[Ord. #94-16, Appx. A; Ord. #04-13, § 8]
When any development proposal approved by the Planning Board, or Zoning Board of Adjustment includes the construction of off-site public improvements, the developer, owner or applicant shall pay to the City of Ocean City, prior to the issuance of any Development Permit or the start of construction, an inspection escrow fee equal to five percent (5%) of the estimated cost of the off-site improvement to be deposited in a construction inspection escrow account. Said estimate shall be approved by the Planning Board or Zoning Board of Adjustment Engineer. City inspection costs will be paid from escrow funds. Certificates of Occupancy or acceptance of such improvements shall not be issued until the City Engineer, Board of Adjustment Engineer or Planning Board Engineer, as the case may be, certifies in writing to the correctness and accuracy of all off-site improvements.