Within 62 days of receipt of the complete application and site plan, the Village Planning Board shall render a decision to approve, approve with conditions, or deny, and shall forward the decisions to the Zoning Enforcement Officer unless the time period is extended by the mutual consent of the Village Planning Board and the applicant. Said sixty-two-day time period shall commence at the time the complete application and site plan are first presented at a duly called Village Planning Board meeting. If the application is required to be referred to the County Planning Board in accord with Article 12-B, § 239-m, of the General Municipal Law, the Village Planning Board shall not act within the first 30 days following the referral to the County Planning Board unless the County Planning Board provides a written reply within the 30 days. If the Village Planning Board fails to act within said sixty-two-day period or extension that has been granted, the site plan shall be considered approved.