Figure 390-1202 Review and Approval Processes | |||||||
|---|---|---|---|---|---|---|---|
Review and Approval Bodies | |||||||
Application Process | Zoning Administrator | Public Hearing (Class 2 notice) Required | Village Staff | Plan Commission | Village Board | Zoning Board of Appeals | |
Zoning Ordinance Text Amendment | RE | PC | RE | RR | A | — | |
Zoning Map Amendment | RE | PC | RE | RR | A | — | |
Site Plan Review | RE | — | RE | RR | A | — | |
Conditional Use Permit | RE | PC | RE | RR | A | — | |
Planned Development (see § 390-0709) | |||||||
Concept Plan | RE | — | RE | RR | A | — | |
General Development Plan | RE | PC | RE | RR | A | — | |
Final Development Plan | RE | — | RE | RR | A | — | |
Temporary Use Permit | RE | — | RE | RR | A | — | |
Zoning Permit | RE | — | RE | RR | A | — | |
Building Permit | A | — | — | — | — | — | |
Certificate of Compliance | RE | — | RE | RR | A | — | |
Sign Permit | A | — | — | — | — | — | |
Variance | RE | ZBA | RE | — | — | A | |
Interpretation | RE | — | RE | RR | A | — | |
Appeal | RE | ZBA | RE | — | — | A | |
Violations and Penalties | A | — | — | — | — | ||
KEY: |
|---|
PC = Plan Commission |
VB = Village Board |
ZBA = Zoning Board of Appeals |
RE = Review and Evaluate |
RR = Review and Recommend |
A = Final Action |
Procedures
Figure 390-1202 Review and Approval Processes | |||||||
|---|---|---|---|---|---|---|---|
Review and Approval Bodies | |||||||
Application Process | Zoning Administrator | Public Hearing (Class 2 notice) Required | Village Staff | Plan Commission | Village Board | Zoning Board of Appeals | |
Zoning Ordinance Text Amendment | RE | PC | RE | RR | A | — | |
Zoning Map Amendment | RE | PC | RE | RR | A | — | |
Site Plan Review | RE | — | RE | RR | A | — | |
Conditional Use Permit | RE | PC | RE | RR | A | — | |
Planned Development (see § 390-0709) | |||||||
Concept Plan | RE | — | RE | RR | A | — | |
General Development Plan | RE | PC | RE | RR | A | — | |
Final Development Plan | RE | — | RE | RR | A | — | |
Temporary Use Permit | RE | — | RE | RR | A | — | |
Zoning Permit | RE | — | RE | RR | A | — | |
Building Permit | A | — | — | — | — | — | |
Certificate of Compliance | RE | — | RE | RR | A | — | |
Sign Permit | A | — | — | — | — | — | |
Variance | RE | ZBA | RE | — | — | A | |
Interpretation | RE | — | RE | RR | A | — | |
Appeal | RE | ZBA | RE | — | — | A | |
Violations and Penalties | A | — | — | — | — | ||
KEY: |
|---|
PC = Plan Commission |
VB = Village Board |
ZBA = Zoning Board of Appeals |
RE = Review and Evaluate |
RR = Review and Recommend |
A = Final Action |