(A) A site-specific development plan must be deemed administratively complete by the Planning Director before approval may be granted in any form.
(1) When determining administrative completeness, the Planning Director may use the regulations set forth in this title to determine if an application meets town standards.
(B) Unless otherwise specified, the application, review, and approval process for currently identified site-specific development plans shall be followed according to the processes set forth in this title.
(C) Where a procedure is not currently in effect, or until this title is later amended to include procedures, the following process is to be followed:
(1) Applications are to be submitted with the following items:
(a) A complete application form for the request; and
(b) A plat of survey of the subject property, if available, or a tax map that identifies the subject property; and
(c) A concept plan that includes the following information:
1. The proposed means of access to a public road;
2. Surrounding land uses;
4. A preliminary map and analysis of natural resources present on the subject property and surrounding property; and
5. A conceptual layout of the proposed land use, which shall be overlaid on the preliminary natural resources map, and which shall show streets, lots, parks and other facilities located to protect natural resource areas.
(2) Review, approval and appeal process.
(a) Once an application has been deemed administratively complete by the Planning Director, and fees have been received, the Planning Director shall compile a staff report (which may include the comments and recommendations of the Water Department and other affected agencies, if applicable) that reviews the application in light of all applicable requirements of this title. This report shall be forwarded to the Planning Commission.
(b) Within the 60 days of the Planning Commission’s receipt of a complete application and staff report, the Planning Commission shall review the proposed land use and act to approve, approve with conditions or deny the land use, based on whether it complies with all applicable requirements of this title.
(c) Any person with a substantial interest in the proposed land use decision of the Planning Commission or any officer or agent of the town may appeal the Planning Commission decision to the Circuit Court in Charleston County. Appellants shall file with the Court of Clerk a written petition plainly and fully setting forth how such decision is contrary to law. Such appeal shall be filed within 30 days of appellant’s actual notice of the Planning Commission's decision.
(D) Once final or conditional approval is granted for the site-specific development plan, by either the local governing body or the Planning Director, and its approval is not overturned in a Circuit Court, vested rights are established for two years from the date of final approval.
(Ord. 2026-10, passed 4-2-2026)