Traffic Impact Analysis TIA
Traffic impacts, and how to mitigate them, are an important consideration for our community when a significant development is proposed. Public policy makers, citizens, and developers all have a stake in understanding and responding to additional demands on the transportation system. A traffic impact analysis (TIA) is a tool used to evaluate the incremental impacts that development, redevelopment and/or change or development use may have on the surrounding transportation system which helps local decision makers evaluate whether a development is appropriate for a site, or identify certain mitigation measures that are necessary to maintain safety and integrity of the transportation network.
After a completed development application (zoning permit, rezoning, etc.) has been filed, and upon initial submittal of a site or sketch plan, the Town of Siler City (Town) Planning Director or his/her designee shall determine the need for a TIA. Types of development applications could include, but are not limited to, multifamily residential, single family residential, commercial, or industrial. If warranted, the transportation consultant assigned by the Town shall prepare the TIA. At the discretion of the North Carolina Department of Transportation (NCDOT) and the Town, a Transportation Technical Memorandum (TTM), in lieu of a full TIA report, may be allowed for some developments. If proposed street connections are not consistent with adopted plans, Town policies, or professional standards, then an explanation or proposed transportation mitigation alternative that is equal or better should be discussed in the study. The NCDOT and the Town will be responsible for determining whether the alternative mitigation plan meets and/or exceeds the performance standards of the proposed street connections in the adopted plans and policies. The TIA review schedule will be determined as agreed to on the Town’s TIA scoping requirements, generally based on the number of study intersections.
A TIA will be required to accompany a development plan when expected gross trip generation is 1000 total trips or more both entering and exiting the site in a 24-hour period, and/or 100 total trips both entering and exiting the site during either the AM or PM peak (prior to any trip reductions are applied)- see L-8(h) below. The gross trip generation will be calculated by the Town based on information (proposed project summary and development plan) provided by the applicant and the final determination for requiring the TIA will be by the Town Planning Director. In the event that a site does not generate 1000 total trips both entering and exiting a site in a 24 hour period, and/or 100 total trips both entering and exiting the site during the AM or PM peak, a TIA may still be required for any site or sketch plan if the subject development reduces an intersection’s level-of-service (LOS), and/or poses a potential safety challenge to the public or as otherwise set forth herein. The latest version of the Institute of Transportation Engineers (ITE) Trip Generation Manual shall be used to determine the expected gross traffic volumes a specific site and/or a specific use will generate. The Town Planning Director or his/her designee may also determine the need for a TIA or TTM based on special circumstances associated with the development and may determine that a TIA is still necessary even if the gross trips fall below this threshold. This may be due to location, an intersection or thoroughfare nearby that is at or above capacity, public safety concerns, sight distance, existing congestion issues within the vicinity of the site, or the nature of the use. The Town may also require a TIA and/or TTM in any of the following scenarios:
A mandatory scoping meeting is required prior to beginning the TIA to discuss the requirements and strategies for a TIA specific to the site and the proposed development. Background information shall be submitted by the applicant five or more business days prior to the scoping meeting and shall include a conceptual site plan showing proposed access points, proposed land use and densities, structure and parking envelopes. The Town, the transportation consultant assigned by the Town, and the applicant(s) are required to attend the mandatory scoping meeting and the NCDOT district staff will be invited and encouraged to attend if access to a state road is involved. The applicant may invite members of his/her development team as needed.
An MOU shall be prepared by the transportation consultant assigned by the Town documenting the understood scope and parameters of the project. The MOU shall be signed by the applicant, the Town, and the NCDOT District Engineer if access to a state road is involved before the consultant can begin work on the TIA. Failure by the applicant to provide accurate information or failure by the assigned transportation consultant to follow the MOU shall result in disapproval of the TIA. If significant changes are made to the scoping parameters documented in the MOU, a revised MOU will be required.
After the scoping meeting, the transportation consultant assigned by the Town shall submit a summary of consultant fees for preparing the TIA to the Town. Per the MOU, the applicant(s) shall agree to provide payment in full to the Town for preparation of the TIA so that the Town can release the work to the consultant. The Town may require all or a portion of the estimated fees to be paid to the Town prior to the commencement of the work. Any additional service incurred by the transportation consultant in addition to the MOU must be approved by the Town and agreed to and paid for by the applicant prior to performance of the additional work.
The outline and contents of what is required to be included in the TIA will be discussed at the scoping meeting and included in the MOU. A detailed summary of the expected content and methodologies to be used in the TIA are discussed below.
Amended November 2, 2020
Traffic Impact Analysis TIA
Traffic impacts, and how to mitigate them, are an important consideration for our community when a significant development is proposed. Public policy makers, citizens, and developers all have a stake in understanding and responding to additional demands on the transportation system. A traffic impact analysis (TIA) is a tool used to evaluate the incremental impacts that development, redevelopment and/or change or development use may have on the surrounding transportation system which helps local decision makers evaluate whether a development is appropriate for a site, or identify certain mitigation measures that are necessary to maintain safety and integrity of the transportation network.
After a completed development application (zoning permit, rezoning, etc.) has been filed, and upon initial submittal of a site or sketch plan, the Town of Siler City (Town) Planning Director or his/her designee shall determine the need for a TIA. Types of development applications could include, but are not limited to, multifamily residential, single family residential, commercial, or industrial. If warranted, the transportation consultant assigned by the Town shall prepare the TIA. At the discretion of the North Carolina Department of Transportation (NCDOT) and the Town, a Transportation Technical Memorandum (TTM), in lieu of a full TIA report, may be allowed for some developments. If proposed street connections are not consistent with adopted plans, Town policies, or professional standards, then an explanation or proposed transportation mitigation alternative that is equal or better should be discussed in the study. The NCDOT and the Town will be responsible for determining whether the alternative mitigation plan meets and/or exceeds the performance standards of the proposed street connections in the adopted plans and policies. The TIA review schedule will be determined as agreed to on the Town’s TIA scoping requirements, generally based on the number of study intersections.
A TIA will be required to accompany a development plan when expected gross trip generation is 1000 total trips or more both entering and exiting the site in a 24-hour period, and/or 100 total trips both entering and exiting the site during either the AM or PM peak (prior to any trip reductions are applied)- see L-8(h) below. The gross trip generation will be calculated by the Town based on information (proposed project summary and development plan) provided by the applicant and the final determination for requiring the TIA will be by the Town Planning Director. In the event that a site does not generate 1000 total trips both entering and exiting a site in a 24 hour period, and/or 100 total trips both entering and exiting the site during the AM or PM peak, a TIA may still be required for any site or sketch plan if the subject development reduces an intersection’s level-of-service (LOS), and/or poses a potential safety challenge to the public or as otherwise set forth herein. The latest version of the Institute of Transportation Engineers (ITE) Trip Generation Manual shall be used to determine the expected gross traffic volumes a specific site and/or a specific use will generate. The Town Planning Director or his/her designee may also determine the need for a TIA or TTM based on special circumstances associated with the development and may determine that a TIA is still necessary even if the gross trips fall below this threshold. This may be due to location, an intersection or thoroughfare nearby that is at or above capacity, public safety concerns, sight distance, existing congestion issues within the vicinity of the site, or the nature of the use. The Town may also require a TIA and/or TTM in any of the following scenarios:
A mandatory scoping meeting is required prior to beginning the TIA to discuss the requirements and strategies for a TIA specific to the site and the proposed development. Background information shall be submitted by the applicant five or more business days prior to the scoping meeting and shall include a conceptual site plan showing proposed access points, proposed land use and densities, structure and parking envelopes. The Town, the transportation consultant assigned by the Town, and the applicant(s) are required to attend the mandatory scoping meeting and the NCDOT district staff will be invited and encouraged to attend if access to a state road is involved. The applicant may invite members of his/her development team as needed.
An MOU shall be prepared by the transportation consultant assigned by the Town documenting the understood scope and parameters of the project. The MOU shall be signed by the applicant, the Town, and the NCDOT District Engineer if access to a state road is involved before the consultant can begin work on the TIA. Failure by the applicant to provide accurate information or failure by the assigned transportation consultant to follow the MOU shall result in disapproval of the TIA. If significant changes are made to the scoping parameters documented in the MOU, a revised MOU will be required.
After the scoping meeting, the transportation consultant assigned by the Town shall submit a summary of consultant fees for preparing the TIA to the Town. Per the MOU, the applicant(s) shall agree to provide payment in full to the Town for preparation of the TIA so that the Town can release the work to the consultant. The Town may require all or a portion of the estimated fees to be paid to the Town prior to the commencement of the work. Any additional service incurred by the transportation consultant in addition to the MOU must be approved by the Town and agreed to and paid for by the applicant prior to performance of the additional work.
The outline and contents of what is required to be included in the TIA will be discussed at the scoping meeting and included in the MOU. A detailed summary of the expected content and methodologies to be used in the TIA are discussed below.
Amended November 2, 2020