Upon installation and completion of the landscape, the County shall require inspection by an independent, certified irrigation designer; independent, certified landscape irrigation auditor; independent, licensed civil engineer; or independent, licensed landscape architect to verify that all landscape improvements were completed in accordance with this chapter. Open trench inspection shall be conducted as necessary. No subject construction project shall be deemed complete until complete inspection of the work has been performed, documented to comply fully with this chapter, and approved by the Director or designee. The inspection shall verify at minimum that:
(A)
The landscape improvements were installed in accordance with approved landscape checklist or landscape plan and with this chapter.
(B)
The irrigation system complies with manufacturer's installation specifications and is in a leakfree condition.
(C)
The installed irrigation system is functioning as designed, specified and approved.
(D)
The irrigation schedule is consistent with the hydrozones and plant factors, and will apply water at a rate at or below the maximum applied water allowance for the subject landscape.
(E)
The irrigation system does not cause water waste due to runoff, low head drainage, overspray or other similar condition.
(F)
The person responsible for long-term landscape maintenance and irrigation management at the property has received the recommended irrigation schedule.
(G)
The inspector has provided the County of Santa Cruz with a completed and signed certificate of installation that attests to the installation of a landscape compliant with this chapter, with attachments including a copy of the irrigation schedule and schedule of landscape and irrigation maintenance provided to the owner.
(Ord. 5148 § 1, 2013; Ord. 5218 § 1, 2016)