Review of Control Plan. Within 30 days of receipt of the application, control plan, or control plan statement and fee, the Building Inspector shall review the application and control plan to determine if the requirements of this section are met. The Inspector may request comments from other departments or agencies. If the requirements of this section are met, the Inspector shall approve the plan, inform the applicant and issue a permit. If the conditions are not met, the Inspector shall inform the applicant, in writing, and may either require needed information or disapprove the plan. Within 30 days of receipt of needed information, the Inspector shall again determine if the plan meets the requirements of this section. If the plan is disapproved, the Inspector shall inform the applicant, in writing, of the reasons for the disapproval.