(1) When any building is erected, constructed, reconstructed, altered, repaired, or converted, or any building or land is used in violation of this chapter, the Zoning Administrator is authorized and directed to institute any appropriate action to put an end to such violation.
(2) Pursuant to the provisions of this chapter, more specific penalties are prescribed for violations of the tree protection regulations (see Subchapter E) and the critical area buffer (see Subchapter D, Part 3).
(B) Types of violations. The following activities, acts, failures to act, and conditions are violations of this chapter and will be enforced using the penalties and remedies provided by this Subchapter, the Mount Pleasant Code, and any requirements or limitations of South Carolina law:
(1) Development or use without permit or approval. Any activity that is not authorized by the acquisition of all required permits, approvals, certificates, and authorizations required by this chapter;
(2) Development or use of land inconsistent with this chapter. Any activity that is inconsistent with any zoning, development, landscaping, sign, or general regulation of this chapter or any amendment to it;
(3) Development or use inconsistent with conditions of approval. Any activity that is inconsistent with any term, condition, or qualification placed by the town upon a required permit, certificate, rezoning, plan approval, or other form of authorization granted by the town to allow the use, development, placement of signs, or other activity upon land or improvements of land;
(4) Making a lot or yard nonconforming. Reducing or diminishing any lot area, lot width, lot depth, or setback so that the lot or yard is smaller than prescribed by the requirements of this chapter;
(5) Increasing impervious surface coverage. Increasing the impervious surface coverage on a lot so that it exceeds the maximum allowed by this chapter;
(6) Increasing the intensity of use. Increasing the intensity or density of use of any land or structure, except in accordance with the procedural and substantive requirements of this chapter;
(7) Deficient landscaping and site improvements. Failing to install or maintain any landscaping, screening, or site improvements required by this chapter;
(8) Removal of vegetation in buffers and bufferyards. The unauthorized removal or disturbance of vegetation from required buffers or bufferyards, except in accordance with the provisions of Subchapter D;
(9) Removal of protected trees. The unauthorized removal or disturbance of protected trees, except in accordance with the provisions of Subchapter E;
(10) Disrupting notice. Removing, defacing, obscuring, or interfering with any notice posted or made pursuant to this chapter;
(11) Failure to comply with a stop work order. Continuing construction or other site work on any development, building, or structure on any land or site after service of a stop work order issues by the town pursuant to this subchapter;
(12) Displaying a temporary sign longer than permitted. Displaying a temporary sign for a period of time in excess of that stated in the approval;
(13) Unauthorized changes to Zoning Map. Any change in zoning district boundaries on the Zoning Map that is not made in conformance with the procedures set forth in Subchapter I; and
(14) Other acts. Any other act that is prohibited by this chapter or the failure to do any act that is required by this chapter is a violation under this section and is punishable under this chapter.
(C) Each day constitutes a separate offense. Each day that any violation of any provision of this chapter continues constitutes a separate offense.