Guarantees, Inspections and Off-Tract Improvements
Application Fee | Escrow Deposit | |
|---|---|---|
Subdivisions | ||
Minor (creating 1 or 2) | $500 | $1,000 |
Major Preliminary | $500 | $1,000 |
Major Final | $300 | $650 |
Informal Concept Plat | ||
Minor Plat | $100 | $200 |
Major Plat | $150 | $300 |
Site Plans | ||
Minor Plat | $500 | $1,000 |
Major Preliminary | $750 | $1,200 |
Major Final | $300 | $750 |
Informal Concept Plan | ||
Minor Plan | $150 | $300 |
Major Plan | $150 | $300 |
Appeal and Variance Application | ||
Appeals (40:55D-70a) | $400 | $800 |
Interpretation (04:55D-70b) | $400 | $00 |
Variance Hardship (40:55D-70c) or Use (40:55D-70d) | $500 + $150 per each additional variance | $1,000 |
Permit (40:55D-34 & 35) | $300 | $300 |
Signs | See Chapter 39 | |
Conditional Use | $300 | $500 |
Special Meeting at Applicant's Request | $500 | — |
Certified List of Property Owners | $0.25/name or $10 whichever is greater | |
Copy of Minutes, Transcripts, or Decisions [Ord. No. 1116 § 1] | Fees are to be charged in accordance with N.J.S.A. 47:1A-5 and are subject to change based on current legislation | |
Copies of Audio Recordings | $25 | |
Minor or Major Amendments, Site Plans or Subdivision Applications | 50% of original fee 50% of original fee | |
Request for Extension of Preliminary or Final Site Plan or Subdivision Approvals | $200 | $100 |
Request for Reapproval of Site Plan or Subdivision Applications | 50% of original fee | 50% of original fee |
In all applications for major or minor subdivisions, lot consolidations, removal or additions of easements or any other action that may require a modification to the tax map, an Administrative Tax Map Maintenance Fee shall be submitted by separate check in the amount of $100 per lot in order to update and modify the Borough of Wildwood Crest tax maps. The above fee shall be deposited in a fund for use by the Tax Assessor in order to update the tax map by the professional land surveyor or Borough Engineer on record with the Borough of Wildwood Crest. Tax maps shall be updated in January each year for the previous year. The Tax Assessor shall retain a record of tax map updates each year. [Ord. No. 1185] | ||
Total enlargement or Improvement cost\Developer's cost | = | Total tributary gallons per day\Development gallons per day |
Total project cost\Developer's cost | = | Total tributary gallons per day to new system\Total gallons per day to new system from development |
Total cost of the roadway improvement and/or extension\Developer's cost | = | Traffic\Future peak-hour traffic generated by the development |
Total enlargement or improvement cost of drainage facilities\Developer's cost | = | Total tributary cubic feet per second\Development cubic feet per second |
Guarantees, Inspections and Off-Tract Improvements
Application Fee | Escrow Deposit | |
|---|---|---|
Subdivisions | ||
Minor (creating 1 or 2) | $500 | $1,000 |
Major Preliminary | $500 | $1,000 |
Major Final | $300 | $650 |
Informal Concept Plat | ||
Minor Plat | $100 | $200 |
Major Plat | $150 | $300 |
Site Plans | ||
Minor Plat | $500 | $1,000 |
Major Preliminary | $750 | $1,200 |
Major Final | $300 | $750 |
Informal Concept Plan | ||
Minor Plan | $150 | $300 |
Major Plan | $150 | $300 |
Appeal and Variance Application | ||
Appeals (40:55D-70a) | $400 | $800 |
Interpretation (04:55D-70b) | $400 | $00 |
Variance Hardship (40:55D-70c) or Use (40:55D-70d) | $500 + $150 per each additional variance | $1,000 |
Permit (40:55D-34 & 35) | $300 | $300 |
Signs | See Chapter 39 | |
Conditional Use | $300 | $500 |
Special Meeting at Applicant's Request | $500 | — |
Certified List of Property Owners | $0.25/name or $10 whichever is greater | |
Copy of Minutes, Transcripts, or Decisions [Ord. No. 1116 § 1] | Fees are to be charged in accordance with N.J.S.A. 47:1A-5 and are subject to change based on current legislation | |
Copies of Audio Recordings | $25 | |
Minor or Major Amendments, Site Plans or Subdivision Applications | 50% of original fee 50% of original fee | |
Request for Extension of Preliminary or Final Site Plan or Subdivision Approvals | $200 | $100 |
Request for Reapproval of Site Plan or Subdivision Applications | 50% of original fee | 50% of original fee |
In all applications for major or minor subdivisions, lot consolidations, removal or additions of easements or any other action that may require a modification to the tax map, an Administrative Tax Map Maintenance Fee shall be submitted by separate check in the amount of $100 per lot in order to update and modify the Borough of Wildwood Crest tax maps. The above fee shall be deposited in a fund for use by the Tax Assessor in order to update the tax map by the professional land surveyor or Borough Engineer on record with the Borough of Wildwood Crest. Tax maps shall be updated in January each year for the previous year. The Tax Assessor shall retain a record of tax map updates each year. [Ord. No. 1185] | ||
Total enlargement or Improvement cost\Developer's cost | = | Total tributary gallons per day\Development gallons per day |
Total project cost\Developer's cost | = | Total tributary gallons per day to new system\Total gallons per day to new system from development |
Total cost of the roadway improvement and/or extension\Developer's cost | = | Traffic\Future peak-hour traffic generated by the development |
Total enlargement or improvement cost of drainage facilities\Developer's cost | = | Total tributary cubic feet per second\Development cubic feet per second |