Administration and Procedure
Special Permit and/or Variances from Section 104.3.2(4) paragraph 2 shall go through formal Site Plan Review. |
Projects developing under Section 415 (Registered Marijuana Dispensaries) are required to go through formal Site Plan Review. |
In addition, the Building Commissioner may require a site plan review if he deems it necessary in order to determine zoning compliance. |
The objectives of the design review process are to: | |
1. | Preserve the natural and cultural patterns of the surrounding landscape whenever possible. |
2. | Encourage incorporation of public amenities, including, but not limited to, sidewalks, benches, and bike racks within commercial developments. Encourage clustering of buildings in large developments to retain more open space. |
3. | Building is encouraged to be of a style which complements and promotes traditional Cape Cod architectural styles and character with proper scale, proportion and roof pitch. Traditional building materials (clapboards and cedar shingles) are recommended for usage. Colors of clapboard and trim should be muted colors of traditional usage, not designed to shock or stand out. |
4. | Identify the internal parking circulation system in a manner which will reduce curb cuts, improve landscaping and traffic flow, allow for proper turning radius and parking space, encourage pedestrian uses and access, screen trash receptacles, and minimize any accessory signage. |
The Board of Appeals shall have the right to impose such reasonable conditions on the special permit as it deems appropriate. Projects shall be subject to the inclusionary zoning provisions of section 412.2. All Special Permit applications and/or Variances for this section of the Bylaw shall include the following: |