CITY OF CORTEZ — ZONING DEVELOPMENT PERMIT
The Zoning Administrator and Building Official must verify compliance with applicable City Land Use Code criteria for each of the categories listed in Sections 3 and 4 prior to consideration of applications for Building Permits.
1. APPLICANT SHALL COMPLETE:
2. APPLICANT SHALL ATTACH TWO (2) COPIES OF A COMPLETE SITE AND ACCESS PLAN OR PLAT SHOWING THE BUILDING OR STRUCTURE IN SUFFICIENT DETAIL TO DEMONSTRATE THAT THE PROPOSED CONSTRUCTION, RECONSTRUCTION OR CONVERSION, MOVING AND/OR ALTERATION IS IN CONFORMANCE WITH THE PROVISIONS OF THE APPLICABLE ZONE DISTRICT.
3. ZONING ADMINISTRATOR SHALL VERIFY COMPLIANCE WITH:
Application Completeness_______(If incomplete, return to Applicant)
Zoning _______Conditional Use Permit #_______
Floodplain Development Permit #_____Board of Adjustment Resolution # _____
List Conditions of Approval or Attached: _____
_____
_____
4. BUILDING OFFICIAL SHALL VERIFY COMPLIANCE WITH:
Water Supply _____
Sanitation _____
5. IF THE BUILDING OFFICIAL SO AUTHORIZES, APPLICATION(S) FOR A BUILDING PERMIT THAT CONFORM MATERIALLY WITH ALL INFORMATION PROVIDED ABOVE MAY BE SUBMITTED TO THE BUILDING DEPARTMENT.
CITY OF CORTEZ — ZONING DEVELOPMENT PERMIT
The Zoning Administrator and Building Official must verify compliance with applicable City Land Use Code criteria for each of the categories listed in Sections 3 and 4 prior to consideration of applications for Building Permits.
1. APPLICANT SHALL COMPLETE:
2. APPLICANT SHALL ATTACH TWO (2) COPIES OF A COMPLETE SITE AND ACCESS PLAN OR PLAT SHOWING THE BUILDING OR STRUCTURE IN SUFFICIENT DETAIL TO DEMONSTRATE THAT THE PROPOSED CONSTRUCTION, RECONSTRUCTION OR CONVERSION, MOVING AND/OR ALTERATION IS IN CONFORMANCE WITH THE PROVISIONS OF THE APPLICABLE ZONE DISTRICT.
3. ZONING ADMINISTRATOR SHALL VERIFY COMPLIANCE WITH:
Application Completeness_______(If incomplete, return to Applicant)
Zoning _______Conditional Use Permit #_______
Floodplain Development Permit #_____Board of Adjustment Resolution # _____
List Conditions of Approval or Attached: _____
_____
_____
4. BUILDING OFFICIAL SHALL VERIFY COMPLIANCE WITH:
Water Supply _____
Sanitation _____
5. IF THE BUILDING OFFICIAL SO AUTHORIZES, APPLICATION(S) FOR A BUILDING PERMIT THAT CONFORM MATERIALLY WITH ALL INFORMATION PROVIDED ABOVE MAY BE SUBMITTED TO THE BUILDING DEPARTMENT.