setbacks up to 400 feet in situations where the height of structures or the topography affects the visual impact of the facility.
(3)
These setback requirements shall not apply to internal property lines of those parcels on which a solar facility is located.
(4)
Access, erosion and stormwater structures, and interconnection to the electrical grid may be made through setback areas provided that such are generally perpendicular to the property line.
(5)
Vehicular access to the site shall be a minimum of 50 feet from the nearest dwelling located on adjacent property.
(e)
Buffer. The buffer shall be located within the setbacks required under this section and shall run around the entire perimeter of the property. The buffer shall be maintained for the life of the facility.
(f)
Screening. The facilities, including security fencing that is not ornamental, shall be screened from the ground-level view of adjacent properties or a public street in the buffer zone. Screening may also be required in other locations to screen specific uses or structures. A recommendation that the screening and/or buffer creation requirements be waived or altered may be made by the planning commission when the applicant proposes to use existing wetlands or woodlands to satisfy the screening requirement. The wetlands or woodlands shall be permanently protected as a designated buffer and the overall buffer shall measure at least 150 feet. Screening methods may include:
(1)
Existing screening. Existing vegetation, topography, buildings, open space, or other elements located on the site may be considered as part of the required screening. Existing trees and vegetation may be retained within the buffer area except where dead, diseased, or as necessary for development or to promote healthy growth.
(2)
Vegetative screening. In the event existing vegetation or landforms providing the screening are inadequate or disturbed, new plantings shall be provided in a landscaped strip at least 50 feet wide. Landscaping intended for screening shall consist of a combination of non-invasive species, pollinator species, and native plants, shrubs, trees, grasses, forbs, and wildflowers. Trees intended for screening shall consist of a combination of evergreen and deciduous trees that are five to six feet in height at time of planting. A triple row of trees shall be placed on average at 15 feet on center. A list of appropriate plant materials shall be available at the planning office. Species listed on DCR's invasive plant species list shall not be used.
(3)
Berming. Berms shall generally be constructed with a 3:1 side slope to rise ratio, four to six feet above the adjacent grade, with a three-foot-wide top with appropriate pollinator-friendly native plants, shrubs, trees, forbs, and wildflowers. The outside edges of the berm shall be sculpted such that there are vertical and horizontal undulations to give variations in appearance. When completed, the berm should not have a uniform appearance like a dike.
(4)
Opaque architectural fencing. Fencing intended for screening shall be at least 75 percent visually solid as viewed on any line perpendicular to the fence from adjacent property or a public street. Such fencing may be used in combination with other screening methods but shall not be the primary method. A typical example is the use of wood privacy fencing and landscaping to screen structures such as substations. Depending on the location, ornamental features may be required on the fence. Fencing material shall not include plastic slats.
(g)
Security fence. The facilities shall be enclosed by security fencing not less than six feet in height and topped with barbed wire, as appropriate. A performance bond reflecting the costs of anticipated fence maintenance shall be posted and maintained. Failure to maintain the security fencing shall result in revocation of the CUP and the facility's decommissioning.
(h)
Ground cover. Ground cover on the site shall be native vegetation and maintained in accordance with the landscaping plan in accordance with established performance measures. A performance bond reflecting the costs of anticipated maintenance shall be posted and maintained. Failure to maintain the ground cover shall result in revocation of the CUP and the facility's decommissioning. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
(i)
Access corridors. The applicant shall identify access corridors for wildlife to navigate through and across the solar facility. The proposed wildlife corridors shall be shown on the site plan submitted to the county. Areas between fencing shall be kept open to allow for the movement of migratory animals and other wildlife.
(j)
Support buildings. The design of support buildings and related structures shall use materials, colors, textures, screening, and landscaping that will blend the facilities to the natural setting and surrounding structures.
(k)
Maintenance. The owner or operator shall maintain the solar facility in good condition. Such maintenance shall include, but not be limited to, painting, structural integrity of the equipment and structures, as applicable, and maintenance of the buffer areas and landscaping. Site access shall be maintained to a level acceptable to the county. The project owner shall be responsible for the cost of maintaining the solar facility and access roads, and the cost of repairing damage to private roads occurring as a result of construction and operation.
(l)
Inspections.
(1)
The applicant will allow designated county representatives or employees access to the facility for inspection purposes with 24-hour notice.
(2)
The applicant shall reimburse the county its costs in obtaining an independent third party to conduct inspections required by local and state laws and regulations.
(m)
Design, maintenance of utility-scale facility. A utility-scale solar facility shall be designed and maintained in compliance with standards contained in applicable local, state, and federal building codes and regulations that were in force at the time of the permit approval.
(n)
Liability insurance. The applicant shall provide proof of adequate liability insurance for a solar facility prior to beginning construction and before the issuance of a zoning or building permit to the zoning administrator.
(o)
Lighting. Lighting fixtures as approved by the county shall be the minimum necessary for safety and/or security purposes to protect the night sky by facing downward and to minimize off-site glare. No facility shall produce glare that would constitute a nuisance to the public. Any exceptions shall be enumerated on the concept plan and approved by the zoning administrator.
(p)
Signage. No signage of any type may be placed on the facility other than notices, warnings, and identification information required by law.
(q)
Noise. At all times, the solar facility shall comply with the county's noise regulations set forth in chapter 20, article III.
(r)
Coordination of local emergency services. Applicants for new solar facilities shall coordinate with the county's emergency services staff to provide materials, education and/or training to the departments serving the property with emergency services in how to safely respond to on-site emergencies.
(s)
Decommissioning.
(1)
Solar facilities which have reached the end of their useful life or have not been in active and continuous service for a period of six months shall be removed at the owner's or operator's expense, except if the project is being repowered or a force majeure event has or is occurring requiring longer repairs; however, the county may require evidentiary support that a longer repair period is necessary.
(2)
The owner or operator shall notify the zoning administrator by certified mail and in person of the proposed date of discontinued operations and plans for removal.
(3)
Decommissioning shall include removal of all solar electric systems, buildings, cabling, electrical components, security barriers, roads, foundations, pilings, and any other associated facilities, so that any agricultural ground upon which the facility and/or system was located is again tillable and suitable for agricultural or forestall uses. The site shall be graded and re-seeded to restore it to as natural a pre-development condition as possible or replanted with pine seedlings to stimulate pre-timber pre-development conditions as indicated on the concept plan. Any exception to site restoration, such as leaving access roads in place or seeding instead of planting seedlings must be requested by the landowner in writing, and this request must be approved by the board of supervisors.
(4)
The site shall be re-graded and re-seeded or replanted within 12 months of removal of solar facilities. Re-grading and re-seeding or replanting shall be initiated within a six-month period of removal of equipment.
(5)
Decommissioning and reclamation shall be performed in compliance with the approved decommissioning and reclamation plan. The board of supervisors may approve any appropriate amendments to or modifications of the decommissioning plan.
(6)
Hazardous material from the property shall be disposed of in accordance with federal and state law.
(7)
If the owner or operator of the solar facility fails to remove the installation in accordance with the requirements of this permit or within the proposed date of decommissioning, the county may collect the surety and the county or hired third party may enter the property to physically remove the installation.
(t)
Additional conditions. Any other condition may be added by the planning commission or board of supervisors as part of a CUP approval.
(Ord. of 2-17-2022, § 16-406)
In addition to the above general provisions, application requirements, and development and performance standards, the following additional requirements shall be met for the approval of a battery energy storage facility:
(1)
Battery energy storage facilities shall be constructed, maintained, and operated in accordance with national industry standards and regulations, including the most current adopted edition of the National Electrical Code, International Fire Code of the International Code Council, and the National Fire Protection Association Fire Code. The batteries will be NFPA (National Fire Protection Agency) complaint. In the event of a conflict between the national industry standards and these conditions, the national industry standards shall control so that as technology advances, updated technology may be used.
(2)
Battery cells shall be placed in a battery energy storage system (BESS) with a battery management system (BMS). The BESS shall provide a secondary layer of physical containment to the batteries and be equipped with cooling, ventilation, and fire suppression systems. Each individual battery shall have 24/7 automated fire detection and extinguishing technology built in. The BMS shall monitor individual battery module voltages and temperatures, container temperature and humidity, off-gassing of combustible gas, fire, ground fault and DC surge, and door access and be able to shut down the system before thermal runaway takes place.
(3)
The battery energy storage system will be placed on an appropriate foundation and screened with vegetation outside of environmentally sensitive areas.
(4)
Access to all batteries and electrical switchgear shall be from the exterior for normal operation and maintenance. Access to the container interior shall not be permitted while the system is in operation except for safety personnel and first responders.
(5)
Qualifications and experience from selected developers and integrators shall be provided including disclosure of fires or other hazards at facilities.
(6)
Safety testing and failure modes analysis data from selected developers and manufacturers shall be provided.
(7)
The latest applicable product certifications shall be provided.
(8)
The solar facility operator or owner shall be responsible for any environmental remediation required by the county or the state and the costs of such remediation. All remediation shall be completed in a timely manner.
(9)
Battery storage shall be developed in collaboration with technical experts and first responders to utilize technology-appropriate best practices for safe energy storage systems, including, but not limited to, the following:
a.
Adequate access/egress for the first responders;
b.
Adequate facility signage (on battery chemistry and person to contact);
c.
Accessible safety data sheets;
d.
System-specific emergency response plans;
e.
Training for first responders on the type of system, potential hazards and risks, and system-specific emergency response plans;
f.
Adequate water sources and fire suppression appliances for the firefighters if required in the emergency response plans;
g.
Signage on hazardous materials present in the vicinity;
h.
Emergency lighting;
i.
Separate battery modules to make it easier to isolate a failed battery from the rest;
j.
Sufficient disconnect and shutdown capability including a master kill switch to disable and discharge batteries;
k.
System-appropriate sensors and alarms;
l.
Air ventilation and fire suppression systems;
m.
Drainage for water runoff; and
n.
Other practices as recommended by experts or local first responders.
(10)
The solar facility operator or owner shall conduct regular on-site inspections of the battery units and submit a written report to the zoning administrator on their condition, at least once every six months. The solar facility operator or owner shall conduct monthly inspections electronically of the battery units and submit a written report to the zoning administrator.
(Ord. of 2-17-2022, § 16-407)
In addition to the above general provisions, application requirements, and development and performance standards, the following additional requirements shall be met for the approval of a substation:
(1)
Siting. Substations located within the solar facility shall be sited in accordance with these regulations.
(2)
Term and special permits. Substations included as part of the solar facility shall have the same term as the solar facility. However, substations may have a life longer than that of the larger solar facility, and, alternatively, may individually and not as part of a solar facility receive a conditional use permit in accordance with these regulations.
(Ord. of 2-17-2022, § 16-408)
(a)
The board of supervisors may consider conditions addressing a proposed solar and/or battery facility, including, but not limited to, the following:
(1)
A solar facility shall be constructed, maintained, and operated in substantial compliance with:
a.
The development standards under this article.
b.
The approved concept plan.
c.
Any other conditions imposed pursuant to a conditional use permit.
(2)
The board of supervisors may, in its sole discretion, by conditional use permit, waive or modify requirements set out in this article for solar or battery storage facilities, based on unique site conditions, if it finds that such waiver or modification promotes good land use planning and is compatible with surrounding land uses, and as long as the project still otherwise complies with applicable state law and local ordinances.
(b)
Site plan requirements. In addition to all state site plan requirements and site plan requirements of the zoning administrator, the applicant shall provide the following plans for review and approval for the solar facility prior to the issuance of a building permit:
(1)
Construction management plan. The applicant shall prepare a construction management plan for each applicable site plan for the solar facility, and each plan shall address the following:
a.
Traffic control methods (in coordination with the Virginia Department of Transportation (VDOT) prior to initiation of construction):
1.
Lane closures.
2.
Signage.
3.
Flagging procedures.
b.
Site access planning. Directing employee and delivery traffic to minimize conflicts with local traffic.
c.
Site security. The applicant shall implement security measures prior to the commencement of construction of solar facilities on the project site.
d.
Lighting. During construction of the solar facility, any temporary construction lighting shall be positioned downward, inward, and shielded to eliminate glare from all adjacent properties. Emergency and/or safety lighting shall be exempt from this construction lighting condition.
e.
Water supply. In the event that on-site wells are used during construction of the solar energy facility, the applicant shall prepare and submit for review to the county hydrogeologic information necessary for the county to determine the potential impact to pre-existing users for the same aquifer proposed to be used for the solar energy facility and a plan to mitigate impacts to pre-existing users within the area of impact of the project. If the county, in consultation with the department of environmental quality, determines that the installation of a well will not adversely affect existing users, the applicant may proceed with well construction in compliance with approval by the department of environmental quality. At the end of the construction of the solar energy facility, the well shall not thereafter be used except only for personal toilet and lavatory facilities as required by the Uniform Statewide Building Code for operations and maintenance buildings.
(2)
Construction mitigation plan. The applicant shall prepare a construction mitigation plan for each applicable site plan for the solar facility, and each plan shall address the effective mitigation of dust, burning operations, hours of construction activity, access and road improvements, and handling of general construction complaints as set forth and described in the application materials and to the satisfaction of the zoning administrator. Damage to public roads related to construction activities shall be repaired as soon as possible and not postponed until construction completion. The applicant shall provide written notice to the zoning administrator of the plans for making such repairs, including time within which repairs will be commenced and completed, within 30 days of any written notice received from the zoning administrator.
a.
Driving of posts shall be limited to 7:00 a.m. to 6:00 p.m., Monday through Saturday. Driving of posts shall be prohibited on state and federal holidays. The applicant may request permission from the county administrator to conduct post driving activity on Sunday, but such permission will be granted or denied at the sole discretion of the county administrator.
b.
Other construction activity on site shall be permitted Monday through Sunday in accordance with the county's noise regulations set forth in chapter 20, article III.
c.
During construction, the setbacks may be used for staging of materials and parking. No material and equipment laydown area, construction staging area, or construction trailer shall be located within 200 feet of any property containing a residential dwelling.
d.
Construction lighting shall be minimized and shall be directed downward.
(3)
Erosion and sediment control plan. The county will have a third-party review with corrections completed prior to county review and approval. The owner or operator shall construct, maintain, and operate the project in compliance with the approved plan. An erosion and sediment bond (or other security) will be posted for the construction portion of the project. In addition to state and local requirements, the plan shall:
a.
Clearly show existing and proposed contours; and
b.
Note the locations and amount of topsoil to be removed (if any) and the percent of the site to be graded.
(4)
Stormwater management plan. The county will have a third-party review with corrections completed prior to county review and approval. The owner or operator shall construct, maintain, and operate the project in compliance with the approved plan. A stormwater control bond (or other security) will be posted for the project for both construction and post construction as applicable and determined by the zoning administrator.
(5)
Landscaping plan. The applicant will submit a final landscaping plan for review and approval by the zoning administrator. The owner or operator shall construct, maintain, and operate the facility in compliance with the approved plan. A separate security shall be posted for the ongoing maintenance of the project's land cover and vegetative buffers in an amount deemed sufficient by the zoning administrator. Failure to maintain the landscaping in accordance with the plan may result in the issuance of a notice of violation by the zoning administrator. The applicant (or the operator) shall promptly communicate with the zoning administrator within 30 days of the date of the notice of violation and submit a plan in writing satisfactory to the zoning administrator to remedy such violation no later than 180 days after the date of the notice of violation. Failure to remedy the violation before the end of the 180-day cure period may result in revocation of the CUP.
a.
Ground cover shall be native vegetation where compatible with site conditions and, in all cases, shall be approved by the zoning administrator.
b.
Screening vegetation shall include pollinator plants where compatible with site conditions and, in all cases, shall be approved by the zoning administrator.
c.
Only EPA approved herbicides shall be used for vegetative and weed control at the solar energy facility by a licensed applicator. No herbicides shall be used within 150 feet of the location of an approved ground water well. The applicant shall submit an herbicide land application plan prior to approval of the certificate of occupancy (or equivalent). The plan shall specify the type of herbicides to be used, the frequency of land application, the identification of approved groundwater wells, wetlands, and streams, and the distances from land application areas to features such as wells, wetlands, streams and other bodies of water. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
(6)
Decommissioning and reclamation plan. The applicant will submit a final decommissioning and reclamation plan in accordance with these regulations for review and approval by the zoning administrator.
(7)
Cost reimbursement. The applicant shall reimburse the county its costs in obtaining independent third-party reviews as required by these conditions.
(c)
The design, installation, maintenance, and repair of the solar facility shall be in accordance with the most current National Electrical Code (NFPA 70) available (2014 version or later as applicable).
(d)
If the solar facility does not receive a building permit within 18 months of approval of the conditional use permit, the permit shall be terminated.
(e)
If the solar facility is declared to be unsafe by the zoning administrator or building official, the facility must be in compliance within 14 days or the conditional use permit shall be terminated, and system removed from the property.
(f)
The owner and operator shall give the county written notice of any change in ownership, operator, or power purchase agreement within 30 days.
(Ord. of 2-17-2022, § 16-409)
(a)
In approving a conditional use permit, the board of supervisors may consider conditions that require:
(1)
Dedication of real property of substantial value; or
(2)
Substantial cash payments for or construction of substantial public improvements, the need for which is not generated solely by the granting of a conditional use permit, so long as such conditions are reasonably related to the project.
(b)
The board may include other reasonable conditions as permitted by state law and as otherwise provided for in this article.
(c)
Once a condition is granted, it shall continue in effect until a subsequent amendment changes the zoning on the property for which conditions were granted. However, such conditions shall continue if the subsequent amendment is part of a comprehensive implementation of a new or substantially revised zoning ordinance.
(Ord. of 2-17-2022, § 16-410)
- SOLAR AND BATTERY FACILITIES
The purpose of this article is to establish requirements for construction and operation of solar and battery facilities and to provide standards for the placement, design, construction, monitoring, modification, and removal of solar facilities; address public safety, minimize impacts on scenic, natural, and historic resources; and provide adequate financial assurance for decommissioning.
(Ord. of 2-17-2022, § 16-401)
This article shall apply to all solar and battery facilities constructed after the effective date of the ordinance from which this article is derived, including any physical modifications to any existing solar facilities that materially alter the type, configuration, or size of such facilities or other equipment.
(Ord. of 2-17-2022, § 16-402)
(a)
Rooftop and small-scale solar facilities may be installed by right in all zoning districts as an accessory use to provide electricity to individual structures; provided a site plan (as applicable) has been submitted to the zoning administrator for review and approval; all federal, state, and local regulations have been followed; and the system is located upon the property or structure being served. Rooftop facilities on commercial or industrial buildings shall also submit an engineering study to the building official's office for review and approval.
(b)
Medium-scale solar facilities may be installed by right as an accessory use in the industrial districts to provide electricity for use on-site for commercial and industrial applications; provided a site plan has been submitted to the zoning administrator for review and approval; all federal, state and local regulations have been followed; the system is located on the property or structure to be served; and the system is in accord with the underlying zoning requirements of the districts.
(c)
Solar facilities shall be permitted in zoning districts as follows:
(d)
Battery facilities shall be subject to a conditional use permit and permitted as follows:
(1)
An accessory use to utility-scale solar facilities, other energy generation facilities, or substations; or
(2)
A primary use on a parcel contiguous to utility-scale solar facilities, other energy generation facilities, and substations.
(e)
Solar facilities should locate on brownfields, county-owned capped landfills, or near existing industrial uses, where feasible.
(Ord. of 2-17-2022, § 16-403)
(a)
Pre-application meeting. A pre-application meeting shall be held with the zoning administrator to discuss the location, scale, and nature of the proposed use, what will be expected during that process, and the potential for a siting agreement.
(b)
Neighborhood meeting. A public meeting shall be held prior to the public hearing with the planning commission to give the community an opportunity to hear from the applicant and ask questions regarding the proposed project.
(1)
The applicant shall inform the zoning administrator's office and adjacent property owners in writing of the date, time, and location of the meeting at least seven days but no more than 14 days in advance of the meeting date.
(2)
The date, time, and location of the meeting shall be advertised in the county's newspaper of record by the applicant at least seven days but no more than 14 days in advance of the meeting date.
(3)
The meeting shall be held within the county at a location open to the general public with adequate parking and seating facilities which may accommodate persons with disabilities.
(4)
The meeting shall give members of the public the opportunity to review application materials, ask questions of the applicant, and provide feedback.
(5)
The applicant shall provide to the zoning administrator a summary of any input received from members of the public at the meeting.
(c)
Submittal of the permit application and fees.
(1)
There is a combined application for the 2232 review and CUP permit.
(2)
There are separate fees for the 2232 review and CUP permit.
(d)
2232 review. Code of Virginia, §15.2-2232 requires a review of public utility facility proposals by the planning commission to determine if their general or approximate location, character, and extent are substantially in accord with the comprehensive plan or part thereof.
(1)
The planning commission must determine, at a public meeting, whether the project is in substantial accord with the comprehensive plan. Failure of the planning commission to act within 60 days of submission, unless the time is extended by the board of supervisors, shall be deemed approval.
a.
If the planning commission approves the 2232 review, the project shall be recommended for a public hearing for the CUP permit.
b.
If the planning commission does not approve the 2232 review, the applicant may appeal the decision to the board of supervisors within ten days after the decision of the planning commission. The appeal shall be by written petition to the board of supervisors setting forth the reasons for the appeal. The appeal shall be heard and determined within 60 days from its filing unless the time is extended by the applicant. A majority vote of the board of supervisors shall overrule the planning commission.
(2)
If the board of supervisors agree to negotiate a siting agreement in accordance with Code of Virginia, § 15.2-2316.8, the 2232 review process may be delayed until negotiations are complete. If the siting agreement is approved, it fulfills the requirement for a 2232 review.
(3)
Consideration of the conditional use permit by the planning commission. The planning commission must consider the conditional use permit application at a public hearing. The planning commission has three options:
a.
Recommend approval of the application to the board of supervisors to include recommendation conditions, if applicable.
b.
Recommend denial of the application to the board of supervisors with written reasons for its decision.
c.
Defer the application for further discussion and consideration.
(4)
Consideration of the conditional use permit by the board of supervisors. The board of supervisors must consider the conditional use permit application at a public hearing. The board of supervisors has three options:
a.
Approve the application to include recommended conditions, if applicable.
b.
Deny the application with written reasons for its decision.
c.
Defer the application for further discussion and consideration.
(5)
Siting agreement. The process may also include negotiating a siting agreement in accordance with Code of Virginia, § 15.2-2316.8. The board of supervisors must consider the siting agreement at a public hearing. An approved siting agreement fulfills the requirement for a 2232 review (Code of Virginia, § 15.2-2232).
(Ord. of 2-17-2022, § 16-404)
Applications for a conditional use permit shall include:
(1)
An application packet including:
a.
Completed county application form and checklist.
b.
Documents demonstrating the ownership of the subject parcels.
c.
Proof that the applicant has authorization to act upon the owner's behalf.
d.
Identification of the intended utility company who will interconnect to the facility.
e.
List of all adjacent property owners, their tax map numbers, and addresses.
f.
A description of the current use and physical characteristics of the subject parcels.
g.
A description of the existing uses of nearby properties.
h.
A narrative identifying the applicant, owner, or operator, and describing the proposed solar facility project, including an overview of the project and its location, approximate rated capacity of the solar facility project, the approximate number of panels, representative types, expected footprint of solar equipment to be constructed, and type and location of interconnection to electrical grid.
i.
Aerial imagery which shows the proposed location of the solar facility, fenced area, driveways, and interconnection to electrical grid with the closest distance to all adjacent property lines and dwellings along with main points of ingress/egress.
j.
Payment of the application fee and any additional review costs, advertising, or other required staff time.
(2)
Concept plan. A concept plan prepared by an engineer with a professional engineering license in the commonwealth, that shall include the following:
a.
Project title information including tax parcel number, zoning, owner names, addresses, and phone numbers.
b.
Neighboring property information including tax parcel number, zoning, and owner names.
c.
Existing wetlands, waterways, and floodplains.
d.
Locations and types of soils on site.
e.
Areas of steep slopes.
f.
Existing and proposed buildings and structures including preliminary locations of the proposed solar panels and related equipment.
g.
Existing and proposed points of ingress/egress including access roads, drives, turnout locations, and parking.
h.
Location of substations, electrical cabling from the solar facility systems to the substations, ancillary equipment, buildings, and structures including those within any applicable setback.
i.
Fencing or other methods of ensuring public safety.
j.
Locations of topsoil to be removed and preserved.
k.
Locations of stormwater drainage and erosion and sediment control features.
l.
Setbacks.
m.
The location and nature of proposed buffers and screening elements, including vegetative and constructed buffers.
(3)
An estimated construction schedule.
(4)
Environmental inventory and impact statement regarding any site and viewshed impacts, including direct and indirect impacts to national and state forests, national or state parks, wildlife management areas, conservation easements, recreational areas, or any known historic or cultural resources within three miles of the proposed project using information provided by the state department of environmental quality (DEQ), the state department of conservation and recreation (DCR), state department of wildlife resources (DWR), state department of historic resources (DHR), and/or a report prepared by a qualified third party, such as ConserveVirginia or Virginia Cultural Resource Information System.
(5)
A visual impact analysis demonstrating project siting and proposed mitigation, if necessary, so that the solar facility minimizes impact on the visual character of the county.
a.
The applicant shall provide accurate, to scale, photographic simulations showing the relationship of the solar facility and its associated amenities and development to its surroundings. The photographic simulations shall show such views of solar structures from locations such as property lines and roadways, as deemed necessary by the county in order to assess the visual impact of the solar facility.
b.
The total number of simulations and the perspectives from which they are prepared shall be established by the zoning administrator after the pre-application meeting.
(6)
Solar facility inventory. An inventory of all solar facilities, existing or proposed, within a four-mile radius.
(7)
Draft traffic study. The study shall include modelling the construction and decommissioning processes. County staff will review the study in cooperation with the Virginia Department of Transportation (VDOT).
(8)
Draft landscaping plan. The plan shall indicate:
a.
All ground cover, screening and buffering materials, landscaping, and elevations.
1.
Ground cover shall be native vegetation where compatible with site conditions.
2.
Screening vegetation shall include pollinator plants where compatible with site conditions.
3.
Only EPA approved herbicides shall be used for vegetative and weed control at the solar energy facility by a licensed applicator. No herbicides shall be used within 150 feet of the location of an approved groundwater well. The applicant shall submit an herbicide land application plan prior to approval of the certificate of occupancy (or equivalent). The plan shall specify the type of herbicides to be used, the frequency of land application, the identification of approved groundwater wells, wetlands, and streams, and the distances from land application areas to features such as wells, wetlands, streams, and other bodies of water. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
b.
Locations of wildlife corridors.
c.
Maintenance requirements.
(9)
Draft decommissioning and reclamation plan. A detailed decommissioning and reclamation plan, certified by an engineer, which shall include the following:
a.
The anticipated life of the project. The applicant shall provide the basis for determining the anticipated life of the project.
b.
The estimated decommissioning and reclamation cost in current dollars. The applicant shall provide a cost estimate for the decommissioning and reclamation of the facility prepared by a professional engineer or contractor who has expertise in the removal of solar facilities. The decommissioning and reclamation cost estimate shall explicitly detail the cost without any reduction for salvage value.
c.
The method of ensuring that funds will be available for decommissioning and reclamation. A proposed method of providing appropriate escrow, surety, or security for the cost of the decommissioning and reclamation plan. The surety shall be updated when the decommissioning and reclamation cost estimate is updated. The estimated cost of decommissioning shall be guaranteed by the deposit of funds in an amount equal to the estimated cost in an escrow account at a federally insured financial institution approved by the county unless otherwise provided for in subsection (9)c.4 of this section.
1.
The applicant shall deposit the required amount into the approved escrow account before any building permit is issued to allow construction of the solar facility.
2.
The escrow account agreement shall prohibit the release of the escrow funds without the written consent of the county. The county shall consent to the release of the escrow funds upon the owner's or occupant's compliance with the approved decommissioning and reclamation plan. The county may approve the partial release of escrow funds as portions of the approved decommissioning plan are performed.
3.
The amount of funds required to be deposited in the escrow account shall be the full amount of the estimated decommissioning and reclamation cost.
4.
The county may approve alternative methods to secure the availability of funds to pay for the decommissioning and reclamation of a solar facility, such as a performance bond, letter of credit, or other security approved by the county.
d.
The method that the estimated cost will be kept current. The decommissioning and reclamation cost estimate shall include a mechanism for calculating increased removal costs due to inflation. This cost estimate shall be recalculated every five years and the surety shall be updated accordingly. If the recalculated estimated cost exceeds the original estimated cost by ten percent, then the owner or occupant shall deposit additional funds into the escrow account to meet the new cost estimate. If the recalculated estimated cost is less than 90 percent of the original estimated cost, then the county may approve reducing the amount of the escrow account to the recalculated estimate of cost.
e.
The manner in which the site will be decommissioned and reclaimed. This will include:
1.
Notice to the zoning administrator by certified mail and in person of the proposed date of discontinued operations and plans for removal.
2.
A traffic study submitted with application modelling the decommissioning processes. County staff will review the study in cooperation with VDOT.
3.
An estimated deconstruction schedule.
4.
Removal of all solar electric systems, buildings, cabling, electrical components, security barriers, roads, foundations, pilings, and any other associated facilities, so that any agricultural ground upon which the facility and/or system was located is again tillable and suitable for agricultural or forestall uses.
5.
The site shall be graded and re-seeded or replanted within 12 months of removal of solar facilities to restore it to as natural a pre-development condition as possible. Re-grading and re-seeding or replanting shall be initiated within a six-month period of removal of equipment. Any exception to site restoration, such as leaving access roads in place or re-seeded or replanted, must be requested by the landowner in writing, and this request must be approved by the board of supervisors.
6.
Hazardous material from the property shall be disposed of in accordance with federal and state law.
(10)
Additional information may be required as determined by the zoning administrator, such as a scaled elevation view of the property and other supporting drawings, photographs of the proposed site, photo or other realistic simulations or modeling of the proposed project from potentially sensitive locations as deemed necessary by the zoning administrator to assess the visual impact of the project, landscaping plan, coverage map, and additional information that may be necessary for a technical review of the proposal.
(Ord. of 2-17-2022, § 16-405)
(a)
Generally. A utility-scale solar facility shall be constructed, operated, and maintained in substantial compliance with the approved concept plan with allowances for changes required by the state department of environmental quality (DEQ) permit by rule (PBR) or state corporation commission (SCC) permit process.
(b)
Location standards for utility-scale solar facilities. The location standards stated in this subsection for utility-scale solar facilities are intended to mitigate the adverse effects of such uses on adjoining property owners, the area, and the county.
(1)
The minimum area of a utility-scale solar facility shall be 100 acres or more.
(2)
The equipment, improvements, structures, and percent of acreage coverage of a utility-scale solar facility shall be shown on the approved concept plan and site plan. The percent of acreage coverage shall not exceed 65 percent.
(c)
Height.
(1)
The maximum height of the lowest edge of photovoltaic panels shall be ten feet as measured from the finished grade. The maximum height of the highest edge of photovoltaic panels shall not exceed 15 feet as measured from the finished grade.
(2)
The maximum height of other facility structures shall not exceed 15 feet. This limit shall not apply to utility poles or the interconnection to the overhead electric utility grid.
(3)
The board of supervisors may approve a greater height based upon the demonstration of a significant need where the impacts of increased height are mitigated.
(d)
Setbacks. Solar facilities shall meet all setback requirements for primary structures for the zoning district in which the facility is located and the requirements set forth in this subsection (the more restrictive requirements shall apply).
(1)
The minimum setback of structures and uses associated with the facility, including fencing, PV panels, parking areas, and outdoor storage, but not including landscaping and berming, shall be:
a.
150 feet from adjacent property lines.
b.
150 feet from all public rights-of-way.
c.
300 feet from a dwelling.
(2)
The planning commission or board of supervisors may require increased setbacks up to 400 feet in situations where the height of structures or the topography affects the visual impact of the facility.
(3)
These setback requirements shall not apply to internal property lines of those parcels on which a solar facility is located.
(4)
Access, erosion and stormwater structures, and interconnection to the electrical grid may be made through setback areas provided that such are generally perpendicular to the property line.
(5)
Vehicular access to the site shall be a minimum of 50 feet from the nearest dwelling located on adjacent property.
(e)
Buffer. The buffer shall be located within the setbacks required under this section and shall run around the entire perimeter of the property. The buffer shall be maintained for the life of the facility.
(f)
Screening. The facilities, including security fencing that is not ornamental, shall be screened from the ground-level view of adjacent properties or a public street in the buffer zone. Screening may also be required in other locations to screen specific uses or structures. A recommendation that the screening and/or buffer creation requirements be waived or altered may be made by the planning commission when the applicant proposes to use existing wetlands or woodlands to satisfy the screening requirement. The wetlands or woodlands shall be permanently protected as a designated buffer and the overall buffer shall measure at least 150 feet. Screening methods may include:
(1)
Existing screening. Existing vegetation, topography, buildings, open space, or other elements located on the site may be considered as part of the required screening. Existing trees and vegetation may be retained within the buffer area except where dead, diseased, or as necessary for development or to promote healthy growth.
(2)
Vegetative screening. In the event existing vegetation or landforms providing the screening are inadequate or disturbed, new plantings shall be provided in a landscaped strip at least 50 feet wide. Landscaping intended for screening shall consist of a combination of non-invasive species, pollinator species, and native plants, shrubs, trees, grasses, forbs, and wildflowers. Trees intended for screening shall consist of a combination of evergreen and deciduous trees that are five to six feet in height at time of planting. A triple row of trees shall be placed on average at 15 feet on center. A list of appropriate plant materials shall be available at the planning office. Species listed on DCR's invasive plant species list shall not be used.
(3)
Berming. Berms shall generally be constructed with a 3:1 side slope to rise ratio, four to six feet above the adjacent grade, with a three-foot-wide top with appropriate pollinator-friendly native plants, shrubs, trees, forbs, and wildflowers. The outside edges of the berm shall be sculpted such that there are vertical and horizontal undulations to give variations in appearance. When completed, the berm should not have a uniform appearance like a dike.
(4)
Opaque architectural fencing. Fencing intended for screening shall be at least 75 percent visually solid as viewed on any line perpendicular to the fence from adjacent property or a public street. Such fencing may be used in combination with other screening methods but shall not be the primary method. A typical example is the use of wood privacy fencing and landscaping to screen structures such as substations. Depending on the location, ornamental features may be required on the fence. Fencing material shall not include plastic slats.
(g)
Security fence. The facilities shall be enclosed by security fencing not less than six feet in height and topped with barbed wire, as appropriate. A performance bond reflecting the costs of anticipated fence maintenance shall be posted and maintained. Failure to maintain the security fencing shall result in revocation of the CUP and the facility's decommissioning.
(h)
Ground cover. Ground cover on the site shall be native vegetation and maintained in accordance with the landscaping plan in accordance with established performance measures. A performance bond reflecting the costs of anticipated maintenance shall be posted and maintained. Failure to maintain the ground cover shall result in revocation of the CUP and the facility's decommissioning. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
(i)
Access corridors. The applicant shall identify access corridors for wildlife to navigate through and across the solar facility. The proposed wildlife corridors shall be shown on the site plan submitted to the county. Areas between fencing shall be kept open to allow for the movement of migratory animals and other wildlife.
(j)
Support buildings. The design of support buildings and related structures shall use materials, colors, textures, screening, and landscaping that will blend the facilities to the natural setting and surrounding structures.
(k)
Maintenance. The owner or operator shall maintain the solar facility in good condition. Such maintenance shall include, but not be limited to, painting, structural integrity of the equipment and structures, as applicable, and maintenance of the buffer areas and landscaping. Site access shall be maintained to a level acceptable to the county. The project owner shall be responsible for the cost of maintaining the solar facility and access roads, and the cost of repairing damage to private roads occurring as a result of construction and operation.
(l)
Inspections.
(1)
The applicant will allow designated county representatives or employees access to the facility for inspection purposes with 24-hour notice.
(2)
The applicant shall reimburse the county its costs in obtaining an independent third party to conduct inspections required by local and state laws and regulations.
(m)
Design, maintenance of utility-scale facility. A utility-scale solar facility shall be designed and maintained in compliance with standards contained in applicable local, state, and federal building codes and regulations that were in force at the time of the permit approval.
(n)
Liability insurance. The applicant shall provide proof of adequate liability insurance for a solar facility prior to beginning construction and before the issuance of a zoning or building permit to the zoning administrator.
(o)
Lighting. Lighting fixtures as approved by the county shall be the minimum necessary for safety and/or security purposes to protect the night sky by facing downward and to minimize off-site glare. No facility shall produce glare that would constitute a nuisance to the public. Any exceptions shall be enumerated on the concept plan and approved by the zoning administrator.
(p)
Signage. No signage of any type may be placed on the facility other than notices, warnings, and identification information required by law.
(q)
Noise. At all times, the solar facility shall comply with the county's noise regulations set forth in chapter 20, article III.
(r)
Coordination of local emergency services. Applicants for new solar facilities shall coordinate with the county's emergency services staff to provide materials, education and/or training to the departments serving the property with emergency services in how to safely respond to on-site emergencies.
(s)
Decommissioning.
(1)
Solar facilities which have reached the end of their useful life or have not been in active and continuous service for a period of six months shall be removed at the owner's or operator's expense, except if the project is being repowered or a force majeure event has or is occurring requiring longer repairs; however, the county may require evidentiary support that a longer repair period is necessary.
(2)
The owner or operator shall notify the zoning administrator by certified mail and in person of the proposed date of discontinued operations and plans for removal.
(3)
Decommissioning shall include removal of all solar electric systems, buildings, cabling, electrical components, security barriers, roads, foundations, pilings, and any other associated facilities, so that any agricultural ground upon which the facility and/or system was located is again tillable and suitable for agricultural or forestall uses. The site shall be graded and re-seeded to restore it to as natural a pre-development condition as possible or replanted with pine seedlings to stimulate pre-timber pre-development conditions as indicated on the concept plan. Any exception to site restoration, such as leaving access roads in place or seeding instead of planting seedlings must be requested by the landowner in writing, and this request must be approved by the board of supervisors.
(4)
The site shall be re-graded and re-seeded or replanted within 12 months of removal of solar facilities. Re-grading and re-seeding or replanting shall be initiated within a six-month period of removal of equipment.
(5)
Decommissioning and reclamation shall be performed in compliance with the approved decommissioning and reclamation plan. The board of supervisors may approve any appropriate amendments to or modifications of the decommissioning plan.
(6)
Hazardous material from the property shall be disposed of in accordance with federal and state law.
(7)
If the owner or operator of the solar facility fails to remove the installation in accordance with the requirements of this permit or within the proposed date of decommissioning, the county may collect the surety and the county or hired third party may enter the property to physically remove the installation.
(t)
Additional conditions. Any other condition may be added by the planning commission or board of supervisors as part of a CUP approval.
(Ord. of 2-17-2022, § 16-406)
In addition to the above general provisions, application requirements, and development and performance standards, the following additional requirements shall be met for the approval of a battery energy storage facility:
(1)
Battery energy storage facilities shall be constructed, maintained, and operated in accordance with national industry standards and regulations, including the most current adopted edition of the National Electrical Code, International Fire Code of the International Code Council, and the National Fire Protection Association Fire Code. The batteries will be NFPA (National Fire Protection Agency) complaint. In the event of a conflict between the national industry standards and these conditions, the national industry standards shall control so that as technology advances, updated technology may be used.
(2)
Battery cells shall be placed in a battery energy storage system (BESS) with a battery management system (BMS). The BESS shall provide a secondary layer of physical containment to the batteries and be equipped with cooling, ventilation, and fire suppression systems. Each individual battery shall have 24/7 automated fire detection and extinguishing technology built in. The BMS shall monitor individual battery module voltages and temperatures, container temperature and humidity, off-gassing of combustible gas, fire, ground fault and DC surge, and door access and be able to shut down the system before thermal runaway takes place.
(3)
The battery energy storage system will be placed on an appropriate foundation and screened with vegetation outside of environmentally sensitive areas.
(4)
Access to all batteries and electrical switchgear shall be from the exterior for normal operation and maintenance. Access to the container interior shall not be permitted while the system is in operation except for safety personnel and first responders.
(5)
Qualifications and experience from selected developers and integrators shall be provided including disclosure of fires or other hazards at facilities.
(6)
Safety testing and failure modes analysis data from selected developers and manufacturers shall be provided.
(7)
The latest applicable product certifications shall be provided.
(8)
The solar facility operator or owner shall be responsible for any environmental remediation required by the county or the state and the costs of such remediation. All remediation shall be completed in a timely manner.
(9)
Battery storage shall be developed in collaboration with technical experts and first responders to utilize technology-appropriate best practices for safe energy storage systems, including, but not limited to, the following:
a.
Adequate access/egress for the first responders;
b.
Adequate facility signage (on battery chemistry and person to contact);
c.
Accessible safety data sheets;
d.
System-specific emergency response plans;
e.
Training for first responders on the type of system, potential hazards and risks, and system-specific emergency response plans;
f.
Adequate water sources and fire suppression appliances for the firefighters if required in the emergency response plans;
g.
Signage on hazardous materials present in the vicinity;
h.
Emergency lighting;
i.
Separate battery modules to make it easier to isolate a failed battery from the rest;
j.
Sufficient disconnect and shutdown capability including a master kill switch to disable and discharge batteries;
k.
System-appropriate sensors and alarms;
l.
Air ventilation and fire suppression systems;
m.
Drainage for water runoff; and
n.
Other practices as recommended by experts or local first responders.
(10)
The solar facility operator or owner shall conduct regular on-site inspections of the battery units and submit a written report to the zoning administrator on their condition, at least once every six months. The solar facility operator or owner shall conduct monthly inspections electronically of the battery units and submit a written report to the zoning administrator.
(Ord. of 2-17-2022, § 16-407)
In addition to the above general provisions, application requirements, and development and performance standards, the following additional requirements shall be met for the approval of a substation:
(1)
Siting. Substations located within the solar facility shall be sited in accordance with these regulations.
(2)
Term and special permits. Substations included as part of the solar facility shall have the same term as the solar facility. However, substations may have a life longer than that of the larger solar facility, and, alternatively, may individually and not as part of a solar facility receive a conditional use permit in accordance with these regulations.
(Ord. of 2-17-2022, § 16-408)
(a)
The board of supervisors may consider conditions addressing a proposed solar and/or battery facility, including, but not limited to, the following:
(1)
A solar facility shall be constructed, maintained, and operated in substantial compliance with:
a.
The development standards under this article.
b.
The approved concept plan.
c.
Any other conditions imposed pursuant to a conditional use permit.
(2)
The board of supervisors may, in its sole discretion, by conditional use permit, waive or modify requirements set out in this article for solar or battery storage facilities, based on unique site conditions, if it finds that such waiver or modification promotes good land use planning and is compatible with surrounding land uses, and as long as the project still otherwise complies with applicable state law and local ordinances.
(b)
Site plan requirements. In addition to all state site plan requirements and site plan requirements of the zoning administrator, the applicant shall provide the following plans for review and approval for the solar facility prior to the issuance of a building permit:
(1)
Construction management plan. The applicant shall prepare a construction management plan for each applicable site plan for the solar facility, and each plan shall address the following:
a.
Traffic control methods (in coordination with the Virginia Department of Transportation (VDOT) prior to initiation of construction):
1.
Lane closures.
2.
Signage.
3.
Flagging procedures.
b.
Site access planning. Directing employee and delivery traffic to minimize conflicts with local traffic.
c.
Site security. The applicant shall implement security measures prior to the commencement of construction of solar facilities on the project site.
d.
Lighting. During construction of the solar facility, any temporary construction lighting shall be positioned downward, inward, and shielded to eliminate glare from all adjacent properties. Emergency and/or safety lighting shall be exempt from this construction lighting condition.
e.
Water supply. In the event that on-site wells are used during construction of the solar energy facility, the applicant shall prepare and submit for review to the county hydrogeologic information necessary for the county to determine the potential impact to pre-existing users for the same aquifer proposed to be used for the solar energy facility and a plan to mitigate impacts to pre-existing users within the area of impact of the project. If the county, in consultation with the department of environmental quality, determines that the installation of a well will not adversely affect existing users, the applicant may proceed with well construction in compliance with approval by the department of environmental quality. At the end of the construction of the solar energy facility, the well shall not thereafter be used except only for personal toilet and lavatory facilities as required by the Uniform Statewide Building Code for operations and maintenance buildings.
(2)
Construction mitigation plan. The applicant shall prepare a construction mitigation plan for each applicable site plan for the solar facility, and each plan shall address the effective mitigation of dust, burning operations, hours of construction activity, access and road improvements, and handling of general construction complaints as set forth and described in the application materials and to the satisfaction of the zoning administrator. Damage to public roads related to construction activities shall be repaired as soon as possible and not postponed until construction completion. The applicant shall provide written notice to the zoning administrator of the plans for making such repairs, including time within which repairs will be commenced and completed, within 30 days of any written notice received from the zoning administrator.
a.
Driving of posts shall be limited to 7:00 a.m. to 6:00 p.m., Monday through Saturday. Driving of posts shall be prohibited on state and federal holidays. The applicant may request permission from the county administrator to conduct post driving activity on Sunday, but such permission will be granted or denied at the sole discretion of the county administrator.
b.
Other construction activity on site shall be permitted Monday through Sunday in accordance with the county's noise regulations set forth in chapter 20, article III.
c.
During construction, the setbacks may be used for staging of materials and parking. No material and equipment laydown area, construction staging area, or construction trailer shall be located within 200 feet of any property containing a residential dwelling.
d.
Construction lighting shall be minimized and shall be directed downward.
(3)
Erosion and sediment control plan. The county will have a third-party review with corrections completed prior to county review and approval. The owner or operator shall construct, maintain, and operate the project in compliance with the approved plan. An erosion and sediment bond (or other security) will be posted for the construction portion of the project. In addition to state and local requirements, the plan shall:
a.
Clearly show existing and proposed contours; and
b.
Note the locations and amount of topsoil to be removed (if any) and the percent of the site to be graded.
(4)
Stormwater management plan. The county will have a third-party review with corrections completed prior to county review and approval. The owner or operator shall construct, maintain, and operate the project in compliance with the approved plan. A stormwater control bond (or other security) will be posted for the project for both construction and post construction as applicable and determined by the zoning administrator.
(5)
Landscaping plan. The applicant will submit a final landscaping plan for review and approval by the zoning administrator. The owner or operator shall construct, maintain, and operate the facility in compliance with the approved plan. A separate security shall be posted for the ongoing maintenance of the project's land cover and vegetative buffers in an amount deemed sufficient by the zoning administrator. Failure to maintain the landscaping in accordance with the plan may result in the issuance of a notice of violation by the zoning administrator. The applicant (or the operator) shall promptly communicate with the zoning administrator within 30 days of the date of the notice of violation and submit a plan in writing satisfactory to the zoning administrator to remedy such violation no later than 180 days after the date of the notice of violation. Failure to remedy the violation before the end of the 180-day cure period may result in revocation of the CUP.
a.
Ground cover shall be native vegetation where compatible with site conditions and, in all cases, shall be approved by the zoning administrator.
b.
Screening vegetation shall include pollinator plants where compatible with site conditions and, in all cases, shall be approved by the zoning administrator.
c.
Only EPA approved herbicides shall be used for vegetative and weed control at the solar energy facility by a licensed applicator. No herbicides shall be used within 150 feet of the location of an approved ground water well. The applicant shall submit an herbicide land application plan prior to approval of the certificate of occupancy (or equivalent). The plan shall specify the type of herbicides to be used, the frequency of land application, the identification of approved groundwater wells, wetlands, and streams, and the distances from land application areas to features such as wells, wetlands, streams and other bodies of water. The operator shall notify the county prior to application of pesticides and fertilizers. The county reserves the right to request soil and water testing.
(6)
Decommissioning and reclamation plan. The applicant will submit a final decommissioning and reclamation plan in accordance with these regulations for review and approval by the zoning administrator.
(7)
Cost reimbursement. The applicant shall reimburse the county its costs in obtaining independent third-party reviews as required by these conditions.
(c)
The design, installation, maintenance, and repair of the solar facility shall be in accordance with the most current National Electrical Code (NFPA 70) available (2014 version or later as applicable).
(d)
If the solar facility does not receive a building permit within 18 months of approval of the conditional use permit, the permit shall be terminated.
(e)
If the solar facility is declared to be unsafe by the zoning administrator or building official, the facility must be in compliance within 14 days or the conditional use permit shall be terminated, and system removed from the property.
(f)
The owner and operator shall give the county written notice of any change in ownership, operator, or power purchase agreement within 30 days.
(Ord. of 2-17-2022, § 16-409)
(a)
In approving a conditional use permit, the board of supervisors may consider conditions that require:
(1)
Dedication of real property of substantial value; or
(2)
Substantial cash payments for or construction of substantial public improvements, the need for which is not generated solely by the granting of a conditional use permit, so long as such conditions are reasonably related to the project.
(b)
The board may include other reasonable conditions as permitted by state law and as otherwise provided for in this article.
(c)
Once a condition is granted, it shall continue in effect until a subsequent amendment changes the zoning on the property for which conditions were granted. However, such conditions shall continue if the subsequent amendment is part of a comprehensive implementation of a new or substantially revised zoning ordinance.
(Ord. of 2-17-2022, § 16-410)