Permit Requirements. Before any owner shall be permitted to place a storage container on a lot, an application to the Building Department for a permit to do so shall be filed and approved. The application shall identify the owner and/or the tenant, location, size and the length of time that the storage container is requested.
1.
After approval of a zoning permit, a storage container after approval of a zoning permit shall be permitted to remain for the following length of time:
(b)
Ninety days if a valid building permit was issued pertaining to the need for a storage container.
2.
The owner may seek to keep the storage container for an additional period of time by making a separate application for extension to the Building Department with the understanding and acknowledgment that any extension granted will not be further extended and additional fees will be required unless extenuating circumstances apply such as a fire or natural disaster.