Site or Off-Tract Improvements
Applicant's contribution | = | Applicant generated traffic to be accommodated by the improvement
(peak-hour volume) | X | Total cost of improvement |
Capacity as a result of the improvement (peak-hour volume) |
Applicant's contribution | = | Development generated peak runoff to be accommodated by the
improvement (cfs, peak 25-year storm) | X | Total cost of improvement |
Approximate peak runoff generated by existing drainage area
contributory to subject improvement (cfs, peak 25-year storm) |
Applicant's contribution | = | Flow to be accommodated by the improvement (gpd) | X | Total cost of improvement |
Capacity of improvement (gpd) |
Site or Off-Tract Improvements
Applicant's contribution | = | Applicant generated traffic to be accommodated by the improvement
(peak-hour volume) | X | Total cost of improvement |
Capacity as a result of the improvement (peak-hour volume) |
Applicant's contribution | = | Development generated peak runoff to be accommodated by the
improvement (cfs, peak 25-year storm) | X | Total cost of improvement |
Approximate peak runoff generated by existing drainage area
contributory to subject improvement (cfs, peak 25-year storm) |
Applicant's contribution | = | Flow to be accommodated by the improvement (gpd) | X | Total cost of improvement |
Capacity of improvement (gpd) |