Specific Criteria for Special Exceptions, Conditional Uses, and Uses Permitted by Right
Tower-Based | |||
|---|---|---|---|
WCF Out of ROW | WCF in ROW | ||
Height | Tower-based WCFs shall be designed to minimum functional height. Applicants must submit documentation justifying the total height. | Tower-based WCFs shall be designed to minimum functional height. Applicants must submit documentation justifying the total height. | |
Lot size | Only use on lot: | Subject to underlying zoning district. | Not applicable. |
Combined with another use on lot: | Area needed to accommodate the WCF and guy wires, equipment building, security fence, and buffer planting. | Not applicable. | |
Setbacks | Towers: | Setback from property lines at least 100% of the combined height of the wireless support structure and antenna, or the underlying district requirement, whichever is greater. | Setback from existing buildings at least 100% of the combined height of the wireless support structure and antenna. |
Equipment buildings: | Subject to underlying zoning district. | Not applicable. | |
From a residential district or use: | 100 feet. | 100 feet | |
Non-Tower Based | |||
|---|---|---|---|
WCF Out of ROW | WCF in ROW | ||
Height | On building or similar structure: | WCF shall not exceed a height of 15 feet above the roof or parapet, whichever is higher, unless the WCF applicant obtains a special exception. | Not applicable. |
On streetlights, utility poles, traffic signals, signs and similar structures: | Not applicable. | WCF located above the surface grade shall consist of equipment components designed at the minimum functional height and that are compatible in scale and proportion to the structures upon which they are mounted. All equipment shall be the smallest and least visibly intrusive equipment feasible. | |
General: | Applicants must submit documentation justifying the total height. | Applicants must submit documentation justifying the total height of the structure. | |
Setbacks | Mounted antenna: | Subject to underlying zoning district or setback of existing wireless support structure. | Not applicable. |
Equipment buildings: | WCF Equipment buildings shall comply with minimum requirements of underlying District. | Not applicable. | |
Lot size | Subject to underlying zoning district. | Not applicable. | |
WCF Review Time frames | ||
|---|---|---|
Borough shall notify the applicant in writing of any information that may be required to complete application. | Borough shall approve or deny the application unless a shorter time period is applicable under the Pennsylvania MPC. | |
New Tower-Based WCFs | Within 30 calendar days of the date the application was filed with the Borough. | Within 150 days* of submission of an application for a WCF. |
Non-Tower-Based WCFs | Within 30 calendar days of the date the application was filed with the Borough. | Within 90 days* of submission of an application for a WCF. |
Eligible Facilities** Requests (as defined) | Within 30 calendar days of the date the application was filed with the Borough. | Within 60 days* of submission of an application for a WCF. |
NOTES: | |
|---|---|
* | The time period may be tolled by mutual agreement or in cases where the Borough informs the applicant in a timely manner that the application is incomplete. If an application is considered incomplete, the time period begins running again as soon as the applicant makes a supplemental submission, but may be tolled again if the Borough provides written notice to the applicant within 10 days that the application remains incomplete and specifically delineates which of the deficiencies specified in the original notice of incompleteness have not been addressed. |
** | The Borough shall only require the applicant to provide documentation that is reasonably related to determining whether the request is for an eligible facility. |
Specific Criteria for Special Exceptions, Conditional Uses, and Uses Permitted by Right
Tower-Based | |||
|---|---|---|---|
WCF Out of ROW | WCF in ROW | ||
Height | Tower-based WCFs shall be designed to minimum functional height. Applicants must submit documentation justifying the total height. | Tower-based WCFs shall be designed to minimum functional height. Applicants must submit documentation justifying the total height. | |
Lot size | Only use on lot: | Subject to underlying zoning district. | Not applicable. |
Combined with another use on lot: | Area needed to accommodate the WCF and guy wires, equipment building, security fence, and buffer planting. | Not applicable. | |
Setbacks | Towers: | Setback from property lines at least 100% of the combined height of the wireless support structure and antenna, or the underlying district requirement, whichever is greater. | Setback from existing buildings at least 100% of the combined height of the wireless support structure and antenna. |
Equipment buildings: | Subject to underlying zoning district. | Not applicable. | |
From a residential district or use: | 100 feet. | 100 feet | |
Non-Tower Based | |||
|---|---|---|---|
WCF Out of ROW | WCF in ROW | ||
Height | On building or similar structure: | WCF shall not exceed a height of 15 feet above the roof or parapet, whichever is higher, unless the WCF applicant obtains a special exception. | Not applicable. |
On streetlights, utility poles, traffic signals, signs and similar structures: | Not applicable. | WCF located above the surface grade shall consist of equipment components designed at the minimum functional height and that are compatible in scale and proportion to the structures upon which they are mounted. All equipment shall be the smallest and least visibly intrusive equipment feasible. | |
General: | Applicants must submit documentation justifying the total height. | Applicants must submit documentation justifying the total height of the structure. | |
Setbacks | Mounted antenna: | Subject to underlying zoning district or setback of existing wireless support structure. | Not applicable. |
Equipment buildings: | WCF Equipment buildings shall comply with minimum requirements of underlying District. | Not applicable. | |
Lot size | Subject to underlying zoning district. | Not applicable. | |
WCF Review Time frames | ||
|---|---|---|
Borough shall notify the applicant in writing of any information that may be required to complete application. | Borough shall approve or deny the application unless a shorter time period is applicable under the Pennsylvania MPC. | |
New Tower-Based WCFs | Within 30 calendar days of the date the application was filed with the Borough. | Within 150 days* of submission of an application for a WCF. |
Non-Tower-Based WCFs | Within 30 calendar days of the date the application was filed with the Borough. | Within 90 days* of submission of an application for a WCF. |
Eligible Facilities** Requests (as defined) | Within 30 calendar days of the date the application was filed with the Borough. | Within 60 days* of submission of an application for a WCF. |
NOTES: | |
|---|---|
* | The time period may be tolled by mutual agreement or in cases where the Borough informs the applicant in a timely manner that the application is incomplete. If an application is considered incomplete, the time period begins running again as soon as the applicant makes a supplemental submission, but may be tolled again if the Borough provides written notice to the applicant within 10 days that the application remains incomplete and specifically delineates which of the deficiencies specified in the original notice of incompleteness have not been addressed. |
** | The Borough shall only require the applicant to provide documentation that is reasonably related to determining whether the request is for an eligible facility. |