Guarantees
Wherever a performance guarantee is required under the terms of this Code, said guarantee shall be submitted in conformance with this Section, and made a part of the Development Agreement executed for the Development.
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
The performance guarantee shall be one of the following:
Each performance guarantee shall be in an amount not less than 125 percent of the average of three (3) cost estimates from a qualified contractor or engineer experienced in constructing or engineering the type of public improvement for which the guarantee is requested. In the event cost estimates cannot be readily obtained from three contractors or engineers, the County may accept a cost estimate from fewer than three contractors or engineers if, in the opinion of the County Engineer, the cost estimates received properly acknowledge the entire scope of work necessary to complete the public improvement and are reflective of local market costs. The guarantee, shall be posted in such a manner that any portion of the guarantee released shall require the advance written consent of the County. Any interest derived from cash guarantee accounts shall be the property of the developer.
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
The duration of the performance guarantee shall be for the applicable period of time specified for each particular type of development or activity. Said period shall begin on the date of final approval by the County.
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
At the completion of the work, or not less than thirty (30) days prior to the release date of the bond or other assurance, the developer shall submit to the Zoning Administrator a Certificate of Completion. Following receipt of the certificate, the Zoning Administrator shall make a preliminary inspection and shall submit a report to the Chairman of the County Commission, setting forth the conditions of such facilities. The Zoning Administrator shall set the date and time of a staff meeting to review the status of the Development and to receive comments and recommendations from staff regarding the adequacy of the improvements and compliance with County Standards, Codes, and Ordinances. If the condition of said improvements or activities for which the guarantee is required are found to be satisfactory, and all liens are paid, the Chairman or their designated representative shall act to either:
If the condition of material or workmanship shows unusual depreciation or does not comply with the acceptable standards of durability, or if any outstanding liens are not paid, or the terms of the guarantee have not been satisfied, the matter shall be referred to the Cow1ty Commission and, in accordance with the provisions of 7.5, the Commission may declare the developer in default.
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
Where, in the opinion of the County Commission, a developer fails or neglects to satisfactorily install the required improvements or make required corrections, or to pay all liens on connection with said improvements, or otherwise fails in carrying out the activity for which a financial guarantee was required, the Commission, after a public hearing with due notice on the matter may:
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
Where the guarantee is required to insure the timely installation of improvements, the County may authorize a partial release(s) of the performance guarantee in accordance with the following schedule:
Percent of Work Complete
Percent of Total Guarantee Amount Eligible for Release (Less Retainage, see 7.7)
25
25
50
45
75
70
100 (upon satisfactory final inspection)
100
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
A retainage of not less than twenty-five percent (25%) of the total amount of the guarantee shall be retained by the County for a period of not less than one year following the date of final acceptance of the improvements by the County. Such retainage shall be a guarantee of the durability of all improvements. If during the one year period the durability of said improvements is found to be satisfactory, said retainage may be released following the procedure outlined under Section 7-4. If, however, during said period the condition, or material or workmanship, of the improvement(s) fail or show unusual depreciation, or if it becomes evident that certain work was not completed, or that said improvements do not otherwise comply with accepted standards of durability, said condition shall be corrected by the developer. If the corrections are not made within a reasonable time, the County Commission, in accordance with Section 7-5, may declare such person in default and use the retainage to defray the cost of any required work.
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021
HISTORY:
Ord. 453, 5/1/2012
Ord. 515, 5/1/2019
Ord. 525, 12/4/2019
Ord. 545, 3/17/2021