search icon

Dupont City Zoning Code

Division VI

Permits and Code Changes

§ 25.130.010 Purpose.

An accessory use permit is a mechanism by which the city may permit a use that is incidental and/or secondary to a use that is permitted on a subject property.
(Ord. 02-707 § 1)

§ 25.130.020 Procedure.

Accessory uses shall be processed with a Type I procedure as set forth in DMC § 25.175.010.
(Ord. 02-707 § 1)

§ 25.130.030 Decisional criteria.

(1) 
All of the following decisional criteria must be met in order for the application to be approved:
(a) 
The use is not the sole use on the subject property;
(b) 
The use does not constitute more than 25 percent of the floor area of the principal building to which it is accessory;
(c) 
The use does not increase traffic generation to or from the subject property beyond that projected by the ITE Trip Generation Manual, current edition, of any other similarly sized use permitted in the district; and
(d) 
The use complies with the land use code requirements of the district in which the property is located.
(2) 
Conditions of Approval. The city may condition the application in order to insure conformance with provisions of the above decisional criteria.
(Ord. 02-707 § 1)

§ 25.135.010 Purpose.

A conditional use permit is a mechanism by which the city may require special conditions on development or on the use of land in order to insure that designated uses or activities are compatible with other uses in the same land use district and in the vicinity of the subject property.
(Ord. 02-707 § 1)

§ 25.135.020 Procedure.

Conditional use proposals shall be processed with a Type III procedure as set forth in DMC § 25.175.010.
(Ord. 02-707 § 1)

§ 25.135.030 Review criteria.

In order to approve a conditional use permit, the decision maker shall make written findings of fact demonstrating that all of the following criteria are satisfied:
(1) 
That the use is listed as a conditional use, or that that listing for conditional uses contains the language permitting similar land uses in the district where the conditional use is proposed. For the use to be determined “similar” the majority of the aspects of use shall be the same or lesser than those of listed conditional uses;
(2) 
That the granting of such conditional use permit will not be detrimental to the public health, safety, comfort, convenience and general welfare, will not adversely affect the established character of the surrounding neighborhood, and will not be injurious to the property or improvements in such vicinity and/or district in which the property is located;
(3) 
That the proposed use is properly located in relation to the other land uses and to transportation and service facilities in the vicinity; and further, that the use can be adequately served by such public facilities and street capacities without placing an undue burden on such facilities and streets;
(4) 
That the site is of sufficient size to accommodate the proposed use and all yards, open spaces, walls and fences, parking, loading, landscaping and other such features required by the DMC;
(5) 
That the proposed use is consistent with the goals and policies of the DuPont comprehensive plan.
(Ord. 02-707 § 1)

§ 25.140.010 Purpose.

(1) 
To protect residential areas from potential adverse impacts of activities conducted for financial gain or profit in a dwelling unit; and
(2) 
To permit residents of the community a broad choice in the use their homes as a place of livelihood and the production or supplementing of personal/family income.
(Ord. 02-707 § 1)

§ 25.140.020 Procedure.

Home occupations shall be processed with a Type I procedure as set forth in DMC § 25.175.010 with a filing fee per DMC § 2.03.010.
(Ord. 02-707 § 1; Ord. 05-790 § 10)

§ 25.140.030 Review criteria.

In order to approve a home occupation permit, the decision maker shall make written findings of fact demonstrating that all of the following criteria are satisfied:
(1) 
The occupation is limited to such uses as personal, business, or professional services, offices and repair shops for household items, and does not involve automotive, truck or motorcycle repair.
(2) 
The occupation shall be conducted only by the persons residing in the dwelling unit plus no more than one nonresident assistant or employee. Persons engaged in building trades or similar fields, using their dwelling unit or residential premises as an office for business activities carried on off the premises may have more employees than the limitation set forth in this chapter if they are not employed on the premises.
(3) 
The occupation shall be conducted wholly within a structure and shall be conducted in such a manner as to give no outward appearance nor manifest any characteristics of a business, in the ordinary meaning of the term, that would infringe upon the right of the neighboring residents to enjoy a peaceful occupancy of their homes.
(4) 
Point of purchase retail sales is not permitted.
(5) 
The home occupation shall not generate traffic volumes greater than what would normally be expected in a residential neighborhood. Parking shall be provided in conformance with Chapter 25.95 DMC.
(6) 
Signs shall not be permitted.
(7) 
Home occupations shall comply with all other local, state or federal regulations pertinent to the activity pursued, and the requirements or permission granted or implied by this chapter shall not be construed as an exemption from such regulations.
(8) 
A home occupation permit issued to one person shall not be transferable to any other person; nor shall a home occupation permit be valid at any address other than the one appearing on the permit.
(9) 
Any person engaging in a home occupation shall register as a business under DMC § 5.04.010.
(Ord. 02-707 § 1)

§ 25.145.010 Nonconforming buildings and uses.

Except as otherwise provided, this chapter shall apply to buildings, structures, land, and uses which become nonconforming as a result of this code.
(Ord. 02-707 § 1)

§ 25.145.015 Procedure.

An application to modify, alter, reduce, enlarge, maintain, restore, reconstruct or repair an existing nonconforming use or nonconforming structure will be processed under the Type III procedure. Processes for all procedures are set forth in DMC § 25.175.010.
(Ord. 02-707 § 1)

§ 25.145.020 Effect of removal or destruction of nonconforming buildings or discontinuance of nonconforming use.

If a nonconforming building is destroyed, removed, or suffers damage of 50 percent or more of its market value, future uses of the land must conform to this code. If a nonconforming use is discontinued for more than one year, the land or building may not again be occupied or used except by a conforming use.
(Ord. 02-707 § 1)

§ 25.145.030 Maintenance and reconstruction.

Upkeep, repair, and maintenance of nonconforming buildings is permitted. A nonconforming building damaged by less than 50 percent of its market value by fire, explosion, other casualty, act of God or other cause beyond the owner's control may be restored and the prior use may be continued, subject to all provisions of this code, if restoration is commenced within one year from the damage and completed with reasonable diligence.
(Ord. 02-707 § 1)

§ 25.145.040 Structural alteration or enlargement.

Nonconforming buildings may not be enlarged or structurally altered except:
(1) 
To make the building more conforming;
(2) 
Where required by law;
(3) 
Where a building is nonconforming only because of substandard yards, open spaces, area, or height and the structural alterations and enlargements do not increase the degree of nonconformity;
(4) 
Structural alterations which do not increase the floor space are permitted where necessary to adapt a nonconforming building to new technologies or equipment for the existing uses;
(5) 
Other structural alterations may be authorized as conditional uses under Chapter 25.135 DMC, Conditional Uses, if the alteration will improve the safety, appearance, or functionality of the property or make it less detrimental to other uses in the vicinity.
(Ord. 02-707 § 1)

§ 25.150.010 Purpose.

Site plan review is intended to insure that development projects carried out in given land use districts are executed in a manner consistent with existing ordinances concerning public utilities, traffic, facilities and services and provide unified site design, access, landscaping, screening, building placement and parking lot layout.
(Ord. 02-707 § 1)

§ 25.150.020 Procedure.

Site plan review and approval shall be required either before or concurrent with issuance of the building permit. A building permit application may be submitted before or in conjunction with an application for site plan application approval. Site plan review shall be processed as a Type II procedure except for multifamily projects larger than 80 units, development projects greater than 15 acres in the business technology park and manufacturing research park, and building area larger than 50,000 square feet in the commercial district, all of which shall be processed as a Type III procedure as set forth in DMC § 25.175.010.
(Ord. 02-707 § 1; Ord. 03-736 § 8)

§ 25.150.030 Review criteria.

In order to obtain site plan approval, all of the development regulations and criteria specified in the district applicable to the property must be satisfied in addition to any general development requirements in Chapters 25.75 through 25.95 and 25.105 through 25.125 DMC.
(Ord. 02-707 § 1)

§ 25.150.040 Duration of approval.

Construction of the development proposal shown on the site plan must commence within 24 months from the date of the city's final decision on the site plan, otherwise the site plan approval expires.
(Ord. 02-707 § 1)

§ 25.150.050 Amendments to site plan.

(1) 
Minor site plan amendments shall be processed as a Type I procedure as set forth in DMC § 25.175.010. Minor site plan amendments may be made and approved when a building permit is issued.
(2) 
Major site plan amendments shall be processed as a Type II procedure except for multifamily projects larger than 80 units and development projects greater than 15 acres in the business technology park and manufacturing research park which shall be processed as a Type III procedure as set forth in DMC § 25.175.010. When an applicant proposes a change to a site plan which constitutes a major amendment, no building or engineering permit related to the development proposal shall be issued by the city until the major amendment final decision has been issued.
(Ord. 02-707 § 1; Ord. 03-736 § 9)

§ 25.152.010 Purpose.

Master plan review is intended to ensure that a specific land area is planned out in advance in terms of transportation networks, parks and open space, land uses, utilities, and community character. The master plan review is more detailed in nature than site plan review but establishes the urban framework for a specific subarea within the larger neighborhood context. The master plan is also intended to establish initial approval for the future land usage on a district scale as opposed to site-by-site applications.
(Ord. 18-1032 § 2 (Exh. 5))

§ 25.152.020 Procedure.

(1) 
A master plan shall be reviewed and processed as a Type III procedure as set forth in DMC § 25.175.010.
(2) 
The hearing examiner may impose conditions to ensure neighborhood compatibility, to mitigate impacts relating to traffic and the environment, and to ensure sound urban design practices based on the city of DuPont comprehensive plan.
(3) 
A master plan may be required for a specific overlay district and/or as part of a conditional approval.
(Ord. 18-1032 § 2 (Exh. 5))

§ 25.152.025 Master plan components.

The master plan shall include the following components in addition to other supplemental information required by this code:
(1) 
Project Narrative. The master plan shall include a project narrative that describes (a) the project intent, (b) general character, (c) future land uses, (d) urban design, and (e) compatibility standards.
(2) 
Concept Plan. The master plan shall include a concept map depicting (a) the transportation network including streets and trails, (b) land uses, (c) parks and open-space networks, (d) natural resources and environmental protection areas, and (e) landmarks. The master plan concept plan shall also include a site statistic table that includes (a) land areas, (b) density/intensity calculations, (c) proposed land uses, and (d) parking calculations.
(3) 
Street Design. The master plan shall include typical street cross sections for all internal roadways. Street trees and paving material shall be identified.
(4) 
Utility Plan. The master plan shall include a general utility plan for potable water, sanitary sewer, and stormwater plan for the entire project boundary.
(5) 
Architecture and Materials Board. The master plan shall include information relating to the intended architecture and building materials that will be used for future development within the plan boundaries. The materials list should include (a) roofing material (b) exterior treatment, (c) window/fenestration design, and (d) colors.
(Ord. 181032 § 2 (Exh. 5))

§ 25.152.030 Review criteria.

In order to obtain master plan approval, all of the development regulations and criteria specified in the district applicable to the property must be satisfied. Additionally, the request must fully comply with the general goals, vision and policies established in the comprehensive plan with specific focus on the applicable village in which it is located.
(Ord. 18-1032 § 2 (Exh. 5))

§ 25.152.040 Duration of approval.

Site plan approval of the development proposal shown on the master plan must commence within 24 months from the date of the city's final decision on the master plan, otherwise the master plan approval expires.
(Ord. 18-1032 § 2 (Exh. 5))

§ 25.152.050 Amendments to master plans.

(1) 
Minor master plan amendments shall be processed as a Type I procedure as set forth in DMC § 25.175.010.
(a) 
Minor Amendments Defined. A minor amendment may be considered a change that:
(i) 
Does not result in conflicts in on-site circulation and/or negative impacts with ingress/ egress.
(ii) 
Does not change the use unless such change is of a similar or less intensity, as determined by the community development director.
(iii) 
Does not increase the density or intensity of the development by more than five percent or two dwelling units, whichever is less.
(iv) 
Does not result in a reduction of the required common open space area.
(v) 
Does not result in a substantial change to the location of a structure previously approved in terms of relation to nearby streets and separation from adjacent uses.
(vi) 
Does not result in a change to or the cancellation of any condition or limits placed upon the application as originally approved.
(vii) 
Does not add property to the parcel proposed for development.
(viii) 
Does not increase the height of the buildings in a manner that will change the overall height of the project, will not alter the scale of the project, does not exceed the maximum height permitted in the district.
(ix) 
Does not substantially alter the character and design of the project in terms of scale and building style.
(2) 
Major amendments shall be processed as a Type III procedure as set forth in DMC § 25.175.010. When an applicant proposes a change to a master plan which constitutes a major amendment, no building or engineering permit related to the development proposal shall be issued by the city until the major amendment final decision has been issued.
(Ord. 18-1032 § 2 (Exh. 5))

§ 25.155.010 Purpose.

The purpose of this chapter is to provide a process to consider and grant permits for temporary uses as defined in DMC § 25.10.210.
(Ord. 02-707 § 1; Ord. 07-854 § 1)

§ 25.155.020 Procedure.

A temporary use shall be processed as a Type I procedure as set forth in DMC § 25.175.010 with a filing fee per DMC § 2.03.010. A single one-year extension may be granted for only construction trailers if the primary development project that necessitates the temporary use is not completed within the one-year time period.
(Ord. 02-707 § 1; Ord. 05-790 § 11)

§ 25.155.030 Decisional criteria.

(1) 
All of the following decisional criteria must be met in order for the application to be approved:
(a) 
The use is consistent with the comprehensive plan;
(b) 
The use is consistent with the allowed uses in the district in which the property is located;
(c) 
The use complies with applicable health and safety requirements of the district in which the property is located; and
(d) 
The use complies with all other applicable criteria and standards of the DMC.
(2) 
Conditions of Approval. The city may condition the application in order to insure conformance with provisions of the above decisional criteria.
(3) 
Removal. The subject site shall be returned to its predevelopment state within 30 days of cessation of the temporary use as required by the approval. Additionally, a construction office for which a temporary use permit has been granted shall be removed from the subject site when the related construction is completed or the last unit is completed by the contractor.
(4) 
Assurance Device. The decision maker may, in his/her sole discretion, require that the applicant for the temporary use post a bond, in the form and by a surety acceptable to the city attorney, and in an amount estimated by the city, to cover the cost of removal of the temporary use and restoration of the property.
(Ord. 02-707 § 1)

§ 25.160.010 Purpose.

A variance is a mechanism by which the city may grant relief from the provisions of the land use code where practical difficulty renders compliance with the provisions of that code an unnecessary hardship, where the hardship is a result of the physical characteristics of the subject property and where the purpose of that code and of the comprehensive plan cannot be fulfilled. Variances are not intended to be used as a means of circumventing individually inconvenient regulations, as a means to change the allowable uses in a land use district, or as a means to rezone property.
(Ord. 02-707 § 1; Ord. 07-854 § 1)

§ 25.160.020 Procedure.

An administrative variance shall be processed as a Type II procedure and a general variance shall be processed as a Type III procedure. Procedures are set forth in DMC § 25.175.010. The elements of a complete application for an administrative and general variance are set forth in DMC § 25.150.050, together with the applicant’s written statement of justification, describing the manner in which the variance application meets the criteria for approval in DMC §§ 25.160.030 and 25.160.040.
(Ord. 02-707 § 1)

§ 25.160.030 Administrative variance.

Administrative variances may be granted if the applicant demonstrates that approval would result in:
(1) 
A decrease of not more than 20 percent of the required width of a side, front or rear yard or yard between buildings;
(2) 
An increase of not more than 10 percent of the permitted projection of cornices, sills, eave projections, fences or structures, maximum permitted lot coverage, unenclosed awnings and unenclosed and uncovered decks into a required front, side or rear yard;
(3) 
An increase of not more than 10 percent in the maximum permitted height of a building.
(Ord. 02-707 § 1)

§ 25.160.040 General variance.

Any application for a variance not meeting the requirements of an administrative variance, DMC § 25.160.030, shall be processed as a general variance.
(Ord. 02-707 § 1)

§ 25.160.050 Review criteria.

In order to approve an administrative variance or a general variance, the decision maker shall make written findings demonstrating that all of the following criteria have been met:
(1) 
The proposed variance will not amount to a rezone nor authorize any use not allowed in the land use district;
(2) 
Special conditions and circumstances exist which are peculiar to the land such as size, shape, topography or location, not applicable to other land in the same land use district, demonstrating that literal interpretation of this title would deprive the property owner of rights commonly enjoyed by other properties similarly situated in the same zoning district under the terms of this title;
(3) 
The special conditions and circumstances noted in subsection (2) of this section are not the result from the actions of the applicant or property owner;
(4) 
Granting of the variance requested will not confer a special privilege that is denied other properties in the same land use district;
(5) 
The granting of the variance will not be materially detrimental to the public welfare or injurious to the property or improvements in the vicinity and district in which the subject property is situated; and
(6) 
The requested variance does not go beyond the minimum necessary to afford relief.
(Ord. 02707 § 1)

§ 25.165.010 Purpose.

A reclassification of property is a mechanism by which the land use district classification or conditions applicable to property may be changed to reflect such things as changed circumstances, new land use needs or new land use policies. An amendment to the text of the land use code is a mechanism by which the city may bring its land use and development regulations into conformance with the comprehensive plan or respond to changing conditions or needs of the city.
(Ord. 02-707 § 1)

§ 25.165.020 Procedure.

A rezone of a single piece of property shall be processed as a Type III procedure as set forth in DMC § 25.175.010. A rezone of two or more parcels of property or text amendment of the land use code shall be processed as a Type V procedure as set forth in DMC § 25.175.010.
(Ord. 02-707 § 1)

§ 25.165.030 Review criteria.

(1) 
The city may approve, approve with conditions or deny an application for reclassification of a single piece of property based on the following decisional criteria. All decisional criteria must be met in order for the reclassification to be granted.
(a) 
The reclassification is in accord with the comprehensive plan;
(b) 
The reclassification is warranted due to changed circumstances or a need for additional property in the proposed land use district or due to the proposed land use classification is appropriate for reasonable development of the subject property;
(c) 
The subject property is suitable for development in general conformance with land use standards under the proposed land use district classification;
(d) 
The reclassification will not be materially detrimental to uses or property in the immediate vicinity of the subject property; and
(e) 
The reclassification bears substantial relation to the public health, safety, and welfare.
(2) 
The city may approve, approve with conditions or deny an application for a rezone of two or more parcels of property or amend the text of the land use code based on the following decisional criteria. All decisional criteria must be met in order for the amendment to be granted.
(a) 
The amendment is in accord with the comprehensive plan;
(b) 
The amendment bears substantial relation to the public health, safety, and welfare; and
(c) 
The amendment is not contrary to the best interest of the citizens and property owners of the city of DuPont.
(Ord. 02-707 § 1)

§ 25.170.010 General.

The comprehensive plan is a document which guides the nature and intensity of development in the city. An amendment to the plan is a mechanism by which the city may modify its land use, development or growth policies in order to respond to changing circumstances or needs of the city.
(Ord. 02-707 § 1)

§ 25.170.020 Applicability.

This section shall apply to initial adoption of the comprehensive plan and subsequent adoption of amendments or additional elements to the comprehensive plan in accordance with Chapter 36.70A RCW and all future amendments or applicable federal, state or local laws.
(Ord. 02-707 § 1)

§ 25.170.030 Notice of proposal, community workshop, public hearing.

(1) 
Purpose.
(a) 
Following submittal and active city consideration of a complete comprehensive plan amendment proposal the city shall implement a deliberate public involvement process consisting of the steps listed in this section. In summary, they include: publish a notice of proposal, publish a notice of community workshop, conduct a community workshop, issue a notice of public hearing and conduct a public hearing.
(b) 
The community workshop and public hearing shall be the forum for broad dissemination of proposals and alternatives, opportunity for written comments after effective notice provisions for meaningful open discussion, consideration of, and response to public comments. Errors in exact compliance with the established procedures shall not render the comprehensive plan or development regulations invalid if the spirit of the procedure is observed.
(2) 
Notice of Proposal.
(a) 
Notice. The city shall issue a notice of proposal. Said notice shall contain the following information:
(i) 
Name of applicant.
(ii) 
Summary of amendment.
(iii) 
Area affected by the amendment.
(iv) 
Statement that a copy of the proposal is available for examination at DuPont City Hall.
(v) 
City contact person.
(vi) 
Date of notice.
(b) 
Issuance of Notice. City staff shall issue the notice of proposal following submittal of a complete comprehensive plan amendment application and at least 14 days prior to a community workshop as specified below:
(i) 
Publish notice in the newspaper of record.
(ii) 
Issue a city flyer to all residents within the city.
(iii) 
Send notice to applicant, city businesses and mailing lists, including general lists or lists for specific proposals or subject areas.
(iv) 
In addition, the city may, at its discretion, post the property for site-specific proposals; notify public or private groups with known interest in a certain proposal or in the type of proposal being considered.
(3) 
Community Workshop.
(a) 
Notice. City staff shall hold at least one community workshop. Notice of the community workshop shall contain the following information:
(i) 
Name of applicant.
(ii) 
Summary of amendment.
(iii) 
Area affected by the amendment.
(iv) 
Date, time and location of the community workshop.
(v) 
Statement that a copy of the proposal is available for examination at DuPont City Hall.
(vi) 
City contact person.
(vii) 
Date of notice.
(b) 
Issuance of Notice. City staff shall issue the notice of community workshop at least seven days prior to the date of the workshop as specified below:
(i) 
Publish notice in the newspaper of record.
(ii) 
Issue a city flyer to all residents within the city.
(iii) 
Send notice to applicant, city businesses and mailing lists, including general lists or lists for specific proposals or subject areas.
(iv) 
In addition, the city may, at its discretion, post the property for site-specific proposals; notify public or private groups with known interest in a certain proposal or in the type of proposal being considered.
(4) 
Public Hearing.
(a) 
Notice. The planning agency shall hold at least one public hearing. Notice of the hearing shall contain the following information:
(i) 
Name of applicant.
(ii) 
Summary of amendment.
(iii) 
Area affected by the amendment.
(iv) 
Date, time and location of the community workshop.
(v) 
Statement that a copy of the proposal is available for examination at DuPont City Hall.
(vi) 
City contact person.
(vii) 
Date of notice.
(b) 
Issuance of Notice. City staff shall issue the notice of hearing at least 10 days prior to the date of the hearing as specified below:
(i) 
Publish notice in the newspaper of record.
(ii) 
Post notice on the official city public notice boards.
(iii) 
Send notice to city businesses and mailing lists, including general lists or lists for specific proposals or subject areas.
(iv) 
Send notice to any party of record and applicant.
(v) 
In addition, the city may, at its discretion, post the property for site-specific proposals, notify public or private groups with known interest in a certain proposal or in the type of proposal being considered.
(Ord. 02-707 § 1)

§ 25.170.040 Adoption required by the city council.

The comprehensive plan or an amendment to the comprehensive plan requires adoption by the city council by ordinance. The city council shall not adopt a comprehensive plan or amendment without first considering a recommendation on the proposed amendment by the planning agency. In addition, amendments to the zoning map will generally require a change in zoning of specific properties; said changes shall be considered concurrently with a plan amendment required by the planning agency and city council and shall not require the payment of additional fees.
(Ord. 02-707 § 1)

§ 25.170.050 Adoption of comprehensive plan.

There is adopted by reference a comprehensive plan, on file with the planning department, as subsequently amplified, augmented and amended pursuant to the provisions of this title, consisting of:
(1) 
City of DuPont Comprehensive Plan (July, 1995);
(2) 
City of DuPont Water System Comprehensive Plan (April, 1997);
(3) 
City of DuPont Interim Capital Facilities Plan (August, 1997);
(4) 
City of DuPont Interim Zoning Map (August, 1997);
(5) 
City of DuPont Shoreline Management Master Program (amended January, 1980).
(Ord. 02-707 § 1)

§ 25.170.060 Adoption and amendment of zoning map.

(1) 
This title includes a map known, cited, and referenced as the city of DuPont Zoning Map (zoning map) which depicts the location and boundaries of various land use classifications, references and other information shown thereon, which map is incorporated by reference as part of this title.
(2) 
A true and correct copy of the zoning map shall be kept in the planning department, and shall be revised to reflect all comprehensive plan land use map amendments within 30 days of enactment of said amendments. Said zoning map shall contain the date of initial adoption and the date of each subsequent revision.
(Ord. 02-707 § 1)

§ 25.170.070 When amendments may be adopted.

All amendments to the comprehensive plan shall be considered concurrently and no more frequently than once each calendar year except: (1) in the event of an emergency, as defined in this chapter; (2) adoption of a subarea plan (neighborhood plan); or (3) adoption or amendment of a shoreline master program. The city council shall consider proposed amendments concurrently with the city's budget. A privately initiated amendment to the plan may be filed only every other year beginning with the year 1999.
(Ord. 02-707 § 1; Ord. 18-1038 § 1 (Exh. A))

§ 25.170.080 Proposals for amendment.

(1) 
A proposed amendment to the comprehensive plan may be submitted by any individual, organization, corporation or partnership, general or special purpose government, or entity of any kind; provided, that if the proposal involves specific real property, the property owner has provided written consent to the proposal. An applicant shall complete the necessary application form as provided by the planning department and pay the required filing fees. An environmental checklist and related fee shall also be required unless the proposal is categorically exempt from environmental review. City staff or the city council may initiate a planning program or specific amendment which may result in an additional element or other amendment to the plan.
(2) 
Except for city-initiated planning programs or individual city-sponsored amendments, all proposed amendments to the comprehensive plan shall be submitted to the planning department no later than April 31st to be docketed for consideration during that year. Proposals filed after April 31st shall be considered during the following year's amendment process unless an emergency exists as defined in this section. All proposed amendments to the comprehensive plan shall be submitted to the planning department in writing on a form provided by the city, together with required filing fees. An environmental checklist and related filing fee shall also be submitted unless the proposal is categorically exempt from environmental review. A proposed amendment request shall include the following information:
(a) 
Name, address and phone number of the applicant and contact person;
(b) 
If the amendment concerns specific real property, both a general and legal description of the property;
(c) 
A description of the plan amendment being requested;
(d) 
Statements addressing the purpose of the amendment and why the amendment is being requested, including addressing any relevant decisional criteria of this section and the DMC; and
(e) 
A list of the names of owners of all property of record within 300 feet of the subject property together with two sets of stamped envelopes addressed to the same.
(3) 
The city shall broadly disseminate information regarding the annual amendment process.
(Ord. 02-707 § 1)

§ 25.170.090 Decisional criteria for plan amendment proposals.

In consideration that the comprehensive plan was developed and adopted after significant study and public participation, the principles, goals, objectives and policies contained therein shall be granted substantial weight when considering any proposed amendment. Therefore, the burden of proof for justifying a proposed amendment rests with the applicant, who must demonstrate that the request complies with all of the following decisional criteria:
(1) 
The proposed plan amendment will further and be consistent with the goals, objectives and policies of the comprehensive plan, except for the policy being amended; County-Wide Planning Policies for Pierce County; and Vision 2020; and
(2) 
The proposed plan amendment is consistent with the city's plans, policies and regulations for providing community facilities, including but not limited to utilities, transportation, parks, or schools, concurrent with development; and
(3) 
If the request is to change the land use designation of a specific property on the interim zoning map, the applicant must also demonstrate either of the following:
(a) 
The existing land use designation was clearly made in error due to an oversight; or
(b) 
There has been a change in circumstances and the proposal would better achieve the comprehensive plan goals and policies than the existing comprehensive plan section.
(Ord. 02-707 § 1)

§ 25.170.100 Periodic assessment of comprehensive plan amendment needs.

(1) 
The city shall monitor the comprehensive plan and regulatory procedures that implement the plan, and may initiate amendments as needed for adoption. This assessment shall be based on, but not limited to:
(a) 
Whether growth and development are occurring at a faster or slower rate than envisioned in the plan; or
(b) 
Whether the capacity to provide adequate services is diminished or increased; or
(c) 
The availability of land to meet demand; or
(d) 
Assumptions upon which the plan is based are found to be invalid; or
(e) 
The effect of the plan on land values and housing is contrary to the plan goals; or
(f) 
A determination that sufficient change or lack of change in circumstances dictate the need for a recommended amendment; or
(g) 
A determination that a question of consistency exists between the comprehensive plan and Chapter 36.70A RCW, the County-Wide Planning Policies for Pierce County, and Vision 2020: Growth Management and Transportation Strategy for the Central Puget Sound Region.
(2) 
An assessment of the comprehensive plan shall occur at least every five years from the date of initial adoption of the plan.
(Ord. 02-707 § 1)

§ 25.170.110 Amendments considered under emergency situation.

The city council may consider amendments to the comprehensive plan at any time during a calendar year as a result of an emergency situation, as defined by “emergency amendment” in DMC § 25.10.050, or to resolve an appeal of the comprehensive plan filed with the Central Puget Sound Growth Management Hearings Board or superior court.
(Ord. 02-707 § 1; Ord. 17-1017 § 2 (Exh. B))

§ 25.170.120 Provisions for amendment transmittal and reporting to state.

The planning department shall notify and transmit copies of all proposed plan amendments and development regulations to the Washington State Department of Trade and Economic Development and designated state agencies at least 60 days prior to adoption as consistent with Chapter 36.70A RCW except for emergency amendments. Notice of emergency plan amendments will be transmitted to the Washington State Department of Trade and Economic Development and designated state agencies as early as possible prior to adoption.
(Ord. 02707 § 1)

§ 25.170.130 Appeals to the adoption or amendment of a comprehensive plan.

All appeals to the adoption of the comprehensive plan or an amendment thereto shall be filed with and processed by the Central Puget Sound Growth Management Hearings Board in accordance with the provisions of Chapter 36.70A RCW.
(Ord. 02-707 § 1)