Zoneomics Logo
search icon

Lyndhurst City Zoning Code

§ 21-20.13

Collection Procedures.

[Ord. #2678, § 21-20.13]
a. 
Upon the granting of a preliminary, final or other applicable approval, for a development, the applicable approving authority shall direct its staff to notify the construction official responsible for the issuance of a building permit.
b. 
For nonresidential developments only, the developer shall also be provided with a copy of Form N-RDF "State of New Jersey Non-Residential Development Certification/Exemption" to be completed as per the instructions provided. The developer of a nonresidential development shall complete Form N-RDF as per the instructions provided. The construction official shall verify the information submitted by the nonresidential developer as per the instructions provided in the Form N-RDF. The tax assessor shall verify exemptions and prepare estimated and final assessments as per the instructions provided in Form N-RDF.
c. 
The construction official responsible for the issuance of a building permit shall notify the local tax assessor of the issuance of the first building permit for a development which is subject to a development fee.
d. 
Within 90 days of receipt of that notice, the municipal tax assessor, based on the plans filed, shall provide an estimate of the equalized assessed value of the development.
e. 
The construction official responsible for the issuance of a final certificate of occupancy notifies the local assessor of any and all requests for the scheduling of a final inspection on property which is subject to a development fee.
f. 
Within 10 business days of a request for the scheduling of a final inspection, the municipal assessor shall confirm or modify the previously estimated equalized assessed value of the improvements of the development; calculate the development fee; and thereafter notify the developer of the amount of the fee.
g. 
Should the Township of Lyndhurst fail to determine or notify the developer of the amount of the development fee within 10 business days of the request for final inspection, the developer may estimate the amount due and pay that estimated amount consistent with the dispute process set forth in subsection b of section 37 of P.L. 2008, c. 46 (C. 40:55D-8.6). The payment of monies by a developer pursuant to this section shall have no effect on the developer's obligation to provide affordable housing where no development fee is due.
h. 
The developer shall pay 100% of the calculated development fee amount prior to the municipal issuance of a final certificate of occupancy for the subject property.
i. 
Appeal of Development Fees.
1. 
A developer may challenge residential development fees imposed by filing a challenge with the county board of taxation. Pending a review and determination by the board, collected fees shall be placed in an interest bearing escrow account by the Township of Lyndhurst. Appeals from a determination of the board may be made to the tax court in accordance with the provisions of the State Tax Uniform Procedure Law, R.S. 54:48-1 et seq., within 90 days after the date of such determination. Interest earned on amounts escrowed shall be credited to the prevailing party.
2. 
A developer may challenge nonresidential development fees imposed by filing a challenge with the director of the division of taxation. Pending a review and determination by the director, which shall be made within 45 days of receipt of the challenge, collected fees shall be placed in an interest bearing escrow account by the Township of Lyndhurst. Appeals from a determination of the director may be made to the tax court in accordance with the provisions of the State Tax Uniform Procedure Law, R.S. 54:48-1 et seq., within 90 days after the date of such determination. Interest earned on amounts escrowed shall be credited to the prevailing party.