Definitions. The following definitions shall apply to resource extraction:
ABANDONED QUARRY SITE
(1)
Abandoned uses/termination of operations. Operations should be considered to have been abandoned if:
(a)
The operator does not demonstrate his intention to resume operations and keep his bond in force more than one year after operations have ceased in a given site. A new permit would be required prior to further excavation or processing if this occurs.
(b)
Within a period of six months, unless extended by written permission by the Bethlehem Planning Board, after notice of the termination by the operator of an extraction operation or after the abandonment of such operation due to its failure to operate according to ordinance standards and requirements, all unused structures, buildings, and equipment along with all buildings, structures and equipment presently used in such operation, shall be dismantled and removed by and at the expense of the operator last operating such buildings, structures and equipment, except such buildings, structures and equipment need not be dismantled and removed as long as they are in good repair and they may reasonably be expected to be used for continued land mining operations or for some other purpose permitted in the zone in which they are located. Further specific steps necessary to complete the reclamation plan shall be undertaken.
ACTIVE QUARRY SITE
A mining operation where land is being disturbed in preparation for and during the removal of a mineral material, not including casual use as defined herein.
BERM
A pile or mound of earth capable of acting as a visual screen or used to control drainage or erosion.
BOTTOM OF EXCAVATION
The generally flat area at the lowest level adjacent to the face of the pit; also commonly known as "toe of slopes."
CASUAL USE
The temporary use of lands for geological investigations (test drilling, sampling, etc.) which do not involve either any significant surface disturbance or site preparation.
CONTIGUOUS LANDS
Lands shall be considered contiguous to each other if they abut each other, or if they are separated by streets, ways, pipelines, electric power lines, conduits or rights-of-way, owned or controlled by third parties.
DISTURBED LAND
Land on which clearing has occurred, excavation has occurred or upon which overburden has been deposited, or both.
EARTH EXTRACTION
The removal of sand, topsoil, gravel, fill dirt or mineral or clay products for sale or use at another site, but not including agricultural operations or the process of grading a lot preparatory to the construction of a structure for which application for a building permit has been made.
EXCAVATIONS or WORKINGS
Shafts, tunnels, entries, winzes, slopes, open cut and any working places and parts of a mine, either above ground or underground, excavated or being excavated, whether abandoned or in use.
FACE or BANK
The sides from the bottom or floor of a pit or quarry to the surface surrounding the pit. Where one or more benches or levels are used in a pit, each bench or level has a separate face.
INACTIVE QUARRY SITE
A mining or quarrying operation where land is not currently being disturbed in preparation for resource extraction, but where intent to abandon the quarry operation is not clearly established. Inactive quarry sites shall make application to the Planning Board for conditional use and site plan approval and apply to the Township Committee for a resource extraction license before commencing resource extraction activities or reclamation activities on site.
MINE
Any mines within the Township, whether on the surface or underground, and any mining plant, material, equipment or explosives on the surface or underground which may contribute to the mining or handling of ore or other metalliferous or nonmetalliferous products. The term "mine" shall also include quarry, sand pit, gravel pit, clay pit and shale pit.
MINE SETBACK
The distance from the bottom of excavation in the case of a dry pit and the normal seasonal high-water line in the case of a wet pit, to a referenced line (i.e., property line, zoning line, right-of-way line) when measured at right angles to the referenced line.
MINING OPERATIONS
Earth extraction, excavations, workings, production, processing, stockpiling, loading and all other functions and accessory uses necessary and related to the proper operation of a mine.
OPERATOR
Individual, partnership, firm, association, trust or corporation responsible for the general operation, management and condition of the facility located at the mining site in question, for which a permit is applied for or granted for any activity covered by this section.
OVERBURDEN
Soil material of any nature (including topsoil), consolidated or unconsolidated, that overlies a mineral deposit of useful materials or ores that are to be mined.
PERMIT AREA
The specific land proposed to be used for mining operations, including required buffers and setbacks, reclamation areas and related plant facilities.
PIT or QUARRY
Includes any excavation, pit, bank or open cut working for the extraction of stone, rock, gravel, sand or any other mineral and shall embrace any and all parts of the property of such quarry or open pit mine that contribute directly or indirectly to the extraction of such mineral.
RECLAMATION
The restoration of an area of land (to include filling, grading, topsoiling, revegetation, equipment removal, etc.) such that the land is made useful for some future use as permitted in the MR zone at the time of the approval of the reclamation plan.
RECLAMATION PLAN
A reclamation plan is a concept plan approved by the Township Planning Board as part of site plan approval for reclamation of the area of land affected by quarrying operations. The reclamation plan shall include an overall plan for the reclamation of the site in order to provide a realistic opportunity to utilize the site for any of the permitted uses in the zone and shall provide a phase plan and bond estimate for the duration of the resource extraction license. The reclamation plan shall include land use objectives, specifications for grading, manner and type of vegetation, such safety devices as shall be used at the site and such maps and other supporting documents as may be required by the Planning Board; said plan shall be prepared by a licensed professional engineer and land surveyor licensed in the State of New Jersey unless otherwise provided by statute.
WET PIT
An excavation in which the bottom is normally wet and the bottom of which is at or below the normal seasonal high-water table.