[Amended 5-8-1986 by Ord. No. 8-86]
No building, structure or sign in any zone shall be erected, added to or structurally altered without a building permit duly issued upon application to the Construction Code Official. No building permit shall be issued unless the proposed construction or use is in full conformity with all the provisions of this chapter. Any building permit issued in violation of the provisions of this chapter shall be null and void and of no effect without the necessity for any proceedings for revocation or nullification thereof, and any work undertaken or use established pursuant to any such permit shall be unlawful.
A. Every application for a building permit shall be accompanied by a plot plan and complete construction specifications drawn to scale, showing:
(1) The actual shape, dimensions, radii, angles and area of the lot on which the building is proposed to be erected or of the lot on which it is situated if an existing building.
(2) The block and lot numbers as they appear on the Official Assessment Map.
(3) The exact size and location on the lot of the proposed building or alteration of an existing building and of other existing buildings on the same lot.
(4) The dimensions of all yards in relation to the subject building and the distance between the building and any other existing buildings on the same lot.
(5) The existing and intended use of all buildings, existing or proposed, and the use of land.
(6) Such topographic or other information with regard to the building, the lot or neighboring lots as may be necessary to determine that the proposed construction will conform to the provisions of this chapter.
B. Applications for the construction of new buildings shall be accompanied by an accurate survey prepared by an engineer or land surveyor licensed by the State of New Jersey.
C. No building permit shall be issued for the construction or alteration of any building costing $2,000 or more unless the plans and specifications therefor are prepared by an architect or a professional engineer licensed by the State of New Jersey.
D. No building permit shall be issued for any building where the site development plan of such building is subject to approval by the Planning Board except upon approval of such plan by the Board.
E. No building permit shall be issued for a building to be used for any conditional use in any zone where such use is allowed only with approval of the Planning Board unless and until approval has been duly granted by the Board.
F. The application and all supporting documentation shall be made in triplicate. Upon the issuance of a building permit, the Construction Code Official shall return one copy of all documents filed to the applicant.
G. Except where otherwise specified in this chapter, the Construction Code Official shall, within 10 days after the filing of a complete and properly prepared application, either issue or deny a building permit. If a building permit is denied, the Construction Code Official shall state in writing the reasons for such denial.
H. Every building permit shall expire if the work authorized has not commenced within six months after the date of issuance or has not been completed within 18 months from such date. If no zoning amendments or other Borough regulations affecting subject property have been enacted in the interim, the Construction Code Official may authorize in writing the extension of either above period for an additional six months, following which no further work is to be undertaken without a new building permit.