A.
Developments are conforming.
1.
Development that was legally established before January 1, 2014 (except as provided in subsection 2 below) that does not comply with the district-specific standards of Chapters 21.04, 21.09, 21.10, and 21.11; the use-specific standards of Chapters 21.05, 21.09, 21.10, and 21.11; or the design and development standards of Chapter 21.07 (except for section 21.07.020B, stream, water body, and wetland protection) shall be considered conforming on January 1, 2014, and subject to this section. The standards for development that do not conform to section 21.07.020B, stream, water body, and wetland protection, are contained in Section 21.13.045, Nonconforming Encroachments into Watercourse, Water Body, and Wetland Setbacks.
2.
For development in the DT districts, the threshold date that is applicable to the provisions in subsection 1 above is instead of January 1, 2014.
3.
No change shall be made to any development outside any existing structures unless the change is in the direction of conformity to the requirements of this title.
B.
Parking out of compliance.
1.
Accessible parking spaces. Nonconforming rights shall not be established for required accessible (ADA) parking in section 21.07.090J. Developments shall provide the total number of accessible parking spaces required.
2.
Bicycle parking spaces. Notwithstanding subsection C below, if changes to a use or development increase the number of required bicycle parking spaces, the number of bicycle spaces related to the increase shall be provided. For example, if a use or development that is required to have ten bicycle spaces has only five spaces, and changes to the use or development allowed through this title create a total minimum requirement of 15 spaces, the use or development shall, at a minimum, provide the additional five spaces. The addition of more spaces may be negotiated through the process outlined in subsection C below.
C.
Bringing characteristics into compliance.
1.
Applicability. This Section 21.13.060 applies to all multifamily, commercial, mixed-use, community use, commercial marijuana, and industrial development projects that:
a.
Do not comply with the district-specific standards of Chapter 21.04, the use-specific standards of Chapter 21.05, the design and development standards of Chapter 21.07 (except for Section 21.07.020B, stream, water body, and wetland protection), or any standards of Chapter 21.11;
b.
Involve a development project costing more than 50% of the assessed value of the structure (or, if no structure over 150 square feet exists, the assessed value of the land); and
c.
Require a permit through Title 21 and/or Title 23.
2.
Standard.
a.
An applicant for a building or land use permit for a multifamily, commercial, mixed-use, community use, or industrial development that meets the applicability thresholds of subsection C.1 above, shall be required to spend 10% of the total project costs on bringing the development towards compliance with the district-specific standards of Chapter 21.04, the use-specific standards of Chapter 21.05, and/or the design and development standards of Chapter 21.07 (hereafter called "characteristics").
b.
If the applicant can bring the development into full compliance with Title 21 for less than 10% of the total project costs, then no additional monies need be spent. The municipality shall not require more than ten percent, but the applicant may choose to spend more.
c.
If the applicant chooses to spend more than 15%, the amount in excess of 15% may be credited, as outlined in the user's guide, towards future improvements under this section.
d.
The director, in consultation with the applicant, shall determine which characteristics shall be addressed, within the expenditure requirements noted herein. The director and the applicant shall consider how to maximize the public benefit and minimize the economic impact to the property owner. The director shall not require compliance with a standard that would create non-compliance with a different standard (i.e., the director shall not require the addition of landscaping that would cause the development to fall under the minimum required number of accessible parking spaces).
e.
The applicant may appeal the director's decision to the planning and zoning commission, which shall hold a non-public hearing on the appeal.
f.
For the purposes of this section, "total project costs" shall be determined by the building official pursuant to municipal code and shall be exclusive of all costs of improvements that move the development in the direction of conformity to the requirements of this title. The costs of remodeling, renovation, or repair that are interior to an existing structure not subject to site plan review shall also be excluded where no change is made to the footprint of the building. The portion of the total project costs that are related to increases in conformity shall be credited toward the percentages required in subsections C.2.a and C.5.
3.
No applicable characteristics. If the director, in consultation with the applicant determines no characteristics can be brought towards conformity without causing other characteristics to come out of compliance, or if the only characteristics left to be addressed are so major as to require relocating the structure, or something of similar magnitude, then the applicant shall not be required to perform such work.
4.
Large commercial establishment. If the development project is a large commercial establishment, as defined in Section 21.07.120, then the applicant shall spend an additional 10% of the total project costs on bringing the structure into compliance with the design standards of Section 21.07.120. If the structure already complies with Section 21.07.120, then this subsection C.5 shall not apply.
5.
Timing of work. The characteristics of use shall be brought towards compliance with all applicable provisions of this title prior to the issuance of the building or land use permit or shall be included in the work to be accomplished under the permit.
(AO 2012-124(S), 2-26-2013; AO 2013-117, 12-3-2013; AO No. 2015-82, § 6, 7-28-2015; AO No. 2017-55, § 13, 4-11-2017; AO No. 2018-67(S-1), § 8, 10-9-2018; AO No. 2019-11, § 6, 2-12-2019; AO No. 2020-38, §§ 11, 13, 5-28-2020; AO No. 2024-15, § 1, 2-27-2024; AO No. 2024-24, § 9, 4-23-2024; AO No. 2025-94, § 4, 10-21-2025; AO No. 2026-46 Amended, 4-28-2026)