The Zoning Administrator, in reviewing all applications for new construction, substantial improvements, prefabricated buildings, placement of mobile homes and other development(s) (as defined in Article 32 of this chapter) shall obtain, review and utilize any reasonably available flood elevation data and Federal, State or other sources. If such data is obtained from the Federal Insurance Administration, such data shall be sufficient. Within areas designed as Zone A on the official floodplain map or any other area determined to be subject to flooding, the following performance standards shall be met:
A.
The lowest habitable floor elevation (to include basement) of new residential structures must be elevated or floodproofed to or above the regulatory flood elevation.
B.
New construction and substantial improvement of any nonresidential structure shall have the lowest floor (including basement), elevated above the regulatory flood elevation; or, together with attendant utility and sanitary facilities shall be constructed to meet the following requirements:
(1)
Be floodproofed so that below the base flood level, the structure is watertight with walls substantially impermeable to the passage of water;
(2)
Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy; and
(3)
Be certified by a registered professional engineer or architect that the standards of the subsection are satisfied. Such certification shall be provided to the officials as set forth in § 470-19.03B(6).
C.
Only construction materials and utility equipment that are resistant to flood damage may be used.
D.
Only construction methods and practices that will minimize flood damage may be used.
E.
All structures must be designed or anchored to prevent the flotation, collapse or lateral movement of the structure or portions of the structure due to flooding.
F.
In regards to mobile homes specific anchoring requirements are:
(1)
Over-the-top ties must be provided at each corner of the mobile home. Two additional ties per side at the intermediate locations shall be provided, except that mobile homes less than 50 feet long require only one additional tie per side.
(2)
Frame ties must be provided at each corner of the home with five additional ties per side at intermediate points, except that mobile homes less than 50 feet long require four additional ties per side.
(3)
All components of the anchoring system shall be capable of carrying a force of 4,800 pounds.
(4)
Any additions to mobile homes must be similarly anchored.
(5)
Mobile homes:
(a)
Mobile homes shall be anchored in accordance with § 470-19.04C.
(b)
For new mobile home parks and mobile home subdivisions; expansions to existing mobile home parks and mobile home subdivisions; for existing mobile home subdivisions where the repair, reconstruction or improvement of the streets, utilities and pads equals or exceeds 50% of value of the repair, reconstruction or improvement has commenced; and for mobile homes not placed in a mobile home park or mobile home subdivision, require that:
[1]
Stands or lots are elevated on compacted fill or on pilings so that the lowest floor of the mobile home will be at or above the base flood level;
[2]
Adequate surface drainage and access for a hauler are provided; and
[3]
In the instance of elevation on pilings, that:
[a]
Lots are large enough to permit steps;
[b]
Piling foundations are placed in stable soil no more than 10 feet apart; and
[c]
Reinforcement is provided for pilings more than six feet above the ground level.
(c)
No new or replacement mobile home shall be placed in a floodway.