CHAPTER 18

32 GENERAL PROVISIONS – NONCONFORMANCE, TEMPORARY USES, AND RE-USE OF FACILITIES

§ 18.32.010 Purpose.

The purposes of this chapter are to:
A. 
Establish the legal status of a nonconformance by creating provisions through which a nonconformance may be maintained, altered, reconstructed or must be terminated;
B. 
Provide for the temporary establishment of uses that are not otherwise permitted in a zone and to regulate such uses by their scope and period of use; and
C. 
Encourage the adaptive re-use of existing public facilities which will continue to serve the community, and to ensure public review of redevelopment plans by allowing:
1. 
Temporary re-use of closed public school facilities retained in school district ownership, and the reconversion of a temporary re-use back to a school use;
2. 
Permanent re-use of surplus nonresidential facilities (e.g., schools, fire stations, government facilities) not retained in school district ownership; or
3. 
Permanent re-use of historic structures listed on the National Register or designated as county landmarks.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. No. 2026-689)

§ 18.32.020 Nonconformance – Applicability.

A. 
Except as specifically detailed in other portions of this code, all nonconformances shall be subject to the provisions of this chapter.
1. 
For details regarding critical areas nonconformance regulations, see NMC § 18.24.055.
B. 
The provisions of this chapter do not supersede or relieve a property owner from compliance with:
1. 
The requirements of NMC Title 15, Buildings and Construction; or
2. 
The provisions of this code beyond the specific nonconformance addressed by this chapter.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2026-682; Ord. No. 2026-689)

§ 18.32.030 Nonconformance – Determining status.

A. 
Any use, or site improvement (e.g., landscaping or signage) shall be considered a legal nonconformance if:
1. 
It was legally established; and
2. 
The use no longer meets the limitations applicable to the zone in which it is located; and/or
3. 
The site improvement does not comply with the current standards of this title, including but not limited to: density, dimensions, landscaping, parking, sign and/or design standards.
B. 
A change in the required permit review process shall not create a nonconformance.
C. 
Any nonconformance that is brought into conformance for any period of time shall forfeit status as a nonconformance, except as specified by NMC § 18.32.060.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. No. 2026-689)

§ 18.32.040 Nonconformance – Abatement of illegal use or site improvement.

Any use or site improvement not established in compliance with use and development standards in effect at the time of establishment shall be deemed illegal and shall be discontinued or terminated and subject to removal pursuant to the applicable provisions of city code.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. No. 2026-689)

§ 18.32.050 Nonconformance – Continuation and maintenance of nonconformance.

A nonconformance may be continued or physically maintained as provided by this chapter.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. No. 2026-689)

§ 18.32.060 Nonconformance – Re-establishment of discontinued nonconforming use.

A nonconforming use may be re-established as a nonconformance, except any nonconforming use that is discontinued for a period of 12 continuous months shall be deemed abandoned and shall not be re-established.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. No. 2026-689)

§ 18.32.070 Nonconformance – Repair or reconstruction of nonconforming structure.

A. 
A damaged, destroyed, or demolished nonconforming improvement may be repaired or reconstructed under the following circumstances:
1. 
The extent of the previously existing nonconformance is not increased, except as provided in subsection (A)(3)(b) of this section and in NMC § 18.24.055 (Nonconformances);
2. 
If required, a building permit application for repair or reconstruction is submitted within 12 months of the occurrence of damage or destruction; and
3. 
The improvement has not been damaged, destroyed, or demolished beyond 50% of the subject property's assessed or appraised value, whichever is higher, except under the following circumstances:
a. 
Residential site improvements that are destroyed by fire or natural disaster may be rebuilt to their pre-fire/disaster condition.
b. 
Structures in the shopping center subdistrict (SCS) that are destroyed by fire or natural disaster may be rebuilt to their pre-fire/disaster condition, subject to the following criteria:
4. 
The building has not been vacant for a period of one year or longer;
5. 
The current or most recent use of the building is a permitted use in the shopping center subdistrict;
6. 
The rebuilt structure complies with adopted design standards to the degree possible in the building's pre-fire/disaster location; and
7. 
The gross floor area of the rebuilt structure is no more than 15% greater than the gross floor area of the pre-loss structure.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2017-564 § 26; Ord. 2019-585 § 3 (Exh. 1); Ord. No. 2026-689)

§ 18.32.080 Nonconformance – Modifications to nonconforming site improvement.

Modifications to a nonconforming site improvement may be permitted, provided the modification does not increase the area, height or degree of an existing nonconformity, except as allowed by NMC § 18.32.070. Modifications required by federal, state or local law shall be exempt from this provision.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2019-585 § 3 (Exh. 1); Ord. No. 2026-689)

§ 18.32.090 Nonconformance – Expansion of nonconformance prohibited.

A nonconformance may not be expanded, except as allowed by NMC § 18.32.070. Expansions subject to control by federal, state or local law shall be exempt from this provision. Such expansion may refer, but is not limited to, required replacement of gasoline storage tanks to come into compliance with current regulations.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2019-585 § 3 (Exh. 1); Ord. No. 2026-689)

§ 18.32.100 Temporary use permits – Uses requiring permits.

Except as provided by NMC § 18.32.110, a temporary use permit shall be required for:
A. 
Uses not otherwise permitted in the zone that can be made compatible for periods of limited duration and/or frequency; or
B. 
Limited expansion of any use that is otherwise allowed in the zone but which exceeds the intended scope of the original land use approval.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.110 Temporary use permits – Exemptions to permit requirement.

A. 
The following uses shall be exempt from requirements for a temporary use permit when located in the CB, NB, O or I zones when the use does not exceed a total of 14 days each calendar year:
1. 
Amusement rides, carnivals, or circuses;
2. 
Community festivals;
3. 
Parking lot sales; and
4. 
Fireworks stands, subject to the provisions of the city's fireworks ordinance.
B. 
Any use not exceeding a cumulative total of two days each calendar year shall be exempt from requirements for a temporary use permit.
C. 
Any community event held in a public park and not exceeding a period of seven days shall be exempt from requirements for a temporary use permit.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2001-239 § 25; Ord. 2003-274 § 1)

§ 18.32.115 Temporary use permit.

A. 
Complete Application. Applications for a temporary use permit shall be considered fully complete once the department determines that the application contains the following materials:
1. 
Description of proposed temporary use.
2. 
Description of proposed dates of temporary use.
3. 
Total days of operation.
4. 
Confirmation if the same temporary use has been permitted for the same use during the same calendar year as now proposed.
5. 
Response to approval criteria in NMC § 18.44.030.
(Ord. 2020-611 § 17)

§ 18.32.120 Temporary use permits – Duration and frequency.

Unless specified elsewhere in this chapter, temporary use permits shall be limited in duration and frequency as follows:
A. 
The temporary use permit shall be effective for no more than 180 days from the date of the first event or occurrence;
B. 
The temporary use shall not exceed a total of 60 days, provided that this requirement applies only to the days that the event(s) actually takes place;
C. 
The temporary use permit shall specify a date upon which the use shall be terminated and removed;
D. 
A temporary use permit shall not be granted for the same temporary use on a property more than once per calendar year; provided, that a temporary use permit may be granted for multiple events during the approval period; and
E. 
The director may extend the time period set forth in subsection (B) of this section, in an amount not to exceed 180 days, based upon reasonable conditions being imposed relating to the health, safety and welfare of the public.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994; Ord. 2015-529 § 3 (Exh. A))

§ 18.32.130 Temporary use permits – Parking.

Parking and access for proposed temporary uses shall be approved by the city.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.140 Temporary use permits – Traffic control.

The applicant for a proposed temporary use shall provide any parking/traffic control attendants as specified by the city.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.145 Temporary education or public facilities.

Temporary education or public structures may be permitted provided that such structures are:
A. 
Allowed only during periods of permit review by the appropriate permitting agency and active construction or remodeling.
B. 
Do not exceed the capacity or square footage of the structure to be constructed or remodeled.
C. 
Removed within 30 days of project completion or cessation of work.
D. 
However, a temporary structure used for educational purposes, such as a modular classroom at a school site, may be permitted to be placed on a site for up to 12 months as a temporary structure. An additional 12 months may be granted by the director. At the end of the permitted period the use will be required to meet the standards of this code to remain on the site. Such standards include but are not limited to parking and landscaping requirements.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.150 Temporary construction buildings.

Temporary structures for storage of tools and equipment, or for supervisory offices may be permitted for construction projects, provided that such structures are:
A. 
Allowed only during periods of active construction; and
B. 
Removed within 30 days of project completion or cessation of work.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.160 Temporary construction residence.

A. 
A mobile home may be permitted on a lot as a temporary dwelling for the property owner, provided a building permit for a permanent dwelling on the site has been obtained.
B. 
The temporary mobile home permit shall be effective for a period of 12 months. The permit may be extended for one additional period of 12 months if the permanent dwelling is constructed with a finished exterior by the end of the initial approval period.
C. 
The mobile home shall be removed within 90 days of:
1. 
The expiration of the temporary mobile home permit; or
2. 
The issuance of a certificate of occupancy for the permanent residence, whichever occurs first.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.170 Temporary mobile home for medical hardship.

A. 
A mobile home may be permitted as a temporary dwelling on the same lot as a permanent dwelling, provided:
1. 
The applicant demonstrates the temporary dwelling is necessary to provide daily care to an individual certified by a physician as needing such care;
2. 
The primary provider of daily care shall reside on-site; and
3. 
The mobile home together with the permanent residence shall meet the setback, height, building footprint, and lot coverage provisions of the applicable zone.
B. 
Temporary mobile home permits for medical hardships shall be effective for 12 months. Extensions of the temporary mobile home permit may be approved in 12 month increments subject to demonstration of continuing medical hardship.
C. 
The mobile home shall be removed within 90 days of:
1. 
The expiration of the temporary mobile home permit; or
2. 
The cessation of provision of daily care.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.180 Temporary real estate offices.

One temporary real estate office may be located on any new residential development, provided that activities are limited to the initial sale or rental of property or units within the development. The office use shall be discontinued within one year of recording of a subdivision or short subdivision, or issuance of a final certificate of occupancy in the case of an apartment development.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.190 Re-use of facilities – General standards.

The interim or permanent re-use of surplus nonresidential facilities in residential zoned areas shall require that no more than 50 percent of the original floor area may be demolished for either permanent or interim re-use of facilities.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.200 Re-use of facilities – Re-establishment of closed public school facilities.

The re-establishment or reconversion of an interim nonschool use of school facilities back to school uses shall require a site plan and the issuance of a change of use permit or new occupancy permit.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)

§ 18.32.210 Re-use of facilities – Standards for conversion of historic buildings.

In order to insure that significant features of the property are protected, the following standards shall apply to conversion of historic buildings:
A. 
Gross floor area of building additions or new buildings required for the conversion shall not exceed 20 percent of the gross floor area of the historic building, unless allowed by the zone;
B. 
Conversions to apartments shall not exceed one dwelling unit for each 3,600 square feet of lot area, unless allowed by the zone; and
C. 
Any construction required for the conversion shall require certification of appropriateness from the King County landmark commission.
(Ord. 18 § 1, 1994; Ord. 45 § 1, 1994)