Final zoning and land development approval. In accordance with the preliminary zoning approval, an applicant may submit an application for final zoning and land development approval. In concert with the permissions of MPC Article VII-A,[7] the applicant shall submit a site plan and, concurrently, any related land development plans including construction plans for public and private improvements, permits and approvals, landscape plan, typical site cross-sections, common area plans, building elevations and other architectural drawings, public sewage, public water, stormwater facilities, highway occupancy permits (if applicable), agreement for dedication of roads and streets, parking agreements (if applicable), deed restrictions, easements, and protective covenants, and proof of approval from other agencies.
A.
Final zoning and land development approval submission. The following submission items for final zoning and land development approval are subject to review by the Planning Commission and to be approved by Borough Council.
B.
Final zoning and land development approval submission contents.
(2)
Worksheet 2: Site plan input worksheet.
(a)
Worksheet 2 provides a set of dimensional requirements needed for specific parcels to conform to the standards adopted in the Overlay.
(3)
Worksheet 3. Master plan reconciliation summary.
(a)
Worksheet 3 utilizes the standards put forth in Worksheet 1 and incorporates the applicant's site plan summary into the remaining development entitlement. This ensures that all developments remain in compliance with the Master Plan.
(4)
Submission Checklist 1. Final Zoning and Land Development Approval Submission.
(a)
Submission Checklist 1 provides the applicant a checklist of deliverables needed for final zoning and land development approval from the Borough. For the Borough to begin the review process, all submission items must be submitted simultaneously, unless otherwise permitted by the Commonwealth of Pennsylvania. In the case where another governmental or agency review is necessary, the applicant shall provide documentation proving that said process is underway. Submission Checklist 1 includes the following items:
1)
Site plan.
a)
A Site Plan shall be provided in an accurate and final form appropriate for recording. Land Development Plans shall be submitted on sheets measuring 24 inches by 36 inches, or other size requested by the Allegheny County Department of Real Estate. Where necessary to avoid sheets larger than the maximum size prescribed above, Site Plans shall be drawn on multiple sheets and accompanied by a key diagram showing relative location of the sections.
b)
The Site Plan shall be in such a format and/or such material as is required for recording by Allegheny County. The Site Plan shall also meet the following requirements:
i
Copy of the approved preliminary plan.
ii
Final land use table indicating specific building uses.
iii
Final plat, in accurate and final form for recording. The final plat shall include the following:
(i)
Title block, placed in the lower right-hand corner and containing the following information:
c)
Tract boundaries, right-of-way lines of streets, easements and other right-of-way lines with accurate distances to hundredths of a foot and bearings to 1/4 of a minute. Tract boundaries shall be determined by field survey only and shall be balanced and closed. Surveys shall be prepared in accordance with the standards contained in the Allegheny County Subdivision and Land Development Ordinance.
d)
Complete curve data for all curves included in the final plat, including radius, arc length, chord bearing and chord distance.
i
Location, type and size of all monuments and lot line markers. State whether found, set or to be set.
ii
Approved street names and street right-of-way widths.
iii
Lot numbers, lot dimensions, lot areas in square feet and building setback lines.
iv
Tabulation of area data in acres and square feet, including lots, parcels, units, areas dedicated for rights-of-way, etc., and total plan area.
v
Lot and block or tax map parcel numbers.
vi
Easements and rights-of-way for all public and private improvements, including widths, purposes and limitations, if any.
vii
Accurate dimensions, acreage and purpose of any property to be reserved as public or common open space.
viii
Indication of platting of adjacent property and the names of the adjacent property owners.
ix
Site location map, prepared in accordance with the Allegheny County Subdivision and Land Development Ordinance.
x
All required municipal certifications, which shall include the Municipal Engineer.
xi
Certification of plat preparation and accuracy by a registered surveyor.
xii
Certification of the dedication of streets and other property.
xiii
All other certifications, dedications and acknowledgments, as required by Allegheny County.
xiv
Plats which require access to a road under the jurisdiction of the Pennsylvania Department of Transportation shall contain a notice that, before driveway access is permitted, a highway occupancy permit is required in accordance with the Act of June 1, 1945, known as the "State Highway Law."
xv
Notation on the plan of any modifications or waivers granted to the provisions of this chapter.
2)
Construction plans for public and private improvements. Files shall be prepared by a registered professional on drafting sheets. The construction plans shall show the following:
a)
Conformity with the design standards specified in this chapter.
b)
Plan and center-line profile drawings of each street in the plan and extending at least 200 feet beyond the plan. Street profiles shall include complete vertical curve information.
c)
At least a typical cross-section of each street in a new development, extending at least 50 feet from the street center line to each side, or extending 25 feet from the right-of-way line to each side, whichever is greater.
d)
The location of all existing and proposed sanitary sewers, storm sewers, manholes, catch basins and endwalls within the site, and all necessary extensions thereof beyond the site.
e)
By plan, all pipe sizes, distances and directions of flow. Show sanitary sewer wye locations, including a station for each wye as measured from the downstream manhole.
f)
By profile, all pipe sizes, materials, distances and grades; and, top and invert elevations of all manholes, catch basins and endwalls. Show existing and proposed ground.
g)
All construction details for stormwater detention facilities, including any intake control structures, discharge control structures, underground storage tanks, sumps and stormwater detention basins.
h)
The locations of all other existing and proposed utilities including gas, water, fire hydrants, electric, telephone and cable TV.
i)
All easements and rights-of-way for public improvements.
3)
Permits and approvals. The applicant shall submit certified copies of all permits and approvals required by applicable federal and state laws and county codes and regulations, including, without limitation, the following:
a)
Allegheny County Conservation District adequacies and permits.
b)
Federal Aviation Administration and PennDOT Bureau of Aviation approvals where required.
c)
Pennsylvania Department of Environmental Protection stormwater, sewage facilities permit, general permit, wetland encroachment permits, stream encroachment/obstruction permits, etc.
d)
County of Allegheny and Commonwealth of Pennsylvania permits for any proposed roads or driveways.
e)
Water supply certification.
f)
Letters of intent to provide service from utilities companies.
g)
A copy of comments received, if any, from the Allegheny County Health Department on the stormwater management plan.
h)
When required by the Borough, additional information related to infill, redevelopment and or replacement in accordance with the Borough requirements.
i)
If required under this chapter, locations of street trees, groundcover/landscaping and sidewalks.
j)
Where applicable, plans of bridges and other improvements and shall contain sufficient information to provide complete working plans for the proposed construction including calculations and required Pennsylvania Engineer's Seal.
k)
Where individual onsite water supply systems are proposed, certification of the acceptability of the water supply system by the Pennsylvania Department of Environmental Protection must be submitted wherever their approval is required.
l)
Other certificates of approval as may be required by the Borough Engineer, Planning Commission and the Borough Council.
4)
Land development plans shall include the following information:
a)
Final grading plan. The final grading plan shall include all final contours, grades, floor elevations, permanent conservation measures, limit of disturbance line, typical keyway and/or benching details, and earthwork quantities in cubic yards.
b)
Final stormwater management plan, including all final calculations.
c)
Final soil erosion and sedimentation pollution control plan, as submitted to the Allegheny County Conservation District (ACCD), and evidence that the ACCD has issued a finding of adequacy.
e)
Ground floor height and ground floor land use activity diagram.
f)
Final photometric plan. The photometrics plan shall describe the maximum illumination values and average illumination value required. The location and effect of outdoor lighting on streets and residential lots in the line of sight of proposed lighting shall be provided by the applicant. A computer-generated lighting model with point-by-point illumination of all proposed lighting and areas expected to be illuminated, if applicable, is required. The lighting model shall include buildings, structures, parking areas and lot lines and shall be provided at the same scale as the final site plan.
g)
Survey. The applicant shall submit an engineering land survey of the lot certified by a professional land surveyor. The survey shall be at a scale of not more than one inch equals 100 feet. The plan shall be drawn in accordance with standard land surveying practices, and using standard map symbols to clearly indicate the following:
i
Name of the proposed project.
ii
Location map showing the subdivision/land development location within the boundaries of the Borough (including major transportation routes, title, North arrow and graphic scale).
iii
Existing lot lines, adjacent lot owner(s) names, lot and block numbers and recorded subdivision name with recording information.
iv
Name, address of current landowner(s), applicant and firm that prepared the survey.
v
The entire existing lot boundary with bearings and distances as surveyed.
vi
The total acreage of the entire existing land.
vii
Streets abutting the lot, indicating names, right-of-way widths and cartway widths and ownership (federal, state, county, municipal or private).
viii
Existing and proposed easements, indicating location, width, purpose and lessee.
ix
Location of existing buildings, sanitary sewer, storm sewer, water, gas, petroleum and high-pressure gas lines indicating line size, manholes, fire hydrants, utilities and other visible elements in the system on or adjacent to the lot proposed to be developed.
x
Existing contours at a minimum vertical interval of two feet.
xi
A description of the lot locating proposed, existing and preexisting gas and oil wells, location maps, dates of operation, and lease holder(s) shall be provided.
xii
Where practical, datum to which contour elevations refer shall refer to known, established elevations.
5)
Landscape plan.
a)
One landscape plan shall be provided in accordance with § 27-502.12.
i
For surface parking areas, see § 27-502.12A(1) for applicable requirements, unless the Applicant constructs pervious pavement for equivalent surface parking spaces in the Site Plan.
ii
Any required parking island shall have the same dimensions of a non-ADA parking space and shall be located within the parking area itself.
iii
Surface parking areas with greater than 45 surface parking spaces, inclusive of ADA spaces, shall provide an additional 1,000 square feet of landscape median for every additional 50 surface parking spaces.
iv
The regulations in § 27-502.12A(2) do not apply to the Riverfront Overlay.
v
For all nonresidential redevelopment, infill construction, excavation, and/or building expansion proposed within the site plan, see § 27-502.12B for applicable requirements.
b)
A landscape plan submitted as part of final zoning and land development approval shall contain the following supplemental items:
i
Master Plan area as approved in preliminary zoning approval as a background.
ii
Approximate locations and spacing of all proposed plant material with typical dimensions at maturity by species. Existing vegetation to remain shall also be illustrated.
iii
Botanical and common names of all plant species, their sizes and quantities as noted in a plant schedule and as individual callouts on the graphic.
6)
Typical site cross-sections. Site cross sections shall be created in accordance with the standards established by Sharpsburg Borough or elsewhere herein. All details of the cross-section, crowns, curb, pavement, subgrade and roadside ditches shall conform to the designated cross section. (State approval shall also be obtained where necessary.)
7)
Common area plans. All development proposals involving land or facilities that will be commonly owned among more than one titleholder shall include a diagram illustrating the location(s) and extent of said land at the time of plan application. The ownership and method of assuring perpetual maintenance to be applied to those areas which are to be used for recreational or other common purposes shall be defined and recorded in a manner reasonably and mutually acceptable to the Borough and applicant. Common area plans may or may not include public open space previously utilized in the Master Plan in the preliminary zoning approval application.
8)
Building elevations and other architectural drawings.
a)
Building elevations and other architectural drawings shall be provided for all developments other than single-family residential.
b)
Building elevations and other architectural drawings containing the following information shall be provided. Elevations and drawings shall be illustrated to scale (no less than 1/4 inch to one foot) showing:
i
Drawings or elevations depicting the front, rear and side facades of all proposed buildings including building's architectural features, exterior building materials, colors and/or finishes.
ii
The drawings or elevations shall indicate the height of the building in feet and number of stories and the building's relationship to the finished grade immediately surrounding the building.
iii
Spot elevations designating the existing and proposed grading.
9)
Level of service of public water and sewage supply. If water is to be provided by means other than private wells owned and maintained by the individual owners of lots within the development, applicants shall present evidence to the Borough that the development is supplied by an authorized Authority. This evidence shall take the form of a copy of a certificate of public convenience from the Pennsylvania Public Utility Commission or an application for such certificate, a cooperative agreement or a commitment or agreement to serve the area in question, whichever is appropriate, submitted to the Borough. All properties in the Riverfront Overlay shall connect with an approved public water supply system, if available. If the water distribution system cannot be tied-in with an approved public system, an individual well or spring must be installed and operated in full compliance with the latest Pennsylvania Department of Environmental Protection specifications covering such facilities. All land developments of other types must be equipped with a public water supply system, approved as adequate by the Borough Council.
a)
The plans for the installation of the mains of a water distribution system shall be prepared by the applicant and reviewed by the Borough Engineer. A statement of approval from the Borough Engineer shall be submitted to the Borough Council.
b)
Upon completion of water distribution and supply system, one copy of the plans for the system shall be filed with the Borough Council. The plan shall also be reviewed and approved by the Pennsylvania Department of Environmental Protection.
c)
Fire hydrants. It will be the responsibility of the applicant to provide all subdivisions and land developments with fire hydrants. Hydrants shall be installed with the installation of the water lines or as soon as they become available. The location of the hydrants shall be approximately every 1,000 feet and shall be subject to approval by the Borough on the final plat.
10)
Stormwater facilities.
a)
Land development plans shall be based on a stormwater management study performed in accordance with the Stormwater Management Ordinance (Chapter 17) of the Borough of Sharpsburg Municipal Code relating to stormwater management. A copy of said study shall be submitted.
b)
Where applicable, if the Allegheny County Conservation District or the PADEP has reviewed a stormwater management plan in accordance with PA Chapter 102 regulations that differs from the requirements set forth in the Stormwater Management Ordinance (Chapter 190), the approved ACCD and DEP plans authorizing the design and discharge together with a written request for modification from the ordinance shall be submitted.
11)
Highway occupancy permit. The applicant shall obtain a copy of the submitted application and approved permit for a highway occupancy permit (HOP) for plans that require access to a highway (Pennsylvania Route or United States Route) under the jurisdiction of the Pennsylvania Department of Transportation. The HOP plan shall contain a notice that a highway occupancy permit is required pursuant to Section 420 of the Act of June 1, 1945 (P.L. 1424, No. 428), known as the "State Highway Law," before driveway access to a state highway is permitted.
12)
Agreement for dedication of streets. When the Borough accepts dedication of all or some of the streets within the proposed subdivision/land development following completion, the Borough Council shall require the posting of financial security to secure the structural integrity of the streets in accordance with the design and specifications as depicted on the final site plan. The term for financial security for the maintenance of the streets shall be 10 months and the amount shall not exceed 5% of the actual cost of installation. If there are conditions related to the dedication of streets or related issues, those conditions and issues shall be noted in the site-related developer agreements.
13)
Shared off-street parking analysis (if applicable).
a)
If an applicant seeks to provide off-street parking spaces that can be used for multiple land uses, the applicant may prepare and submit a shared off-street parking analysis subject to approval by the Borough Traffic Engineer.
b)
The purpose of the shared off-street parking analysis shall be to:
i
Optimize available parking resources within the Riverfront Overlay;
ii
Minimize construction and maintenance costs associated with parking spaces;
iii
Enhance the existing character of the community by providing greater pedestrian access to and from shared off-street parking spaces;
iv
Maximize the land available for the development of public open space, residential, and mixed-use development.
c)
Shared off-street parking analysis submission items. The applicant shall submit a completed off-street parking model and off-street parking plan demonstrating how and where off-street parking requirements will be met as part of final zoning and land development approval.
i
Off-street parking model.
(i)
To identify where off-street parking spaces can be used for multiple land uses, the applicant shall prepare a model demonstrating the typical hourly demands for all residential dwelling units and nonresidential development square footage proposed in the development lot. The typical hourly demands shall be based on metrics published by the Urban Land Institute and are subject to any adopted/published changes to best practices
(ii)
The applicant shall submit an electronic copy of the off-street parking model to the Borough Traffic Engineer for further review.
(iii)
Approval from the Borough Traffic Engineer shall be based on the accuracy of all calculations presented in the off-street parking model and in accordance with the provisions stated herein.</
ii
Off-street parking plan.
(i)
The applicant shall prepare a scaled drawing that graphically depicts the proposed off-street parking associated with the development lot and its proposed buildings and/or parking structures. A parking plan shall include tabular data outlining the number of off-street parking facilities and number of shared off-street parking spaces within each facility.
(ii)
Any off-street parking plan that does not accurately reflect and/or satisfy the demand calculated by the off-street parking model shall be grounds for denial.
14)
Deed restrictions, easements, and protective covenants.
a)
Deed restrictions, easements and protective covenants, if any, shall be provided in a form for recording. Provisions within any declaration of covenants and restrictions shall include:
ii
General plan of development.
iii
Use restrictions and management responsibilities.
iv
Resolution of document conflicts.
v
Fees and related administrative coordination.
15)
Development lot-related developer agreements. The site-related developer's agreements shall include the bylaws for a Master Association, or other similar governing agreements for the contributions to and management of the Master Plan area, if not already submitted as part of preliminary zoning approval, as well as any relevant bylaws for building/association/neighborhood agreement(s) that are applicable to the final zoning and land development approval. Additionally, any bylaws associated with the improvement and maintenance of a public open space area, and deed restrictions in relation to the applicant's method of administering common areas, whether through an association/nonprofit corporation, or through a proposed declaration of condominium.
16)
Proof of approval from other agencies.
a)
Approval of the final plan application by the Borough Council shall be conditioned upon if Allegheny County, state or federal agencies approve the development. It shall be the applicant's responsibility to obtain all necessary approvals from Allegheny County, state and federal agencies and submit these approvals to the Borough including a notification from Pennsylvania Department of Environmental Protection regarding a sewer facilities plan revision approval or waiver (as applicable).
b)
Proof of approval of requests/responses/waivers and permit applications, if and/or where required, shall be including, but not limited to:
i
Pennsylvania Department of Transportation highway occupancy permits.
ii
Pennsylvania Department of Transportation traffic signal permits.
iii
Pennsylvania Department of Environmental Protection Sewerage Planning Module (or exemption if applicable).
iv
Pennsylvania Department of Environmental Protection National Pollutant Discharge Elimination System permits.
v
Pennsylvania Department of Environmental Protection water obstruction and encroachment permits.
vi
Pennsylvania Department of Economic Development and/or Federal Emergency Management Agency floodplain permits.
vii
Hampton-Shaler or otherwise authorized Water Authority approval.
viii
In addition, where any alteration or relocation of a stream or watercourse is proposed, documentation shall be submitted indicating that all affected adjacent municipalities have been notified of the proposed alteration or relocation. The Pennsylvania Department of Community and Economic Development and the Federal Insurance Administrator, or other applicable agency, shall also be notified whenever any such activity is proposed.
ix
Sharpsburg Borough Zoning Approval unless otherwise identified by the Borough.