CHAPTER 17

38 CONDITIONAL USE PERMITS

17.38.010 Purposes and powers.

   In certain zones conditional uses are permitted subject to the granting of a conditional use permit. Because of their unusual characteristics, conditional uses require special consideration so that they may be located properly with respect to the objectives of the zoning ordinance and with respect to their effects on surrounding properties. In order to achieve these purposes and thus give the zone use regulations the flexibility necessary to achieve the objectives of this title, the planning commission is empowered to grant or deny applications for conditional use permits and to impose reasonable conditions upon the granting of such permits. (Ord. 2017-01 (part), 2017: prior code § 7525)

17.38.020 Application procedures.

   A.   Application for a conditional use permit shall be made to the planning commission on a form prescribed by the commission which shall include the following data:
   1.   Name and address of the applicant;
   2.   Statement that the applicant is the owner of the property or is the authorized agent of the owner;
   3.   Address and legal description of the property;
   4.   The application shall be accompanied by such sketches or drawings as may be necessary by the planning division to clearly show the applicant's proposal;
   5.   The purposes of the conditional use permit and the general description of the use proposed;
   6.   Additional information as required by the historic preservation advisory committee.
   7.   Additional technical studies or reports, as required by the Site Plan Review Staff.   
   8.   A traffic study or analysis prepared by a certified traffic engineer, as required by the Site Plan Review Staff or Traffic Engineer, that identifies traffic service levels of surrounding arterials, collectors, access roads, and regionally significant roadways impacted by the project and any required improvements to be included as a condition or mitigation measure of the project in order to maintain the required services levels identified in the General Plan Circulation Element.
   B.   The application shall be accompanied by a fee set by resolution of the city council sufficient to cover the cost of handling the application.
(Ord. 2024-07 § 3 (part), 2024: Ord. 2017-01 (part), 2017: prior code § 7526)

17.38.030 Lapse of conditional use permit.

   A conditional use permit shall lapse and shall become void twenty-four (24) months after the date on which it became effective, unless the conditions of the permit allowed a shorter or greater time limit, or unless prior to the expiration of twenty-four (24) months a building permit is issued by the city and construction is commenced and diligently pursued toward completion on the site that was the subject of the permit. A permit may be renewed for an additional period of one year; provided, that prior to the expiration of twenty-four (24) months from the date the permit originally became effective, an application for renewal is filed with the planning commission. The commission may grant or deny an application for renewal of a conditional use permit. In the case of a planned residential development, the recording of a final map and improvements thereto shall be deemed the same as a building permit in relation to this section. (Ord. 2017-01 (part), 2017: Ord. 2001-13 § 4 (part), 2001: prior code § 7527)

17.38.040 Revocation.

   Upon violation of any applicable provision of this title, or, if granted subject to a condition or conditions, upon failure to comply with the condition or conditions, a conditional use permit shall be suspended automatically. The planning commission shall hold a public hearing within sixty (60) days, in accordance with the procedure prescribed in Section 17.38.080, and if not satisfied that the regulation, general provision or condition is being complied with, may revoke the permit or take such action as may be necessary to insure compliance with the regulation, general provision or condition. Appeals of the decision of the planning commission may be made to the city council as provided in Section 17.38.120. (Ord. 2017-01 (part), 2017: prior code § 7528)

17.38.050 New application.

   Following the denial of a conditional use permit application or the revocation of a conditional use permit, no application for a conditional use permit for the same or substantially the same conditional use on the same or substantially the same site shall be filed within one year from the date of denial or revocation of the permit unless such denial was a denial without prejudice by the planning commission or city council.
(Ord. 2017-01 (part), 2017: prior code § 7530)

17.38.060 Conditional use permit to run with the land.

   A conditional use permit granted pursuant to the provisions of this chapter shall run with the land and shall continue to be valid upon a change of ownership of the site or structure that was the subject of the permit application subject to the provisions of Section 17.38.065. (Ord. 2017-01 (part), 2017: prior code § 7531)

17.38.065 Abandonment of conditional use permit.

   If the use for which a conditional use permit was approved is discontinued for a period of one hundred eighty (180) days, the use shall be considered abandoned and any future use of the site as a conditional use will require the approval of a new conditional use permit. (Ord. 2017-01 (part), 2017)

17.38.070 Temporary uses or structures.

   A.   Conditional use permits for temporary uses or structures may be processed as administrative matters by the city planner and/or planning division staff. However, the city planner may, at his/her discretion, refer such application to the planning commission for consideration.
   B.   The city planner and/or planning division staff is authorized to review applications and to issue such temporary permits, subject to the following conditions:
   1.   Conditional use permits granted pursuant to this section shall be for a fixed period not to exceed thirty (30) days for each temporary use not occupying a structure, including promotional enterprises, or six months for all other uses or structures.
   2.   Ingress and egress shall be limited to that designated by the planning division. Appropriate directional signing, barricades, fences or landscaping shall be provided where required. A security officer may be required for promotional events.
   3.   Off-street parking facilities shall be provided on the site of each temporary use as prescribed in Section 17.34.020.
   4.   Upon termination of the temporary permit, or abandonment of the site, the applicant shall remove all materials and equipment and restore the premises to their original condition.
   5.   Opening and closing times for promotional enterprises shall coincide with the hours of operation of the sponsoring commercial establishment. Reasonable time limits for other uses may be set by the city planner and planning division staff.
   6.   Applicants for a temporary conditional use permit shall have all applicable licenses and permits prior to issuance of a conditional use permit.
   7.   Signing for temporary uses shall be subject to the approval of the city planner.
   8.   Notwithstanding underlying zoning, temporary conditional use permits may be granted for fruit and vegetable stands on properties primarily within undeveloped agricultural areas. In reviewing applications for such stands, issues of traffic safety and land use compatibility shall be evaluated and mitigation measures and conditions may be imposed to ensure that the stands are built and are operated consistent with appropriate construction standards, vehicular access and off-street parking. All fruits and vegetables sold at such stands shall be grown by the owner/operator or purchased by said party directly from a grower/farmer.
   9.   Fruit/Vegetable stands shall be subject to site plan review.
   C.    The City Planner shall deny a temporary use permit if findings cannot be made, or conditions exist that would be injurious to existing site, improvements, land uses, surrounding development or would be detrimental to the surrounding area.
   D.   The applicant or any interested person may appeal a decision of temporary use permit to the planning commission, setting forth the reason for such appeal to the commission. Such appeal shall be filed with the city planner in writing with applicable fees, within ten (10) days after notification of such decision. The appeal shall be placed on the agenda of the commission's next regular meeting. If the appeal is filed within five (5) days of the next regular meeting of the commission, the appeal shall be placed on the agenda of the commission's second regular meeting following the filing of the appeal. The commission shall review the temporary use permit and shall uphold or revise the decision of the temporary use permit, based on the findings set forth in Section 17.38.110. The decision of the commission shall be final unless appealed to the council pursuant to Section 17.02.145.
   E.   A privately owned parcel may be granted up to six (6) temporary use permits per calendar year. (Ord. 2017-01 (part), 2017: Ord. 9605 § 30 (part), 1996: prior code § 7532)

17.38.080 Public hearing - Notice.

   A.   The planning commission shall hold at least one public hearing on each application for a conditional use permit.
   B.   Notice of the public hearing shall be given not less than ten days nor more than thirty (30) days prior to the date of the hearing by mailing a notice of the time and place of the hearing to property owners within three hundred (300) feet of the boundaries of the area occupied or to be occupied by the use that is the subject of the hearing, and by publication in a newspaper of general circulation within the city. (Ord. 2017-01 (part), 2017: prior code § 7533)

17.38.090 Investigation and report.

   The planning staff shall make an investigation of the application and shall prepare a report thereon that shall be submitted to the planning commission. The report can recommend modifications to the application as a condition of approval. (Ord. 2017-01 (part), 2017: prior code § 7534)

17.38.100 Public hearing - Procedure.

   At the public hearing the planning commission shall review the application and the statement and drawing submitted therewith and shall receive pertinent evidence concerning the proposed use and the proposed conditions under which it would be operated or maintained, particularly with respect to the findings prescribed in Section 17.38.110. The planning commission may continue a public hearing from time to time as it deems necessary. (Ord. 2017-01 (part), 2017: prior code § 7535)

17.38.110 Action by planning commission.

   A.   The planning commission may grant an application for a conditional use permit as requested or in modified form, if, on the basis of the application and the evidence submitted, the commission makes the following findings:
   1.   That the proposed location of the conditional use is in accordance with the objectives of the zoning ordinance and the purposes of the zone in which the site is located;
   2.   That the proposed location of the conditional use and the conditions under which it would be operated or maintained will not be detrimental to the public health, safety or welfare, or materially injurious to properties or improvements in the vicinity.
   B.   A conditional use permit may be revocable, may be granted for a limited time period, or may be granted subject to such conditions as the commission may prescribe. The commission may grant conditional approval for a permit subject to the effective date of a change of zone or other ordinance amendment.
   C.   The commission may deny an application for a conditional use permit. (Ord. 2017-01 (part), 2017: prior code § 7536)

17.38.120 Appeal to city council.

   The decision of the City planning commission on a conditional use permit shall be subject to the appeal provisions of Section 17.02.145. (Ord. 2017-01 (part), 2017: Ord. 2006-18 § 6, 2007: prior code § 7537)

17.38.130 Effective date of conditional use permit.

   A conditional use permit shall become effective immediately when granted or affirmed by the council, or ten days following the granting of the conditional use permit by the planning commission if no appeal has been filed. (Ord. 2017-01 (part), 2017: prior code § 7539)