Standards for Uses Subject to Special Permit Procedure
Lot Size (square feet) | Maximum Permitted Gross Floor Area for Customer Convenience Center (square feet) | |
|---|---|---|
30,000 | 750 | |
60,000 | 1,500 | |
90,000 | 2,250 |
Green Building Element/Infrastructure Practice | Points |
|---|---|
Any combination of stormwater practices that attenuate peak flows to a 500-year storm as defined in § 294-6 | 75 |
Permeable pavers, porous concrete, rain gardens not included in the stormwater calculations for Chapter 294 compliance or the 500-year storm calculation for the purpose of achieving green building elements/infrastructure points | 15 |
Solar panels (minimum 10 panels) | 15 |
Exceeding state energy code | 15 |
Biophilic design elements as defined in § 342-3 | 15 |
Building heated by 100% electric systems | 15 |
Bicycle parking (1 space per 10 units, and 1 outlet per 2 spaces for e-bike charging) | 10 |
Electric vehicle charging station (minimum 1 charger per 10 units) | 10 |
Rainwater detention and reuse system or blue roof | 10 |
Zoning District | Maximum FAR or Coverage - 5 or more Units | Percentage Required |
|---|---|---|
C-1 | 0.8 | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |
C-2 | 2.0 | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |
TOD | 0.8 (up to 1.1 if other TOD incentives are utilized) | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |
Standards for Uses Subject to Special Permit Procedure
Lot Size (square feet) | Maximum Permitted Gross Floor Area for Customer Convenience Center (square feet) | |
|---|---|---|
30,000 | 750 | |
60,000 | 1,500 | |
90,000 | 2,250 |
Green Building Element/Infrastructure Practice | Points |
|---|---|
Any combination of stormwater practices that attenuate peak flows to a 500-year storm as defined in § 294-6 | 75 |
Permeable pavers, porous concrete, rain gardens not included in the stormwater calculations for Chapter 294 compliance or the 500-year storm calculation for the purpose of achieving green building elements/infrastructure points | 15 |
Solar panels (minimum 10 panels) | 15 |
Exceeding state energy code | 15 |
Biophilic design elements as defined in § 342-3 | 15 |
Building heated by 100% electric systems | 15 |
Bicycle parking (1 space per 10 units, and 1 outlet per 2 spaces for e-bike charging) | 10 |
Electric vehicle charging station (minimum 1 charger per 10 units) | 10 |
Rainwater detention and reuse system or blue roof | 10 |
Zoning District | Maximum FAR or Coverage - 5 or more Units | Percentage Required |
|---|---|---|
C-1 | 0.8 | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |
C-2 | 2.0 | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |
TOD | 0.8 (up to 1.1 if other TOD incentives are utilized) | 5 to 10 units: 1 FAHU 11 to 20 units: 2 FAHU 21 or more units: 10% of units rounded up to the nearest whole number |