Fees, Guarantees, Inspections, Off-Tract Improvements and Reservation of Public Areas
Application Charge | Review Escrow | ||
|---|---|---|---|
1. | Subdivision | ||
a. Minor Subdivision | $500 | $3,000 (Replenish at $2,000) | |
b. Preliminary Major Subdivision | $750 | $1,000/Lot | |
$5,000 Minimum (Replenish at $2,000) | |||
$30,000 Maximum initial deposit | |||
c. Final Major Subdivision | $500 | $1,000/lot | |
$5,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
d. Concept Plan* | |||
1. Minor Subdivision | $200 | $2,000 (Replenish at $1,000) | |
2. Major Subdivision | $500 | $3,000 (Replenish at $2,000) | |
e. Amended Minor, Prelim. Major, or Final Major | $500 | $1,000/lot | |
$3,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
2. | Site Plan | ||
a. Minor Site Plan | $500 | $4,000 (Replenish at $2,000) | |
b. Preliminary Major Site Plan | $500 | $4,000/acre of disturbance | |
$5,000 Minimum (Replenish at $2,000) | |||
$30,000 Maximum initial deposit | |||
c. Final Major Site Plan | $500 | $4,000/acre of disturbance | |
$5,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
d. Concept Plan* | |||
1. Minor Site Plan | $200 | $2,000 | |
2. Major Site Plan | $200 | $3,000 | |
e. Home Occupation | $200 | $500 | |
f. Amended Minor, Prelim. Major, or Final Major | $500 | $2,000 Minimum (Replenish at $1,000) | |
3. | Variances | ||
a. Appeals (40:55D-70a) | $200 Residential | $3,000 each | |
$500 Commercial/Industrial | |||
b. Interpretation (40:55D-70b) | $200 Residential | $3,000 each | |
$500 Commercial/ Industrial | |||
c. Bulk (40:55D-70c) | $200 Residential | $3,000 each | |
$500 Commercial/ Industrial | |||
d. Use (40:55D-70d) | $200 Residential | $5,000 | |
$500 Commercial/Industrial | |||
e. Permit (40:55D-34 & 35) | $200 Residential | $2,000 | |
$500 Commercial/Industrial | |||
4. | Certification of Pre-Existing Nonconforming Use (N.J.S.A. 40:55D-68) | ||
Application Charge: | $200 Residential $500 Commercial/Industrial | ||
Review Escrow: | $5,000 | ||
4. | Certified List of Property Owners | ||
See Section 706D3 of this ordinance | $0.25/name or $10, whichever is greater | None required | |
5. | Copy of Minutes, Transcripts or Decisions | ||
See Section 706E2 and 708C of this ordinance | $0.75/page for first ten pages copied | None required | |
$0.50/page for the next ten pages | |||
$0.25/page for each additional copy | |||
$2.00 for each CD | |||
6. | Subdivision Approval Certificate | ||
See Section 1004 of this ordinance | $15 per certificate | None required | |
7. | Certificate of Compliance or Certificate of All Taxes Paid to Date | $5 per certificate | None required |
8. | Special Meeting (as requested by the applicant) | $500 | None required |
9. | Geographic Information System Fee: In addition to any other applicable fees, there shall be assessed a charge of twenty-five dollars ($25.00) to each property owner or other applicant who makes an application under this section that will result in any change in the existing lot lines within the Township, the change in the building footprint of an existing structure, the construction of a new structure, or any other change that would result in a revision to the Township Geographic Information System atlas. This fee shall be specifically allocated to and shall be used to pay for the cost of updating the said atlas. | ||
*Fee and escrows paid in connection with concept applications shall be credited toward the fee and escrows required for minor and major subdivision and minor and major site plan applications once submitted within one (1) year of the Board's review of the concept plan. |
Developer's Cost Total Enlargement or Improvement Cost | = | Development gpd Total Tributary gpd |
Developer's Cost Total Project Cost | = | Development Tributary gpd Total Tributary gpd to New System |
Developer's Cost Total Cost of Roadway Improvement and/or Extension | = | Additional Peak-Hour Traffic Generated by the Development Future Total Peak-Hour Traffic |
Developer's Cost Total Enlargement or Improvement Cost of Drainage Facilities [Amended by Ord. #2008-05 § 7] | = | Development cfs Total Tributary cfs |
Fees, Guarantees, Inspections, Off-Tract Improvements and Reservation of Public Areas
Application Charge | Review Escrow | ||
|---|---|---|---|
1. | Subdivision | ||
a. Minor Subdivision | $500 | $3,000 (Replenish at $2,000) | |
b. Preliminary Major Subdivision | $750 | $1,000/Lot | |
$5,000 Minimum (Replenish at $2,000) | |||
$30,000 Maximum initial deposit | |||
c. Final Major Subdivision | $500 | $1,000/lot | |
$5,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
d. Concept Plan* | |||
1. Minor Subdivision | $200 | $2,000 (Replenish at $1,000) | |
2. Major Subdivision | $500 | $3,000 (Replenish at $2,000) | |
e. Amended Minor, Prelim. Major, or Final Major | $500 | $1,000/lot | |
$3,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
2. | Site Plan | ||
a. Minor Site Plan | $500 | $4,000 (Replenish at $2,000) | |
b. Preliminary Major Site Plan | $500 | $4,000/acre of disturbance | |
$5,000 Minimum (Replenish at $2,000) | |||
$30,000 Maximum initial deposit | |||
c. Final Major Site Plan | $500 | $4,000/acre of disturbance | |
$5,000 Minimum (Replenish at $2,000) | |||
$20,000 Maximum initial deposit | |||
d. Concept Plan* | |||
1. Minor Site Plan | $200 | $2,000 | |
2. Major Site Plan | $200 | $3,000 | |
e. Home Occupation | $200 | $500 | |
f. Amended Minor, Prelim. Major, or Final Major | $500 | $2,000 Minimum (Replenish at $1,000) | |
3. | Variances | ||
a. Appeals (40:55D-70a) | $200 Residential | $3,000 each | |
$500 Commercial/Industrial | |||
b. Interpretation (40:55D-70b) | $200 Residential | $3,000 each | |
$500 Commercial/ Industrial | |||
c. Bulk (40:55D-70c) | $200 Residential | $3,000 each | |
$500 Commercial/ Industrial | |||
d. Use (40:55D-70d) | $200 Residential | $5,000 | |
$500 Commercial/Industrial | |||
e. Permit (40:55D-34 & 35) | $200 Residential | $2,000 | |
$500 Commercial/Industrial | |||
4. | Certification of Pre-Existing Nonconforming Use (N.J.S.A. 40:55D-68) | ||
Application Charge: | $200 Residential $500 Commercial/Industrial | ||
Review Escrow: | $5,000 | ||
4. | Certified List of Property Owners | ||
See Section 706D3 of this ordinance | $0.25/name or $10, whichever is greater | None required | |
5. | Copy of Minutes, Transcripts or Decisions | ||
See Section 706E2 and 708C of this ordinance | $0.75/page for first ten pages copied | None required | |
$0.50/page for the next ten pages | |||
$0.25/page for each additional copy | |||
$2.00 for each CD | |||
6. | Subdivision Approval Certificate | ||
See Section 1004 of this ordinance | $15 per certificate | None required | |
7. | Certificate of Compliance or Certificate of All Taxes Paid to Date | $5 per certificate | None required |
8. | Special Meeting (as requested by the applicant) | $500 | None required |
9. | Geographic Information System Fee: In addition to any other applicable fees, there shall be assessed a charge of twenty-five dollars ($25.00) to each property owner or other applicant who makes an application under this section that will result in any change in the existing lot lines within the Township, the change in the building footprint of an existing structure, the construction of a new structure, or any other change that would result in a revision to the Township Geographic Information System atlas. This fee shall be specifically allocated to and shall be used to pay for the cost of updating the said atlas. | ||
*Fee and escrows paid in connection with concept applications shall be credited toward the fee and escrows required for minor and major subdivision and minor and major site plan applications once submitted within one (1) year of the Board's review of the concept plan. |
Developer's Cost Total Enlargement or Improvement Cost | = | Development gpd Total Tributary gpd |
Developer's Cost Total Project Cost | = | Development Tributary gpd Total Tributary gpd to New System |
Developer's Cost Total Cost of Roadway Improvement and/or Extension | = | Additional Peak-Hour Traffic Generated by the Development Future Total Peak-Hour Traffic |
Developer's Cost Total Enlargement or Improvement Cost of Drainage Facilities [Amended by Ord. #2008-05 § 7] | = | Development cfs Total Tributary cfs |