SITE PLAN REVIEW
(Chapter Added by Amended Ord. 2003-1, Adopted 5/1/03, Effective 5/20/03)
The intent of this Section is to provide for consultation and cooperation between land developers and the Township in order that the developer may accomplish his or her objectives in the utilization of his or her land within the regulations of this zoning ordinance and with minimum adverse effect on the use of adjacent streets and highways and on existing and future uses in the immediate area and vicinity. Prior to the issuance of a building permit, for the creation of a use or the erection of a building in the district and under the conditions cited below, a site plan shall be submitted in accordance with this Section to the Township Planning Commission for approval.
An approved site plan shall be effective for a period of one (1) year, or the life of a building permit obtained pursuant to the approved site plan, whichever is longer. If construction is not commenced within the period that the site plan is effective, no construction shall take place unless there has been an extension approved by the Planning Commission and before the extension is granted, there is compliance with all applicable site plan requirements that are in effect at the time of the extension. (Amended by Ord. 91-1, 3/21/91)
Site Plan Approval shall be required for all uses except the following:
The site plan shall contain the following information except that for special uses located on residential lots with a principal single family building, or other uses when specified under the provisions of this ordinance, one or more of the provisions contained in items (a) through (m) below may be waived. Such waiver(s) may be made by the Planning Commission if in its discretion the site plan has been drawn to a legible scale and contains sufficient other data necessary to accurately reflect existing and proposed conditions remain to the proposed use or operation.
At a minimum, the site plan shall illustrate at least that portion of the subject property relevant to the proposal to meet the intent of item (c) below in addition to the requirements of items (a), (b), and (g). (Amended by Ord. 91-1, 3/21/91)
The site plan and all related information specified above shall be presented to the Planning Commission in thirteen (13) copies by the property owner or petitioner at least one week prior to that meeting of the Planning Commission at which the plan will be reviewed.
Nine (9) copies to the Secretary of the Planning Commission One (1) copy to the Township Fire Chief One (1) copy to the Township Engineer One (1) copy to the Township Attorney One (1) copy to the Township Supervisor
The Township Planning Commission shall have the function, duty and power to approve or disapprove, or to approve subject to compliance with certain modifications or conditions, the site plan in accordance with the standards contained in and referenced by this Zoning Ordinance. No action shall be taken by the Planning Commission until a hearing shall be held in accordance with its rules and regulations. In reviewing the application and site plan and in approving, disapproving or modifying the same, the Township Planning Commission shall be governed by the following standards:
The Planning Commission shall review site plans according to the following standards relating to vehicle access and circulation. The purpose of specific access standards is to promote traffic safety, minimize congestion, provide adequate access, promote community character, and ensure orderly development. (Amended Ord. 95-2Z, 3/9/95)
| FRONTAGE | DRIVEWAYS PERMITTED |
| Less Than 300 Feet | 1 |
| 300 To 600 Feet | 2 |
| More Than 600 Feet | 3 |
Any modifications of the site plan desired by Township Planning Commission shall be so stated in writing to the applicant. Site plan approval may be granted contingent upon the revision of said site plan by the petitioner to the satisfaction of the Planning Commission. If any part of the site plan is in conflict any section of this Ordinance in terms of setbacks, parking, maneuvering lanes, etc., a variance must be granted by the Board of Appeals. Six (6) copies of the final approved site plan, with its modifications shall be on record in the Township offices. Each copy shall have the signature of the Chairman of the Planning Commission. If variances are required and have been secured, the site plan shall also show the signature of the Chairman of the Board of Appeals.
If approval is granted by the Planning Commission, the following conditions shall apply:
An application for site plan approval shall be accompanied by such fees the Township Board, by resolution, considers necessary for the processing of the application. Such fee may be utilized by the Township to obtain the services of one or more expert consultants qualified to advise as to whether the proposed development will conform to the applicable Township Ordinances, policies and standards and for investigation and report of any objectionable elements. Such consultants shall report as promptly as possible.
SITE PLAN REVIEW
(Chapter Added by Amended Ord. 2003-1, Adopted 5/1/03, Effective 5/20/03)
The intent of this Section is to provide for consultation and cooperation between land developers and the Township in order that the developer may accomplish his or her objectives in the utilization of his or her land within the regulations of this zoning ordinance and with minimum adverse effect on the use of adjacent streets and highways and on existing and future uses in the immediate area and vicinity. Prior to the issuance of a building permit, for the creation of a use or the erection of a building in the district and under the conditions cited below, a site plan shall be submitted in accordance with this Section to the Township Planning Commission for approval.
An approved site plan shall be effective for a period of one (1) year, or the life of a building permit obtained pursuant to the approved site plan, whichever is longer. If construction is not commenced within the period that the site plan is effective, no construction shall take place unless there has been an extension approved by the Planning Commission and before the extension is granted, there is compliance with all applicable site plan requirements that are in effect at the time of the extension. (Amended by Ord. 91-1, 3/21/91)
Site Plan Approval shall be required for all uses except the following:
The site plan shall contain the following information except that for special uses located on residential lots with a principal single family building, or other uses when specified under the provisions of this ordinance, one or more of the provisions contained in items (a) through (m) below may be waived. Such waiver(s) may be made by the Planning Commission if in its discretion the site plan has been drawn to a legible scale and contains sufficient other data necessary to accurately reflect existing and proposed conditions remain to the proposed use or operation.
At a minimum, the site plan shall illustrate at least that portion of the subject property relevant to the proposal to meet the intent of item (c) below in addition to the requirements of items (a), (b), and (g). (Amended by Ord. 91-1, 3/21/91)
The site plan and all related information specified above shall be presented to the Planning Commission in thirteen (13) copies by the property owner or petitioner at least one week prior to that meeting of the Planning Commission at which the plan will be reviewed.
Nine (9) copies to the Secretary of the Planning Commission One (1) copy to the Township Fire Chief One (1) copy to the Township Engineer One (1) copy to the Township Attorney One (1) copy to the Township Supervisor
The Township Planning Commission shall have the function, duty and power to approve or disapprove, or to approve subject to compliance with certain modifications or conditions, the site plan in accordance with the standards contained in and referenced by this Zoning Ordinance. No action shall be taken by the Planning Commission until a hearing shall be held in accordance with its rules and regulations. In reviewing the application and site plan and in approving, disapproving or modifying the same, the Township Planning Commission shall be governed by the following standards:
The Planning Commission shall review site plans according to the following standards relating to vehicle access and circulation. The purpose of specific access standards is to promote traffic safety, minimize congestion, provide adequate access, promote community character, and ensure orderly development. (Amended Ord. 95-2Z, 3/9/95)
| FRONTAGE | DRIVEWAYS PERMITTED |
| Less Than 300 Feet | 1 |
| 300 To 600 Feet | 2 |
| More Than 600 Feet | 3 |
Any modifications of the site plan desired by Township Planning Commission shall be so stated in writing to the applicant. Site plan approval may be granted contingent upon the revision of said site plan by the petitioner to the satisfaction of the Planning Commission. If any part of the site plan is in conflict any section of this Ordinance in terms of setbacks, parking, maneuvering lanes, etc., a variance must be granted by the Board of Appeals. Six (6) copies of the final approved site plan, with its modifications shall be on record in the Township offices. Each copy shall have the signature of the Chairman of the Planning Commission. If variances are required and have been secured, the site plan shall also show the signature of the Chairman of the Board of Appeals.
If approval is granted by the Planning Commission, the following conditions shall apply:
An application for site plan approval shall be accompanied by such fees the Township Board, by resolution, considers necessary for the processing of the application. Such fee may be utilized by the Township to obtain the services of one or more expert consultants qualified to advise as to whether the proposed development will conform to the applicable Township Ordinances, policies and standards and for investigation and report of any objectionable elements. Such consultants shall report as promptly as possible.