[Ord. No. 2067]
The conditions of site plan approval shall be transmitted to the construction official by the municipal agency, and it shall be their responsibility to see that all conditions of site plan approval are met.
All site plan details, including building construction, parking areas, landscaping and screening shall be commenced within one year from the date of issuance of a building permit. No certificate of occupancy shall be issued until all site plan approval requirements have been fully met.
Preliminary and final site plan approval shall expire as provided by N.J.S.A. 40:55D-49 and 52, unless the applicant seeks and is granted an extension of time. The applicant whose site plan approval has expired may resubmit a site plan.