Planning Board action. Within 62 calendar days of the closing of the public hearing, the Planning Board shall approve, approve with conditions, or disapprove the special use permit application submitted for review. The Planning Board may impose such conditions on the approval of any special use permit application as in its opinion are necessary and reasonable. If the Planning Board has approved the special use permit with conditions, such conditions must be satisfied prior to issuance of a certificate of occupancy. An approved special use permit will be signed by the Planning Board Chairperson or, in the Chairperson's absence, such other person who has been authorized by the Planning Board to sign the permit. After the Planning Board has approved the special use permit and it has been signed by the Chairperson (or such other authorized person), one copy of the permit shall be filed, within five business days of the date of the decision, with the Village Clerk, and a copy of the filed decision shall be mailed to the applicant.