94 PROCEDURES
• Time spent by the applicant to revise plans or provide additional studies or materials requested by the city. |
• Substantial project revisions made or requested by an applicant, in which case the time lines set forth will be calculated from the time that the city determines the revised application to be complete. |
• Projects involving the siting of an essential public facility. |
• Time spent preparing an environmental impact statement. |
• All time required to obtain a variance. |
• Time between submittal and resolution of an appeal, including remands and determination of significance. |
• Time required to process a request for reconsideration. |
• Any extension of time mutually agreed upon by the applicant and the city in writing. |
• Time spent by the applicant to revise plans or provide additional studies or materials requested by the city. |
• Substantial project revisions made or requested by an applicant, in which case the time lines set forth will be calculated from the time that the city determines the revised application to be complete. |
• Projects involving the siting of an essential public facility. |
• Time spent preparing an environmental impact statement. |
• All time required to obtain a variance. |
• Time between submittal and resolution of an appeal, including remands and determination of significance. |
• Time required to process a request for reconsideration. |
• Any extension of time mutually agreed upon by the applicant and the city in writing. |
Table 18.94-1 Land Use Application Types and Approval Authority | ||||||||
|---|---|---|---|---|---|---|---|---|
Application | Type | Approval Authority | Appeal to Hearing Examiner (HE) or Superior Court (SC5) | |||||
I | II | III | IV | Director or Staff | Hearing Examiner (HE) | City Council (CC) | ||
Administrative Variance | X | X | HE/SC | |||||
Administrative Interpretation | X | X | HE/SC | |||||
Boundary Line Adjustment | X | X | HE/SC | |||||
Binding Site Plan Review | X | X | HE/SC | |||||
Building Permit | X | X | HE/SC | |||||
Code Interpretation | X4 | X1 | HE/SC | |||||
Conditional Use Permit | X | X1 | X3 | SC | ||||
Critical Areas Permit | X | X | HE/SC | |||||
Full Variance | X | X1 | X3 | SC | ||||
Home Occupation | X | X | HE/SC | |||||
Legal Lot Determination | X | X | HE/SC | |||||
Plan and Zoning Code Text Amendment | X | X1 | X2 | SC5 | ||||
Planned Unit Development | X | X1 | X3 | SC | ||||
Plat Alteration | ||||||||
Minor | X | X | HE/SC | |||||
Major | X | X1 | X | SC | ||||
Post-Decision Review | ||||||||
Type I | X | X | HE/SC | |||||
Type II | X | X | HE/SC | |||||
Type III | X | X1 | X | SC | ||||
Preapplication Conference | X | X | HE | |||||
Rezone/Plan Amendment | X | X1 | X2 | SC5 | ||||
Road Modification | X | X | HE/SC | |||||
Shoreline Permit | ||||||||
Nonsignificant | X | X | HE/SC5 | |||||
Significant | X | X1 | X | Department of Ecology5 | ||||
Short Plat | X | X | HE/SC | |||||
Sign Site Plan Review | X | X | HE/SC | |||||
Site Plan Review (Type II) | X | X | HE/SC | |||||
Site Plan Review (Type I) | X | X | HE/SC | |||||
Subdivision | X | X1 | X3 | SC | ||||
Temporary Use | X | X | HE/SC | |||||
Wetland Permit | X | X | HE/SC | |||||
1 Department reviews and recommends to hearing body |
2 Planning commission recommends to council for final determination |
3 Hearing examiner makes final decision |
4 The director makes initial interpretations when making Type I and II decisions; the examiner does so when making Type III decisions |
5 Based on the facts of the case, an appeal may be made to an administrative hearings body prior to superior court |