a. All work on any nonconforming project shall cease on the effective date of this ordinance, and all permits previously issued for work on nonconforming projects shall be revoked as of that date. Thereafter, work on nonconforming projects may begin, or may be continued, only pursuant to a special use permit issued by the Board of Adjustment (except as provided in paragraph b. of this section). The Board shall issue such a permit if it finds that the applicant has in good faith made substantial expenditures or incurred substantial binding obligations or otherwise changed his or her position in such substantial way in reasonable reliance on the land use law as it existed before the effective date of this ordinance and thereby would be unreasonably prejudiced if not allowed to complete his or her project as proposed. In considering whether these findings may be made, the Board shall be guided by the following.
1. All expenditures made pursuant to a validly issued and unrevoked building or zoning permit shall be considered as evidence of reasonable reliance on the land use law that existed before this ordinance became effective.
2. Except as provided in subparagraph 1. of this paragraph, no expenditures made between 180 days and the effective date of this ordinance shall be considered as evidence of reasonable reliance on the land use law that existed before this ordinance became effective. An expenditure is made at the time a party incurs a binding obligation to make that expenditure.
3. To the extent that expenditures are reasonable with a reasonable effort, a party shall not be considered prejudiced by having made those expenditures. For example, a party shall not be considered prejudiced by having made expenditure to acquire a potential development site if the property obtained is just as valuable under the new classification as it was under the old, for the expenditure can be recovered by resale of the property.
4. An expenditure shall be considered substantial if it is significant both in dollar amount and in terms of: (i) the total estimate cost of the proposed project; and (ii) the ordinary business practices of the developer.
5. A person shall be considered to have acted in good faith if actual knowledge of a proposed change in the land use law affecting the proposed development site could not be attributed to him or her.
6. Even though a person had actual knowledge of a proposed change in the land use law affecting a development site, the Board may still find that he or she acted in good faith if he or she did not proceed with his or her plans in a deliberate attempt to circumvent the effects of the proposed ordinance, the Board may find that the developer did not proceed in an attempt to undermine the proposed ordinance if it determines that: (i) at the time the expenditures were made, either there was considerable doubt about whether any ordinance would ultimately be passed, or it was not clear that the proposed ordinance would prohibit the intended development; and (ii) the developer had legitimate business reasons for making expenditures.
7. Nothing in this section shall interfere with the provisions in §
1-11 (Vested Right) of this ordinance. The requirements of paragraph a. of this section shall not apply to a nonconforming project if the Zoning Administrator certifies that actual construction of the project began at least 180 days before the effective date of this ordinance and that the work is at least 75% complete at the effective date of this ordinance, notwithstanding the two-year vested rights, §
1-11 of this ordinance.
b. The Board of Adjustment shall not consider any application for the special use permit authorized by paragraph a. of this section that is submitted more than 60 days after the effective date of this ordinance, unless it waives this requirement for good cause shown.
c. If the Board of Adjustment issues a special use permit pursuant to paragraph a. of this section, it may attach such reasonable conditions to the permit as it finds necessary to reduce the extent to which the nonconforming project is incompatible with the surrounding neighborhood. In particular, the Board may require that work on the nonconforming project be continuously maintained, if possible, and that the project be completed as expeditiously as possible.
d. The Zoning Administrator shall send copies of this subsection to owners (and developers, if different from the owners) of all properties in regard to which permits have been issued for nonconforming projects or in regard to which a nonconforming project is otherwise known to be under construction. This notice shall be personally delivered or sent by registered or certified mail not less than 15 days before the effective date of this ordinance.
e. The Board of Adjustment shall establish expedited procedures for hearing applications for special use permits under this subsection. These applications shall be heard, whenever possible, before the effective date of this ordinance, so that construction work is not needlessly interrupted.
f. When it appears from the developer’s plans, or otherwise, that the nonconforming project was intended to be or reasonably could be completed in phases, segments or other discrete units, the Board of Adjustment shall determine and not allow the nonconforming project to be constructed or completed in a fashion that is larger or more extensive than is necessary to allow the developer to recoup and obtain a reasonable rate of return on the expenditures he or she has made in connection with that nonconforming project.
(Ord. Z2013-01, passed 9-12-2013)