[Amended 10-21-1996 by Ord. No. 305; 10-6-1998 by Ord. No. 319]
It shall be unlawful for any person to make any use or change in use of any building or other structure or land, or to commence work for the erection, construction, reconstruction, alteration, razing or enlargement of any building, structure or portion thereof, or to alter, regrade, fill or clear of vegetation any of the following areas: floodplain soils abutting the Delaware River, ponds, wetlands, waters of the commonwealth, steep slopes or woodlands, until all necessary permits required by this chapter have been obtained.
A. Application for a zoning, building and occupancy permit. All applications for permits shall be made to the Zoning Officer, in writing, on forms furnished by the Township and shall include all information necessary to enable the Zoning Officer to ascertain compliance with this chapter.
B. Zoning permit review and approval shall be required prior to the following:
(1) The erection, construction, reconstruction, alteration, addition or enlargement of any building or structure including patios, decks and porches.
(2) Any use or change in use or occupancy of a nonresidential property.
(3) Altering, regrading, filling or clearing of vegetation in any of the following areas: floodplain soils abutting the Delaware River, ponds, wetlands, waters of the commonwealth, steep slopes or woodlands.
C. Issuance of permits. No zoning permits shall be issued until the Zoning Officer has certified that the proposed use of land or existing or proposed building or structure complies with the provisions of the applicable district and other provisions of this chapter.
D. The Zoning Officer may require any of the following information to be provided:
(1) Statement as to the proposed use of the building or land.
(2) A site layout showing the location, dimensions and height of proposed buildings or uses and any existing buildings in relation to property and street lines.
(3) The location, size, arrangement and capacity of all areas to be used for motor vehicles access, off-street parking, off-street loading and unloading and provisions to be made for lighting such areas.
(4) The location, dimensions and arrangements of all open spaces, yards and buffer yards, including methods to be employed for any required screening.
(5) Provisions to be made for treatment and disposal of sewage and industrial wastes, water supply and storm drainage.
(6) Wherever the topography and vegetation are to be disturbed, a plan for the control of erosion and sediment and grading is required. It shall be unlawful to pave, fill, strip or change the existing grade of any land without first obtaining a grading permit and complying with Chapter
116, Grading and Excavation; and it shall be unlawful to disturb, modify, divert, block or affect the natural overland or subsurface flow of stormwater within the Township without first securing a zoning and building permit.
E. Building permit review. Requirements for building permits.
(1) A building permit shall be required prior to the erection, construction, reconstruction, alteration, razing or enlargement of any building, other structure or portion thereof. It shall be unlawful for any person to commence work for the erection, construction, reconstruction, alteration, razing or enlargement of any building structure or portion thereof until a building permit has been duly issued.
(2) All building shall be in compliance with applicable Township building codes, as duly adopted by the Board of Supervisors.
(3) Permits within historic districts. For any erection, alteration or enlargement of any building or other structure, or portion thereof within the historic district, the permit application shall be reviewed by the Historic Architectural Review Board prior to the issuance of a permit in accordance with historic district provisions attached as an appendix to this chapter. Permits shall be issued only after the Board of Supervisors has approved a certificate of appropriateness.
F. Certificate of occupancy.
(1) No structure erected, reconstructed, extended or moved, and no land or building changed in use for which a building permit has been issued shall be occupied or used in whole or in part for any use whatsoever until the owner or authorized agent has been issued a certificate of occupancy by the Zoning Officer, indicating that the building or use complies with terms of the this chapter and Chapter 87, Building Construction.
(2) No certificate of occupancy shall be issued until the premises in question have been inspected and found by the Zoning Officer to be in compliance with this chapter and the Township Building Codes.
(3) The issuance of a certificate of occupancy in no way absolves the owner or authorized agent from compliance with the intent of this chapter.
(4) All applications for certificates of occupancy shall be made, in writing, by the owner or authorized agent on a form supplied by the Zoning Officer at the time of application for a zoning and building permit.
(5) A certificate of occupancy shall become void 90 days from the date of issuance unless occupancy, use or change of use is commenced.