Review Processes And Procedures
The purpose of this chapter is to provide clear and predictable standards of review and processes for the administration of development, subdivisions, and uses within Oakley City.
No development, subdivision, or use may be undertaken within Oakley City unless all permits applicable to the proposed development, subdivision, or use are issued in accordance with the provisions of this Title.
| Table 13-5-8 – Review Cycles, Hearings, and Timelines by Subdivision Use Type | |||||
Use Type | Approval Stage | Max Review Phases | Max Public Hearings | City Turnaround Deadline** | Applicant Turnaround Deadline*** |
1-2
Family Residential* | Preliminary | 4 | 1 | 30
Business Days | 180
Calendar Days |
Final | 1 | 0 | 30
Business Days | 180
Calendar Days | |
All
Other Uses
| Preliminary | 6 | 2 | 30
Business Days | 180
Calendar Days |
Final | 1 | 0 | 30
Business Days | 180
Calendar Days | |
|
* Includes single-family homes, duplexes, and townhomes. **Describes the total time (per review cycle) the City may take to complete both Phase #2 and Phase #3. ***Describes the total time (per review cycle) the applicant may take to submit a revised application before the application expires. | |||||
The following table shows in more detail the vesting processes for various types of key planning and zoning approvals and permits (NOTE: Temporary Use Permits do not vest and run with the land): Table of Vesting of Approvals
| Master Planned Development (MPD) | Development Agreement (DA) | Zoning Change | Conditional Use Permit (CUP) or Low Impact Permit (LIP) | |
| Construction commences within 5 years | Remains valid | Remains valid | As described in the MPD, DA, and Rezone Ordinance | Expires if construction does not commence within 1 year (unless extension granted). |
| Construction does not commence within 5 years | Expires | Expires | Reverts to original (previous) zone per the Code (by Rezone Ordinance) | Expires after 1 year |
| Construction is completed per approved plans. | Remains valid if consistent with approval. | Remains valid until expiration date agreed to in DA. | Remains as described in the MPD, DA, and Rezone Ordinance | Remains valid, "runs with the land." |
| Changes to project prior to 5-year expiration | May require new MPD application | May require amendment to DA | Remains as described in the MPD, DA, and Rezone Ordinance. | If not expired, may require an additional application. |
| Changes after 5-year expiration (if nothing constructed.) | May require a new MPD application | May require new DA | Subject to original (previous) zoning requirements. | May require a new CUP or LIP, depending on the proposed use. |
| Changes requested after construction complete and DA expires | May require new or amended MPD application | May require new DA, depending on change | Remains as described in the Rezone Ordinance unless a new Rezone is requested. | May require a new CUP or LIP, depending on the proposed use. |
Review Processes And Procedures
The purpose of this chapter is to provide clear and predictable standards of review and processes for the administration of development, subdivisions, and uses within Oakley City.
No development, subdivision, or use may be undertaken within Oakley City unless all permits applicable to the proposed development, subdivision, or use are issued in accordance with the provisions of this Title.
| Table 13-5-8 – Review Cycles, Hearings, and Timelines by Subdivision Use Type | |||||
Use Type | Approval Stage | Max Review Phases | Max Public Hearings | City Turnaround Deadline** | Applicant Turnaround Deadline*** |
1-2
Family Residential* | Preliminary | 4 | 1 | 30
Business Days | 180
Calendar Days |
Final | 1 | 0 | 30
Business Days | 180
Calendar Days | |
All
Other Uses
| Preliminary | 6 | 2 | 30
Business Days | 180
Calendar Days |
Final | 1 | 0 | 30
Business Days | 180
Calendar Days | |
|
* Includes single-family homes, duplexes, and townhomes. **Describes the total time (per review cycle) the City may take to complete both Phase #2 and Phase #3. ***Describes the total time (per review cycle) the applicant may take to submit a revised application before the application expires. | |||||
The following table shows in more detail the vesting processes for various types of key planning and zoning approvals and permits (NOTE: Temporary Use Permits do not vest and run with the land): Table of Vesting of Approvals
| Master Planned Development (MPD) | Development Agreement (DA) | Zoning Change | Conditional Use Permit (CUP) or Low Impact Permit (LIP) | |
| Construction commences within 5 years | Remains valid | Remains valid | As described in the MPD, DA, and Rezone Ordinance | Expires if construction does not commence within 1 year (unless extension granted). |
| Construction does not commence within 5 years | Expires | Expires | Reverts to original (previous) zone per the Code (by Rezone Ordinance) | Expires after 1 year |
| Construction is completed per approved plans. | Remains valid if consistent with approval. | Remains valid until expiration date agreed to in DA. | Remains as described in the MPD, DA, and Rezone Ordinance | Remains valid, "runs with the land." |
| Changes to project prior to 5-year expiration | May require new MPD application | May require amendment to DA | Remains as described in the MPD, DA, and Rezone Ordinance. | If not expired, may require an additional application. |
| Changes after 5-year expiration (if nothing constructed.) | May require a new MPD application | May require new DA | Subject to original (previous) zoning requirements. | May require a new CUP or LIP, depending on the proposed use. |
| Changes requested after construction complete and DA expires | May require new or amended MPD application | May require new DA, depending on change | Remains as described in the Rezone Ordinance unless a new Rezone is requested. | May require a new CUP or LIP, depending on the proposed use. |