A.
Prior to the submittal of an application for
Site Plan Review, each applicant, property
owner, or developer is required to have a
pre-application meeting with the Boone County Planning Commission's staff. This meeting shall occur within sixty (60) days of submitting the formal
site plan application. The purpose of the
pre-application meeting is to advise each applicant, property
owner, or developer of the
Site Plan Review procedure and requirements and to allow the applicant the opportunity to present a plan for
building construction and/or site work. At such a meeting, the staff will be able to discuss any initial concerns and omissions about the
Site Plan that is being previewed. In addition, the results of the meeting will also permit the
Zoning Administrator to determine whether the applicant, property
owner, or developer will follow the Minor
Site Plan Review procedure or the Major
Site Plan Review procedure. Both types of procedures are shown in Figure 30-1 and are described as follows:
1.
Minor
Site Plan:
Site Plans are required for all principally permitted, conditional, or accessory uses, except for single
family residential uses, and are reviewed by the Boone County Planning Commission's staff, and involves the following:
a.
No exterior
utility construction (e.g., storm sewer, water, sanitary sewer, etc.).
b.
No grading work or a minimal amount of grading work.
c.
No more than twelve (12) parking spaces.
d.
No more than a fifteen percent (15%) increase of the existing
building square footage.
e.
No additional
access points or curb cuts.
f.
Loading areas that are less than 10,000 square feet.
g.
Does not involve the construction of a new
building upon demolition of an existing
building.
2.
Major
Site Plan:
Site Plans are required for all principally permitted, conditional, or accessory uses, except for single
family residential uses, and are reviewed by the
Project Review Committee and other outside agencies in addition to the Boone County Planning Commission's staff, and involves any of the following:
a.
Exterior
utility construction (e.g., storm sewer, water, sanitary sewer, etc.).
b.
Grading work.
c.
More than twelve (12) parking spaces.
d.
New
building construction or more than a fifteen percent (15%) increase in the existing
building square footage.
e.
f.
Loading areas in excess of 10,000 square feet.
g.
Construction of a new
building, regardless of size, upon demolition of an existing
building.