Definitions.
"Annual high wave run up"is the distance over which the maximum annually occurring significant wave height and associated peak period run-up and wash across the shoreline.
"Basement"means the portion of a building having its floor subgrade (below ground level) on all sides.
"Building footprint"shall mean all parts of a main building (excluding roof overhangs) that rest on the ground directly or indirectly, including those portions of the building that are supported by posts, piers, or columns. Building footprint also includes attached garages, covered carports, bay windows with floor space, lanais, decks, cantilevered decks. This definition does not include vertical access, such as stairs or ramps.
"County Engineer"means the County Engineer of the County of Kaua'i or his/her authorized representative.
"Flood" or "flooding"means a general condition of partial or complete inundation of normally dry land areas from overflow of inland or marine water resulting from any source or the unusual and rapid accumulation of runoff or surface waters from any source.
"Kaua'i Sea Level Rise Constraint District Viewer"is an online atlas in effect on October 14, 2022 and generated by data used in the creation of the Hawai'i Sea Level Rise Vulnerability and Adaptation Report that was mandated by Act 83, Session Laws of Hawai'i (SLH) 2014 and Act 32, SLH 2017. The Viewer provides visualizations depicting projections of future annual high wave run up and passive flooding hazards due to rising sea levels. The methodology and data were provided by the University of Hawai'i School of Ocean and Earth Science and Technology (UH SOEST) through a collaborative project led by the University of Hawai'i Sea Grant College Program (Hawai'i Sea Grant) in partnership with DLNR and the State of Hawai'i Office of Planning, and published under Anderson et al. 2018.
"Lowest floor"means the lowest floor of the lowest enclosed area (including basement). An unfinished or flood resistant enclosure, usable solely for parking of vehicles, building access or storage in an area other than a basement area is not considered a building's lowest floor, for the purposes of this Article, provided that such enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirements of this Chapter.
"Passive flooding"is flooding of low coastal lands due to sea level rise potentially from multiple sources, including but not limited to seawater flowing directly across the shoreline, backflow through storm drains, and rising groundwater tables.
"Planning Director"means the Planning Director of the Planning Department of the County of Kaua'i.
"Sea level rise flood elevation (SLRFE)"the individual depth above existing grade per grid unit provided by the County of Kauai Sea Level Rise Constraint District Viewer for both the high wave run up hazard and the passive flooding hazard when either of those are associated with 3.2 feet of sea level rise occurring within this century.
"Structure,"for the purpose of the Sea Level Rise District (S-SLR), means a walled and roofed building and includes gas or liquid storage tanks that are principally above ground and includes manufactured homes such as mobile homes.
"Substantial damage"means damage of any origin sustained by a structure whereby the cost of restoring the structure to its pre-damaged condition would equal or exceed 50% of the market value of the structure before the damage occurred.
"Substantial improvement"means any combination of repairs, reconstruction, improvements, or additions or other improvements to a structure over a 10 year period, where the cumulative cost equals or exceeds 50% of the market value of the structure before the start of construction of the first improvement during that 10 year period. If the structure has sustained substantial damage, any repairs are considered substantial improvement regardless of the actual repair work performed. The cost of any substantial improvement, including the cost to repair damage to pre-damage condition, shall be reviewed and determined by the County Engineer or his/her authorized representative. The term does not, however, include either: (1) any project for improvement of a structure to correct existing violations of a State or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions, or (2) any alteration of a "historic structure," provided that the alteration will not preclude the structure's continued designation as a "historic structure."