A refund equal to two percent of the storm drain component of the system development charge will be given when the property owner implements any of the following. A two percent refund will be given for each incentive implemented.
1.
Use of nonvegetation pervious materials in an area equal to an additional 25 percent of the subject property beyond any of the percentage requirements in BMC § 17.94.030.
2.
Uses low impact storm drainage techniques such as rain gardens, swales, permeable paving, rain barrel, cistern, or other approved method of reducing use of the city’s storm drain system.
3.
Maintain or plant a minimum of two trees on parcels less than one-half acre or four trees on a parcel one acre or larger.
The refund will be given as a rebate after a certificate of occupancy is issued for the structure and installation of the proposed improvements, as listed above, are in place.
When a new building is a replacement structure and existing landscaping is in place, the applicant will not be required to comply with this chapter.